Evaluation of Disclosure Controls and Procedures

American Water maintains disclosure controls and procedures that are designed to ensure that information required to be disclosed in its reports filed or submitted under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the SEC’s rules and forms, and that such information is accumulated and communicated to management, including the Chief Executive Officer and the Chief Financial Officer, to allow timely decisions regarding required disclosure. In designing and evaluating the disclosure controls and procedures, management recognizes that any controls and procedures, no matter how well designed and operated, can provide only reasonable assurance of achieving the desired control objective.

The Company’s management, including the Chief Executive Officer and the Chief Financial Officer, conducted an evaluation of the effectiveness of its disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) of the Exchange Act) as of September 30, 2025.

Based on that evaluation, the Chief Executive Officer and the Chief Financial Officer have concluded that, as of September 30, 2025, the Company’s disclosure controls and procedures were effective at a reasonable level of assurance.

Changes in Internal Control over Financial Reporting

The Company concluded that there have been no changes in internal control over financial reporting that occurred during the three months ended September 30, 2025, that have materially affected, or are reasonably likely to materially affect, the Company’s internal control over financial reporting.

PART II. OTHER INFORMATION

ITEM 1. LEGAL PROCEEDINGS

The following information updates and amends the information provided in the Company’s Form 10-K in Item 3—Legal Proceedings, and in the Company’s Quarterly Report on Form 10-Q for the quarter ended June 30, 2025 in Part II, Item 1—Legal Proceedings. Capitalized terms used but not otherwise defined herein have the meanings set forth in the Company’s Form 10-K and Form 10-Q. In accordance with the SEC’s disclosure rules, the Company has elected to disclose environmental proceedings involving the Company and a governmental authority if the amount of potential monetary sanctions, exclusive of interest and costs, that the Company reasonably believes will result from such proceeding is $1 million or more.

Alternative Water Supply in Lieu of Carmel River Diversions

Monterey Peninsula Water Supply Project

CPUC Final Approval of Water Supply Project

On May 9, 2025, the CPUC issued a proposed decision in the Phase 2 that is focusing on updated supply and demand estimates for the Water Supply Project, finding that without the Water Supply Project, projected demand will outstrip supply by approximately 2,500 acre-feet per year for 2050. On August 14, 2025, the CPUC approved a final decision updating the supply and demand estimates for the Water Supply Project, finding that the projected demand will outstrip supply by approximately 2,600 acre-feet per year for 2050. On September 17, 2025, the City, MCWD and the MPWMD filed applications for rehearing of the final decision. On September 22, 2025, these parties also filed a motion to stay the final decision. On October 9, 2025, the CPUC issued a factual correction to the final decision to find that the projected demand will outstrip supply by approximately 2,500 acre-feet per year for 2050 and did not rule on the other motions.

Coastal Development Permit Application

On May 12, 2025, the court entered its final decision denying the joint petition for writ of mandate by the City, MCWD and the MPWMD in full. On July 24, 2025, a notice of appeal was filed in this matter.

Proposed Acquisition of Monterey System Assets — Potential Condemnation

MPWMD Condemnation Action

On August 20, 2025, Cal Am filed a motion for summary judgment as to the MPWMD’s condemnation action, alleging that without LAFCO approval, the MPWMD does not have legal authority to pursue eminent domain. On the same date, the MPWMD filed a motion for summary adjudication of the same issue, arguing that LAFCO approval is not required to proceed with its condemnation action. Both motions are scheduled for court hearing on December 12, 2025.

Dunbar, West Virginia Class Action Litigation Settlement

On September 11, 2025, the Circuit Court held its final fairness hearing and issued an order on September 12, 2025, granting final approval of the Dunbar Settlement. Under the terms of the approved Dunbar Settlement, WVAWC has not admitted, and will not admit, any fault or liability for any of the allegations made by the Jeffries plaintiffs. The maximum pre-tax amount of the Dunbar Settlement is approximately $18 million, and the final amount of the Company’s and WVAWC’s contributions to the Dunbar Settlement is expected to be $5 million, with the remainder being contributed by certain of the Company’s general liability insurance carriers. The actual total amount to be paid to claimants through the Dunbar Settlement will depend upon the claims approved through the claims process, and WVAWC has paid approximately $2 million as of September 30, 2025. The deadline for claims submissions was August 25, 2025, and the settlement administrator is evaluating claim submissions to identify compensable claims. The Company intends to fund its and WVAWC’s contributions to the Dunbar Settlement through existing sources of liquidity.

Mountaineer Gas Company Main Break

The West Virginia Business Court has set a new trial date of August 10, 2026, for trial in Mountaineer Gas Company v. West Virginia-American Water Company.

PFAS Multi-District Litigation

As of September 30, 2025, the Company has received settlement payments from defendant 3M Company totaling $135 million, net of legal fees and administrative costs. The Company intends to seek regulatory approval from its respective PUCs to apply the net proceeds for the benefit of customers, where permissible. As of September 30, 2025, these funds are being held in a law firm escrow account and are awaiting distribution to the Company’s utility subsidiaries that are parties to the MDL after receiving approval from the applicable PUCs. The Company anticipates that, during the remainder of 2025, it may receive one or more additional settlement payments from the defendants named above.

The Company has also become aware of a number of substantially similar personal injury short-form complaints that have been filed in the MDL naming, in addition to various other water providers and manufacturers, certain Company utility subsidiaries as defendants. In October 2025, all MDL personal injury complaints that the Company had been made aware of were dismissed by the plaintiffs without prejudice.