Item 4. CONTROLS AND PROCEDURES

7K characters. Original on sec.gov · Markdown

Item 4. CONTROLS AND PROCEDURES

Evaluation of Disclosure Controls and Procedures

American Water maintains disclosure controls and procedures that are designed to ensure that information required to be disclosed in its reports filed or submitted under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the SEC’s rules and forms, and that such information is accumulated and communicated to management, including the Chief Executive Officer and the Chief Financial Officer, to allow timely decisions regarding required disclosure. In designing and evaluating the disclosure controls and procedures, management recognizes that any controls and procedures, no matter how well designed and operated, can provide only reasonable assurance of achieving the desired control objective.

The Company’s management, including the Chief Executive Officer and the Chief Financial Officer, conducted an evaluation of the effectiveness of its disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) of the Exchange Act) as of September 30, 2023.

Based on that evaluation, the Chief Executive Officer and the Chief Financial Officer have concluded that, as of September 30, 2023, the Company’s disclosure controls and procedures were effective at a reasonable level of assurance.

Changes in Internal Control over Financial Reporting

The Company concluded that there have been no changes in internal control over financial reporting that occurred during the three months ended September 30, 2023, that have materially affected, or are reasonably likely to materially affect, the Company’s internal control over financial reporting.

PART II. OTHER INFORMATION

ITEM 1. LEGAL PROCEEDINGS

The following information updates and amends the information provided in the Company’s Form 10-K in Item 3—Legal Proceedings, and in our Quarterly Report on Form 10-Q for the quarter ended June 30, 2023. Capitalized terms used but not otherwise defined herein have the meanings set forth in the Company’s Form 10-K. In accordance with the SEC’s disclosure rules, the Company has elected to disclose environmental proceedings involving the Company and a governmental authority if the amount of potential monetary sanctions, exclusive of interest and costs, that the Company reasonably believes will result from such proceeding is $1 million or more.

Alternative Water Supply in Lieu of Carmel River Diversions

Monterey Peninsula Water Supply Project

Desalination Plant Development Permit

On September 8, 2023, the court of appeal issued its opinion reversing the trial court’s determination in favor of MCWD as to the statement of overriding considerations and rejecting MCWD’s appeals on all of its claims that the Monterey County Superior Court had denied. On September 25, 2023, MCWD filed a petition for rehearing in the court of appeal, which was denied on October 4, 2023.

Proposed Acquisition of Monterey System Assets — Local Area Formation Commission Litigation

Over the written and oral objections of Cal Am, at a hearing held on October 10, 2023, the MPWMD adopted a resolution of necessity to authorize it to file an eminent domain lawsuit with respect to the Monterey system assets. If such a lawsuit is filed, Cal Am would seek dismissal or take other action to assert what it believes would be meritorious defenses against the MPWMD’s claims. While the Company cannot currently predict the outcome of any such lawsuit, the Company believes that, given existing legal precedent related to similar attempts by public agencies in California to take over water systems, Cal Am should be able to defend itself successfully against an eminent domain lawsuit by the MPWMD.

On October 25, 2023, the Monterey County Superior Court issued an Intended Statement of Decision to issue a writ of mandate directing LAFCO to vacate and set aside its original denial of the MPWMD’s application to serve as a retail water provider (in conjunction with its effort to acquire the Monterey water system assets) and to reconsider the application in compliance with all applicable law. The court held that LAFCO incorrectly applied two statutory standards and noted a lack of sufficient evidence to support certain of LAFCO’s factual findings. Once the writ of mandate is issued, the LAFCO denial will be nullified and LAFCO will be required to hold another hearing on the MPWMD’s application. Cal Am is evaluating potential actions relative to the writ of mandate, including filing an appeal or other challenge and/or making suitable presentations at a subsequent LAFCO rehearing.

Dunbar, West Virginia Water Main Break Class Action Litigation

On August 21, 2023, the Circuit Court set a trial date of September 9, 2024, to determine certain liability issues but not to consider class-wide or punitive damages. The Company and WVAWC believe that WVAWC has valid, meritorious defenses to the claims raised in this class action complaint, and WVAWC will continue to vigorously defend itself against these allegations.

Chattanooga, Tennessee Class Action Litigation

On September 21, 2023, the Circuit Court held a hearing on the Tennessee Plaintiffs’ motion for reconsideration of the court’s January 12, 2023, oral ruling denying their motion for class certification. The court upheld its prior ruling but gave the Tennessee Plaintiffs the option to file an amended class definition. On October 12, 2023, the Tennessee Plaintiffs filed an amended class definition seeking certification of a business customer-only class. An order denying the original proposed class and addressing the proposed amended class has not been entered by the court and remains pending.

PFAS Multi-District Litigation

Several of the Company’s utility subsidiaries are parties to a multi-district litigation (the “MDL”) lawsuit, which commenced on December 7, 2018, in U.S. District Court for the District of South Carolina, against manufacturers of certain PFAS for damages, contribution and reimbursement of costs incurred and continuing to be incurred to address the presence of such PFAS in public water supply systems owned and operated by these utility subsidiaries and throughout their service areas. In August 2023, a potential class action settlement involving defendants The Chemours Company, Corteva, Inc. and DuPont de Nemours, Inc. to resolve claims brought in the MDL against them by public water systems, and a similar class action settlement with defendant 3M Company, received preliminary approval from the MDL court. The Company is monitoring ongoing litigation and settlement activity with manufacturers of PFAS in this proceeding for potential impacts to the various claims asserted by the Company, including deadlines set in the MDL of December 4, 2023 and December 11, 2023 for water utilities, including the Company, to opt out of the settlements.