Item 3. LEGAL PROCEEDINGS

36K characters. Original on sec.gov ·

Item 3. LEGAL PROCEEDINGS

| --- | --- |

The Company is involved in certain claims, suits and legal proceedings in the normal course of business. The Company has accrued for litigation and claims where it is probable that a liability has been incurred and the amount of loss can be reasonably estimated. The Company believes, based upon information it currently possesses and taking into account established reserves for estimated liabilities and its insurance coverage, that the ultimate outcome of these proceedings and actions is unlikely to have a material adverse effect on the Company’s financial statements. It is reasonably possible, however, that some matters could be decided unfavorably to the Company and could require the Company to pay damages or make expenditures in amounts that could be material but cannot be estimated as of December 31, 2012.

In 1989, Centrais Elétricas Brasileiras S.A. (“Eletrobrás”) filed suit in the Fifth District Court in the State of Rio de Janeiro (“FDC”) against Eletropaulo Eletricidade de São Paulo S.A. (“EEDSP”) relating to the methodology for calculating monetary adjustments under the parties’ financing agreement. In April 1999, the FDC found for Eletrobrás and in September 2001, Eletrobrás initiated an execution suit in the FDC to collect approximately R$1.3 billion ($626 million) from Eletropaulo (as estimated by Eletropaulo) and a lesser amount from an unrelated company, Companhia de Transmissão de Energia Elétrica Paulista (“CTEEP”) (Eletropaulo and CTEEP were spun off from EEDSP pursuant to its privatization in 1998). In November 2002, the FDC rejected Eletropaulo’s defenses in the execution suit. Eletropaulo appealed and in September 2003, the Appellate Court of the State of Rio de Janeiro (“AC”) ruled that Eletropaulo was not a proper party to the litigation because any alleged liability had been transferred to CTEEP pursuant to the privatization. In June 2006, the Superior Court of Justice (“SCJ”) reversed the Appellate Court’s decision and remanded the case to the FDC for further proceedings, holding that Eletropaulo’s liability, if any, should be determined by the FDC. Eletropaulo’s subsequent appeals were dismissed. In February 2010, the FDC appointed an accounting expert to determine the amount of the alleged debt and the responsibility for its payment in light of the privatization, in accordance with the methodology proposed by Eletrobrás. Eletropaulo filed an interlocutory appeal with the AC asserting that the expert was required to determine the issues in accordance with the methodology proposed by Eletropaulo, and that Eletropaulo should be entitled to take discovery and present arguments on the issues to be determined by the expert. In April 2010, the AC issued a decision agreeing with Eletropaulo’s arguments and directed the FDC to proceed accordingly. However, in December 2012, the FDC disregarded the AC’s decision that the parties were entitled to full discovery and an expert appraisal of the issues prior to the resolution of the case and, instead, issued a decision finding Eletropaulo liable for the debt. The AC subsequently granted Eletropaulo’s request to suspend the execution suit in the FDC and thereafter annulled the FDC’s decision. The case will now return to the FDC for proceedings in accordance with the AC’s April 2010 decision. If the FDC again finds Eletropaulo

Table of Contents

liable for the debt, after the amount of the alleged debt is determined, Eletrobrás will be entitled to resume the execution suit in the FDC. If Eletrobrás does so, Eletropaulo will be required to provide security for its alleged liability. In that case, if Eletrobrás requests the seizure of such security and the FDC grants such request, Eletropaulo’s results of operations may be materially adversely affected and, in turn the Company’s results of operations could be materially adversely affected. In addition, in February 2008, CTEEP filed a lawsuit in the FDC against Eletrobrás and Eletropaulo seeking a declaration that CTEEP is not liable for any debt under the financing agreement. In December 2012, the FDC dismissed the lawsuit. Eletropaulo believes it has meritorious defenses to the claims asserted against it and will defend itself vigorously in these proceedings; however, there can be no assurances that it will be successful in its efforts.

In September 1996, a public civil action was asserted against Eletropaulo and Associação Desportiva Cultural Eletropaulo (the “Associação”) relating to alleged environmental damage caused by construction of the Associação near Guarapiranga Reservoir. The initial decision that was upheld by the Appellate Court of the State of São Paulo in 2006 found that Eletropaulo should repair the alleged environmental damage by demolishing certain construction and reforesting the area, and either sponsor an environmental project which would cost approximately R$1 million ($488 thousand) as of December 31, 2012, or pay an indemnification amount of approximately R$15 million ($7 million). Eletropaulo has appealed this decision to the Supreme Court and the Supreme Court affirmed the decision of the Appellate Court. Following the Supreme Court’s decision, the case is being remanded to the court of first instance for further proceedings and to monitor compliance by the defendants with the terms of the decision.

In August 2001, the Grid Corporation of Orissa, India, now Gridco Ltd. (“Gridco”), filed a petition against the Central Electricity Supply Company of Orissa Ltd. (“CESCO”), an affiliate of the Company, with the Orissa Electricity Regulatory Commission (“OERC”), alleging that CESCO had defaulted on its obligations as an OERC-licensed distribution company, that CESCO management abandoned the management of CESCO, and seeking interim measures of protection, including the appointment of an administrator to manage CESCO. Gridco, a state-owned entity, is the sole wholesale energy provider to CESCO. Pursuant to the OERC’s August 2001 order, the management of CESCO was replaced with a government administrator who was appointed by the OERC. The OERC later held that the Company and other CESCO shareholders were not necessary or proper parties to the OERC proceeding. In August 2004, the OERC issued a notice to CESCO, the Company and others giving the recipients of the notice until November 2004 to show cause why CESCO’s distribution license should not be revoked. In response, CESCO submitted a business plan to the OERC. In February 2005, the OERC issued an order rejecting the proposed business plan. The order also stated that the CESCO distribution license would be revoked if an acceptable business plan for CESCO was not submitted to and approved by the OERC prior to March 31, 2005. In its April 2, 2005 order, the OERC revoked the CESCO distribution license. CESCO has filed an appeal against the April 2, 2005 OERC order and that appeal remains pending in the Indian courts. In addition, Gridco asserted that a comfort letter issued by the Company in connection with the Company’s indirect investment in CESCO obligates the Company to provide additional financial support to cover all of CESCO’s financial obligations to Gridco. In December 2001, Gridco served a notice to arbitrate pursuant to the Indian Arbitration and Conciliation Act of 1996 on the Company, AES Orissa Distribution Private Limited (“AES ODPL”), and Jyoti Structures (“Jyoti”) pursuant to the terms of the CESCO Shareholders Agreement between Gridco, the Company, AES ODPL, Jyoti and CESCO (the “CESCO arbitration”). In the arbitration, Gridco appeared to be seeking approximately $189 million in damages, plus undisclosed penalties and interest, but a detailed alleged damage analysis was not filed by Gridco. The Company counterclaimed against Gridco for damages. In June 2007, a 2-to-1 majority of the arbitral tribunal rendered its award rejecting Gridco’s claims and holding that none of the respondents, the Company, AES ODPL, or Jyoti, had any liability to Gridco. The respondents’ counterclaims were also rejected. In September 2007, Gridco filed a challenge of the arbitration award with the local Indian court. In June 2010, a 2-to-1 majority of the arbitral tribunal awarded the Company some of its costs relating to the arbitration. In August 2010, Gridco filed a challenge of the cost award with the local Indian court. The Company believes that it has meritorious defenses to the claims asserted against it and will defend itself vigorously in these proceedings; however, there can be no assurances that it will be successful in its efforts.

Table of Contents

In early 2002, Gridco made an application to the OERC requesting that the OERC initiate proceedings regarding the terms of OPGC’s existing PPA with Gridco. In response, OPGC filed a petition in the Indian courts to block any such OERC proceedings. In early 2005, the Orissa High Court upheld the OERC’s jurisdiction to initiate such proceedings as requested by Gridco. OPGC appealed that High Court’s decision to the Supreme Court and sought stays of both the High Court’s decision and the underlying OERC proceedings regarding the PPA’s terms. In April 2005, the Supreme Court granted OPGC’s requests and ordered stays of the High Court’s decision and the OERC proceedings with respect to the PPA’s terms. The matter has been awaiting further hearing. However, in December 2012, the parties executed a settlement agreement amending the PPA and resolving the dispute. The amended PPA is subject to regulatory approval.

In March 2003, the office of the Federal Public Prosecutor for the State of São Paulo, Brazil (“MPF”) notified Eletropaulo that it had commenced an inquiry related to the BNDES financings provided to AES Elpa and AES Transgás and the rationing loan provided to Eletropaulo, changes in the control of Eletropaulo, sales of assets by Eletropaulo and the quality of service provided by Eletropaulo to its customers, and requested various documents from Eletropaulo relating to these matters. In July 2004, the MPF filed a public civil lawsuit in the Federal Court of São Paulo (“FSCP”) alleging that BNDES violated Law 8429/92 (the Administrative Misconduct Act) and BNDES’s internal rules by: (1) approving the AES Elpa and AES Transgás loans; (2) extending the payment terms on the AES Elpa and AES Transgás loans; (3) authorizing the sale of Eletropaulo’s preferred shares at a stock-market auction; (4) accepting Eletropaulo’s preferred shares to secure the loan provided to Eletropaulo; and (5) allowing the restructurings of Light Serviços de Eletricidade S.A. and Eletropaulo. The MPF also named AES Elpa and AES Transgás as defendants in the lawsuit because they allegedly benefited from BNDES’s alleged violations. In May 2006, the FCSP ruled that the MPF could pursue its claims based on the first, second, and fourth alleged violations noted above. The MPF subsequently filed an interlocutory appeal with the Federal Court of Appeals (“FCA”) seeking to require the FCSP to consider all five alleged violations. Also, in July 2006, AES Elpa and AES Transgás filed an interlocutory appeal with the FCA, which was subsequently consolidated with the MPF’s interlocutory appeal, seeking a transfer of venue and to enjoin the FCSP from considering any of the alleged violations. In June 2009, the FCA granted the injunction sought by AES Elpa and AES Transgás and transferred the case to the Federal Court of Rio de Janeiro. In May 2010, the MPF filed an appeal with the Superior Court of Justice (“SCJ”) challenging the transfer. In November 2012, the SCJ ruled that the lawsuit must be returned to the FCSP. AES Elpa and AES Brasiliana (the successor of AES Transgás) believe they have meritorious defenses to the allegations asserted against them and will defend themselves vigorously in these proceedings; however, there can be no assurances that they will be successful in their efforts.

AES Florestal, Ltd. (“Florestal”), had been operating a pole factory and had other assets, including a wooded area known as “Horto Renner,” in the State of Rio Grande do Sul, Brazil (collectively, “Property”). Florestal had been under the control of AES Sul (“Sul”) since October 1997, when Sul was created pursuant to a privatization by the Government of the State of Rio Grande do Sul. After it came under the control of Sul, Florestal performed an environmental audit of the entire operational cycle at the pole factory. The audit discovered 200 barrels of solid creosote waste and other contaminants at the pole factory. The audit concluded that the prior operator of the pole factory, Companhia Estadual de Energia Elétrica (“CEEE”), had been using those contaminants to treat the poles that were manufactured at the factory. Sul and Florestal subsequently took the initiative of communicating with Brazilian authorities, as well as CEEE, about the adoption of containment and remediation measures. The Public Attorney’s Office has initiated a civil inquiry (Civil Inquiry n. 24/05) to investigate potential civil liability and has requested that the police station of Triunfo institute a police investigation (IP number 1041/05) to investigate potential criminal liability regarding the contamination at the pole factory. The parties filed defenses in response to the civil inquiry. The Public Attorney’s Office then requested an injunction which the judge rejected on September 26, 2008, and the Public Attorney’s office no longer has a right to appeal the decision. The environmental agency (“FEPAM”) has also started a procedure (Procedure n. 088200567/059) to analyze the measures that shall be taken to contain and remediate the contamination. Also, in March 2000, Sul filed suit against CEEE in the 2nd Court of Public Treasure of Porto Alegre seeking to register in Sul’s name the Property that it acquired through the privatization but that remained

Table of Contents

registered in CEEE’s name. During those proceedings, AES subsequently waived its claim to re-register the Property and asserted a claim to recover the amounts paid for the Property. That claim is pending. In November 2005, the 7th Court of Public Treasure of Porto Alegre ruled that the Property must be returned to CEEE. CEEE has had sole possession of Horto Renner since September 2006 and of the rest of the Property since April 2006. In February 2008, Sul and CEEE signed a “Technical Cooperation Protocol” pursuant to which they requested a new deadline from FEPAM in order to present a proposal. In March 2008, the State Prosecution office filed a Class Action against AES Florestal, AES Sul and CEEE, requiring an injunction for the removal of the alleged sources of contamination and the payment of an indemnity in the amount of R$6 million ($3 million). The injunction was rejected. The above-referenced proposal to FEPAM with respect to containing and remediating the contamination was delivered on April 8, 2008. FEPAM responded by indicating that the parties should undertake the first step of the proposal which would be to retain a contractor. In its response, Sul indicated that such step should be undertaken by CEEE as the relevant environmental events resulted from CEEE’s operations. In October 2011, the State Prosecution Office presented a new request to the court of Triunfo for an injunction against Florestal, Sul and CEEE for the removal of the alleged sources of contamination and remediation, and the court granted the injunction against CEEE but did not grant injunctive relief against Florestal or Sul. CEEE appealed such decision, and the State of Rio Grande do Sul Court of Appeals upheld the decision. As required by the injunction, CEEE has started the removal and disposal of the contaminants, which is ongoing, and Sul is not at risk to bear any of such remediation costs, which are estimated to be approximately R$14.7 million ($7 million). In November 2012, the inspections performed by the court expert and supervised by Sul confirmed that CEEE is fulfilling the injunction by removing the contaminants. The case is in the evidentiary stage awaiting the production of the court’s expert opinion on several matters, including which of the parties had utilized the products found in the area.

In January 2004, the Company received notice of a “Formulation of Charges” filed against the Company by the Superintendence of Electricity of the Dominican Republic. In the “Formulation of Charges,” the Superintendence asserts that the existence of three generation companies (Empresa Generadora de Electricidad Itabo, S.A. (“Itabo”), Dominican Power Partners, and AES Andres BV) and one distribution company (Empresa Distribuidora de Electricidad del Este, S.A. (“Este”)) in the Dominican Republic, violates certain cross-ownership restrictions contained in the General Electricity Law of the Dominican Republic. In February 2004, the Company filed in the First Instance Court of the National District of the Dominican Republic an action seeking injunctive relief based on several constitutional due process violations contained in the “Formulation of Charges” (“Constitutional Injunction”). In February 2004, the Court granted the Constitutional Injunction and ordered the immediate cessation of any effects of the “Formulation of Charges,” and the enactment by the Superintendence of Electricity of a special procedure to prosecute alleged antitrust complaints under the General Electricity Law. In March 2004, the Superintendence of Electricity appealed the Court’s decision. In July 2004, the Company divested any interest in Este. The Superintendence of Electricity’s appeal is pending. The Company believes it has meritorious defenses to the claims asserted against it and will defend itself vigorously in these proceedings; however, there can be no assurances that it will be successful in its efforts.

In February 2008, the Native Village of Kivalina and the City of Kivalina, Alaska, filed a complaint in the U.S. District Court for the Northern District of California against the Company and numerous unrelated companies, claiming that the defendants’ alleged GHG emissions have contributed to alleged global warming which, in turn, allegedly has led to the erosion of the plaintiffs’ alleged land. The plaintiffs assert nuisance and concert of action claims against the Company and the other defendants, and a conspiracy claim against a subset of the other defendants. The plaintiffs seek to recover relocation costs, indicated in the complaint to be from $95 million to $400 million, and other unspecified damages from the defendants. The Company filed a motion to dismiss the case, which the District Court granted in October 2009. The plaintiffs appealed to the U.S. Court of Appeals for the Ninth Circuit. In September 2012, the Ninth Circuit affirmed the District Court’s decision. The plaintiffs’ subsequent petition for en banc review was denied by the Ninth Circuit. The Company believes it has meritorious defenses to the claims asserted against it and will defend itself vigorously in these proceedings; however, there can be no assurances that it will be successful in its efforts.

Table of Contents

In March 2009, AES Uruguaiana Empreendimentos S.A. (“AESU”) in Brazil initiated arbitration in the International Chamber of Commerce (“ICC”) against YPF S.A. (“YPF”) seeking damages and other relief relating to YPF’s breach of the parties’ gas supply agreement (“GSA”). Thereafter, in April 2009, YPF initiated arbitration in the ICC against AESU and two unrelated parties, Companhia de Gas do Esado do Rio Grande do Sul and Transportador de Gas del Mercosur S.A. (“TGM”), claiming that AESU wrongfully terminated the GSA and caused the termination of a transportation agreement (“TA”) between YPF and TGM (“YPF Arbitration”). YPF seeks an unspecified amount of damages from AESU, a declaration that YPF’s performance was excused under the GSA due to certain alleged force majeure events, or, in the alternative, a declaration that the GSA and the TA should be terminated without a finding of liability against YPF because of the allegedly onerous obligations imposed on YPF by those agreements. In addition, in the YPF Arbitration, TGM asserts that if it is determined that AESU is responsible for the termination of the GSA, AESU is liable for TGM’s alleged losses, including losses under the TA. In April 2011, the arbitrations were consolidated into a single proceeding. The hearing on liability issues took place in December 2011, and thereafter the arbitrators took those issues under consideration. AESU believes it has meritorious claims and defenses and will assert them vigorously; however, there can be no assurances that it will be successful in its efforts.

In April 2009, the Antimonopoly Agency in Kazakhstan initiated an investigation of the power sales of Ust-Kamenogorsk HPP (“UK HPP”) and Shulbinsk HPP, hydroelectric plants under AES concession (collectively, the “Hydros”), for the period from January through February 2009. The Antimonopoly Agency determined that the Hydros abused their market position and charged monopolistically high prices for power from January through February 2009. The Agency sought an order from the administrative court requiring UK HPP to pay an administrative fine of approximately KZT 120 million ($1 million) and to disgorge profits for the period at issue, estimated by the Antimonopoly Agency to be approximately KZT 440 million ($3 million). No fines or damages have been paid to date, however, as the proceedings in the administrative court have been suspended due to the initiation of related criminal proceedings against officials of the Hydros. In the course of criminal proceedings, the financial police have expanded the periods at issue to the entirety of 2009 in the case of UK HPP and from January through October 2009 in the case of Shulbinsk HPP, and sought increased damages of KZT 1.2 billion ($8 million) from UK HPP and KZT 1.3 billion ($9 million) from Shulbinsk HPP. The Hydros believe they have meritorious defenses and will assert them vigorously in these proceedings; however, there can be no assurances that they will be successful in their efforts.

In October 2009, AES Mérida III, S. de R.L. de C.V. (AES Mérida), one of our businesses in Mexico, initiated arbitration against its fuel supplier and electricity offtaker, Comisión Federal de Electricidad (“CFE”), seeking a declaration that CFE breached the parties’ power purchase agreement (“PPA”) by supplying gas that did not comply with the PPA’s specifications. Alternatively, AES Mérida requested a declaration that the supply of such gas by CFE is a force majeure event under the PPA. CFE disputed the claims. Although it did not assert counterclaims, in its closing brief CFE asserted that it is entitled to a partial refund of the capacity charge payments that it made for power generated with the out-of-specification gas. In July 2012, the arbitral Tribunal issued an award in AES Mérida’s favor. In December 2012, CFE initiated an action in Mexican court seeking to nullify the award. AES Mérida believes it has meritorious defenses in that action; however, there can be no assurances that it will be successful.

In October 2009, IPL received a Notice of Violation (“NOV”) and Finding of Violation from the EPA pursuant to the CAA Section 113(a). The NOV alleges violations of the CAA at IPL’s three primarily coal-fired electric generating facilities dating back to 1986. The alleged violations primarily pertain to the Prevention of Significant Deterioration and nonattainment New Source Review (“NSR”) requirements under the CAA. Since receiving the letter, IPL management has met with EPA staff regarding possible resolutions of the NOV. At this time, we cannot predict the ultimate resolution of this matter. However, settlements and litigated outcomes of similar cases have required companies to pay civil penalties, install additional pollution control technology on coal-fired electric generating units, retire existing generating units, and invest in additional environmental projects. A similar outcome in this case could have a material impact to IPL and could, in turn, have a material

Table of Contents

impact on the Company. IPL would seek recovery of any operating or capital expenditures related to air pollution control technology to reduce regulated air emissions; however, there can be no assurances that it would be successful in that regard.

In November 2009, April 2010, December 2010, April 2011, June 2011, August 2011, and November 2011, substantially similar personal injury lawsuits were filed by a total of 49 residents and decedent estates in the Dominican Republic against the Company, AES Atlantis, Inc., AES Puerto Rico, LP, AES Puerto Rico, Inc., and AES Puerto Rico Services, Inc., in the Superior Court for the State of Delaware. In each lawsuit, the plaintiffs allege that the coal combustion byproducts of AES Puerto Rico’s power plant were illegally placed in the Dominican Republic from October 2003 through March 2004 and subsequently caused the plaintiffs’ birth defects, other personal injuries, and/or deaths. The plaintiffs did not quantify their alleged damages, but generally alleged that they are entitled to compensatory and punitive damages and the Company is not able to estimate damages, if any, at this time. The AES defendants moved for partial dismissal of both the November 2009 and April 2010 lawsuits on various grounds. In July 2011, the Superior Court dismissed the plaintiffs’ international law and punitive damages claims, but held that the plaintiffs had stated intentional tort, negligence, and strict liability claims under Dominican law, which the Superior Court found governed the lawsuits. The Superior Court granted the plaintiffs leave to amend their complaints in accordance with its decision, and in September 2011, the plaintiffs in the November 2009 and April 2010 lawsuits did so. The AES defendants again moved for partial dismissal of those amended complaints, and in May 2012, the Superior Court ruled on the motion in the November 2009 lawsuit, dismissing the plaintiff’s claims for future medical monitoring expenses but declining to dismiss their claims under Dominican Republic Law 64-00. The Superior Court has not yet ruled on the motion for partial dismissal of the April 2010 lawsuit. The AES defendants filed an answer to the November 2009 lawsuit in June 2012. The Superior Court has stayed the remaining six lawsuits, as well as any subsequently filed similar lawsuits. The Superior Court has also ordered that, for the present, discovery will proceed only in the November 2009 lawsuit and will be limited to causation and exposure issues. The AES defendants believe they have meritorious defenses and will defend themselves vigorously; however, there can be no assurances that they will be successful in their efforts.

On December 21, 2010, AES-3C Maritza East 1 EOOD, which owns a 670 MW lignite-fired power plant in Bulgaria, made the first in a series of demands on the performance bond securing the construction Contractor’s obligations under the parties’ EPC Contract. The Contractor failed to complete the plant on schedule. The total amount demanded by Maritza under the performance bond was approximately €155 million. The Contractor obtained an injunction from a lower French court purportedly preventing the issuing bank from honoring the bond demands. However, the Versailles Court of Appeal canceled the injunction in July 2011, and therefore the issuing bank paid the bond demands in full. In addition, in December 2010, the Contractor stopped commissioning of the power plant’s two units, allegedly because of the purported characteristics of the lignite supplied to it for commissioning. In January 2011, the Contractor initiated arbitration on its lignite claim, seeking an extension of time to complete the power plant, an increase to the contract price, and other relief, including in relation to the bond demands. The Contractor later added claims relating to the alleged unavailability of the grid during commissioning. Maritza rejected the Contractor’s claims and asserted counterclaims for delay liquidated damages and other relief relating to the Contractor’s failure to complete the power plant and other breaches of the EPC Contract. Maritza also terminated the EPC Contract for cause and asserted arbitration claims against the Contractor relating to the termination. The Contractor asserted counterclaims relating to the termination. The Contractor is seeking approximately €240 million ($317 million) in the arbitration, unspecified damages for alleged injury to reputation, and other relief. The arbitral hearing on the merits was scheduled for March 2013, but recently was rescheduled by the arbitrators to a date to be determined. Maritza believes it has meritorious claims and defenses and will assert them vigorously in these proceedings; however, there can be no assurances that it will be successful in its efforts.

On February 11, 2011 AES Eletropaulo received a notice of violation from São Paulo State’s Environmental Authorities for allegedly destroying 0.32119 hectares of native vegetation at the Conservation Park of Serra do Mar (“Park”), without previous authorization or license. The notice of violation asserted a fine of approximately

Table of Contents

R$1 million ($510,370) and the suspension of AES Eletropaulo activities in the Park. As a response to this administrative procedure before the São Paulo State Environmental Authorities (“São Paulo EA”), AES Eletropaulo timely presented its defense on February 28, 2011 seeking to vacate the notice of violation or reduce the fine. In December 2011, the São Paulo EA declined to vacate the notice of violation but recognized the possibility of 40% reduction in the fine if AES Eletropaulo agrees to recover the affected area with additional vegetation. AES Eletropaulo has not appealed the decision and is now discussing the terms of a possible settlement with the São Paulo EA, including a plan to recover the affected area by primarily planting additional trees. In March 2012, the State of São Paulo Prosecutor’s Office of São Bernando do Campo initiated a Civil Proceeding to review the compliance by AES Eletropaulo with the terms of any possible settlement. AES Eletropaulo has had several meetings and field inspections to settle the details of the recovery project. AES Eletropaulo is currently awaiting the approval of the recovery project by the Park Administrator.

In May 2011, a putative class action was filed in the Mississippi federal court against the Company and numerous unrelated companies. The lawsuit alleges that greenhouse gas emissions contributed to alleged global warming which, in turn, allegedly increased the destructive capacity of Hurricane Katrina. The plaintiffs assert claims for public and private nuisance, trespass, negligence, and declaratory judgment. The plaintiffs seek damages relating to loss of property, loss of business, clean-up costs, personal injuries and death, but do not quantify their alleged damages. The Company is unable to estimate the alleged damages at this time. These and other plaintiffs previously brought a substantially similar lawsuit in the federal court but failed to obtain relief. In October 2011, the Company and other defendants filed motions to dismiss the lawsuit. In March 2012, the federal court granted the motion and dismissed the lawsuit. The plaintiffs appealed to the U.S. Court of Appeals for the Fifth Circuit. The appeal is fully briefed. The Company believes it has meritorious defenses and will defend itself vigorously in this lawsuit; however, there can be no assurances that it will be successful in its efforts.

In February 2011, a consumer protection group, S.O.S. Consumidores (“SOSC”), filed a lawsuit in the State of Săo Paulo Federal Court against Eletropaulo and all other distribution companies in the State of Săo Paulo, claiming that the distribution companies had overcharged customers for electricity. SOSC asserts that the distribution companies’ tariffs had been incorrectly calculated by the Brazilian Regulatory Agency (“ANEEL”). ANEEL corrected the alleged error in May 2010. There are separate proceedings against ANEEL to determine whether the tariffs had been properly calculated. SOSC has moved for an injunction requiring tariffs to be corrected from the effective dates of the relevant concession contracts. Electropaulo has opposed that request on the ground that it did not wrongfully collect amounts from its customers, since its tariff was calculated in accordance with the concession contract with the Federal Government and ANEEL’s rules. If it does not prevail in the lawsuit, Eletropaulo estimates that its liability to customers could be approximately R$855 million ($417 million). Electropaulo believes it has meritorious defenses and will defend itself vigorously in this lawsuit; however, there can be no assurances that it will be successful in its efforts.

In June 2011, the São Paulo Municipal Tax Authority (the “Municipality”) filed 60 tax assessments in São Paulo administrative court against Eletropaulo, seeking approximately R$1.2 billion ($586 million) in services tax (“ISS”) that allegedly had not been collected on revenues for services rendered by Eletropaulo. Eletropaulo estimates that, with interest, the amount at issue has increased to approximately R$2 billion ($1 billion). Eletropaulo has challenged the assessments on the ground that the revenues at issue were not subject to ISS. Eletropaulo believes it has meritorious defenses to the assessments and will defend itself vigorously in these proceedings; however, there can be no assurances that it will be successful in its efforts.

In August 2012, Fondo Patrimonial de las Empresas Reformadas (“FONPER”) (the Dominican instrumentality that holds the Dominican Republic’s shares in Empresa Generadora de Electricidad Itabo, S.A. (“Itabo”)) filed a criminal complaint against certain current and former employees of AES. The criminal proceedings include a related civil component initiated against Coastal Itabo, Ltd. (“Coastal”) (the AES affiliate shareholder of Itabo) and New Caribbean Investment, S.A. (“NCI”) (the AES affiliate that manages Itabo). FONPER asserts claims relating to the alleged mismanagement of Itabo and seeks approximately $270 million in

Table of Contents

damages. The Dominican District Attorney has accepted the criminal complaint and is investigating the allegations set forth therein. In September 2012, one of the individual defendants responded to the criminal complaint, denying the charges and seeking an immediate dismissal of same. Further, in August 2012, Coastal and NCI initiated an international arbitration proceeding against FONPER and the Dominican Republic, seeking a declaration that Coastal and NCI have acted both lawfully and in accordance with the relevant contracts with FONPER and the Dominican Republic in relation to the management of Itabo. Coastal and NCI also seek a declaration that the criminal complaint is a breach of the relevant contracts between the parties, including the obligation to arbitrate disputes. Coastal and NCI further seek damages from FONPER and the Dominican Republic resulting from their breach of contract. FONPER and the Dominican Republic have denied the claims. The AES defendants believe they have meritorious claims and defenses, which they will assert vigorously; however there can be no assurance that they will be successful in their efforts.