Dominion Energy 10-Q 2023-09-30

Filed 2023-11-08. 6 sections, 433K characters. Original on sec.gov · Markdown · JSON

Cover and table of contents

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

FORM 10-Q

(Mark one)

☒QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934

For the quarterly period ended September 30, 2023

or

☐TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934

For the transition period from to

Commission File NumberExact name of registrants as specified in their charters, address of principal executive offices and registrants’ telephone numberI.R.S. Employer Identification Number
001-08489DOMINION ENERGY, INC.54-1229715
000-55337VIRGINIA ELECTRIC AND POWER COMPANY54-0418825
120 Tredegar Street Richmond**,** Virginia 23219 (804) 819-2284

State or other jurisdiction of incorporation or organization of the registrants: Virginia

Securities registered pursuant to Section 12(b) of the Act:

RegistrantTrading SymbolTitle of Each ClassName of Each Exchange on Which Registered
DOMINION ENERGY, INC.DCommon Stock, no par valueNew York Stock Exchange

Indicate by check mark whether the registrant (1) has filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file such reports), and (2) has been subject to such filing requirements for the past 90 days.

Dominion Energy, Inc. Yes ☒ No ☐ Virginia Electric and Power Company Yes ☒ No ☐

Indicate by check mark whether the registrant has submitted electronically every Interactive Data File required to be submitted pursuant to Rule 405 of Regulation S-T (§232.405 of this chapter) during the preceding 12 months (or for such shorter period that the registrant was required to submit such files).

Dominion Energy, Inc. Yes ☒ No ☐ Virginia Electric and Power Company Yes ☒ No ☐

Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer, a non-accelerated filer, a smaller reporting company or an emerging growth company. See the definitions of “large accelerated filer,” “accelerated filer,” “non-accelerated filer,” “smaller reporting company,” and "emerging growth company" in Rule 12b-2 of the Exchange Act.

Dominion Energy, Inc.

Large accelerated filer☒Accelerated filer☐Emerging growth company☐
Non-accelerated filer☐Smaller reporting company☐

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. ☐

Virginia Electric and Power Company

Large accelerated filer☐Accelerated filer☐Emerging growth company☐
Non-accelerated filer☒Smaller reporting company☐

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. ☐

Indicate by check mark whether the registrant is a shell company (as defined in Rule 12b-2 of the Exchange Act).

Dominion Energy, Inc. Yes ☐ No ☒ Virginia Electric and Power Company Yes ☐ No ☒

At November 2, 2023, the latest practicable date for determination, Dominion Energy, Inc. had 836,796,771 shares of common stock outstanding and Virginia Electric and Power Company had 314,178 shares of common stock outstanding. Dominion Energy, Inc. is the sole holder of Virginia Electric and Power Company’s common stock.

This combined Form 10-Q represents separate filings by Dominion Energy, Inc. and Virginia Electric and Power Company. Information contained herein relating to an individual registrant is filed by that registrant on its own behalf. Virginia Electric and Power Company makes no representation as to the information relating to Dominion Energy, Inc.’s other operations.

VIRGINIA ELECTRIC AND POWER COMPANY MEETS THE CONDITIONS SET FORTH IN GENERAL INSTRUCTION H(1)(a) AND (b) OF FORM 10-Q AND IS FILING THIS FORM 10-Q UNDER THE REDUCED DISCLOSURE FORMAT.

COMBINED INDEX

Page Number
Glossary of Terms3
PART I. Financial Information
Item 1.Financial Statements9
Item 2.Management’s Discussion and Analysis of Financial Condition and Results of Operations71
Item 3.Quantitative and Qualitative Disclosures About Market Risk89
Item 4.Controls and Procedures90
PART II. Other Information
Item 1.Legal Proceedings91
Item 1A.Risk Factors91
Item 2.Unregistered Sales of Equity Securities and Use of Proceeds91
Item 5.Other Information92
Item 6.Exhibits93

GLOSSARY OF TERMS

The following abbreviations or acronyms used in this Form 10-Q are defined below:

Abbreviation or AcronymDefinition
2017 Tax Reform ActAn Act to Provide for Reconciliation Pursuant to Titles II and V of the Concurrent Resolution on the Budget for Fiscal Year 2018 (previously known as The Tax Cuts and Jobs Act) enacted on December 22, 2017
2019 Equity UnitsDominion Energy’s 2019 Series A Equity Units issued in June 2019, initially in the form of 2019 Series A Corporate Units, which consisted of a stock purchase contract and a 1/10 interest in a share of the Series A Preferred Stock
2021 Triennial ReviewVirginia Commission review of Virginia Power’s earned return on base rate generation and distribution services for the four successive 12-month test periods beginning January 1, 2017 and ending December 31, 2020
2023 Biennial ReviewVirginia Commission review of Virginia Power’s earned return on base rate generation and distribution services for the two successive 12-month test periods beginning January 1, 2021 and ending December 31, 2022 and prospective rate base setting for the succeeding annual periods beginning January 1, 2024 and ending December 31, 2025
2025 Biennial ReviewFuture Virginia Commission review of Virginia Power’s earned return on base rate generation and distribution services for the two successive 12-month test periods beginning January 1, 2023 and ending December 31, 2024 and prospective rate base setting for the succeeding annual periods beginning January 1, 2026 and ending December 31, 2027
ACE RuleAffordable Clean Energy Rule
AFUDCAllowance for funds used during construction
AMIAdvanced Metering Infrastructure
AOCIAccumulated other comprehensive income (loss)
AROAsset retirement obligation
Atlantic Coast PipelineAtlantic Coast Pipeline, LLC, a limited liability company owned by Dominion Energy and Duke Energy
Atlantic Coast Pipeline ProjectA previously proposed approximately 600-mile natural gas pipeline running from West Virginia through Virginia to North Carolina which would have been owned by Dominion Energy and Duke Energy
bcfBillion cubic feet
Bear GardenA 622 MW combined-cycle, natural gas-fired power station in Buckingham County, Virginia
BHEThe legal entity, Berkshire Hathaway Energy Company, one or more of its consolidated subsidiaries (including Eastern Energy Gas Holdings, LLC, Northeast Midstream Partners, LP and Cove Point effective November 2020), or the entirety of Berkshire Hathaway Energy Company and its consolidated subsidiaries
CAAClean Air Act
CCRCoal combustion residual
CCROCustomer credit reinvestment offset
CEOChief Executive Officer
CEPCapital Expenditure Program, as established by House Bill 95, Ohio legislation enacted in 2011, deployed by East Ohio to recover certain costs associated with capital investment
CERCLAComprehensive Environmental Response, Compensation and Liability Act of 1980, also known as Superfund
CFIUSThe Committee on Foreign Investment in the U.S.
CFOChief Financial Officer
CO2Carbon dioxide
Colonial Trail WestA 142 MW utility-scale solar power station located in Surry County, Virginia
CompaniesDominion Energy and Virginia Power, collectively
Contracted EnergyContracted Energy operating segment, formerly known as the Contracted Assets operating segment
Cooling degree daysUnits measuring the extent to which the average daily temperature is greater than 65 degrees Fahrenheit, or 75 degrees Fahrenheit in DESC’s service territory, calculated as the difference between 65 or 75 degrees, as applicable, and the average temperature for that day
Cove PointCove Point LNG, LP (formerly known as Dominion Energy Cove Point LNG, LP)
CPCNCertificate of Public Convenience and Necessity
CVOW Commercial ProjectA proposed 2.6 GW wind generation facility 27 miles off the coast of Virginia Beach, Virginia in federal waters adjacent to the CVOW Pilot Project and associated interconnection facilities in and around Virginia Beach, Virginia
CVOW Pilot ProjectA 12 MW wind generation facility 27 miles off the coast of Virginia Beach, Virginia in federal waters
CWAClean Water Act
DECP HoldingsThe legal entity DECP Holdings, Inc., which holds Dominion Energy's noncontrolling interest in Cove Point
DEQPSMountainWest Pipeline Services, Inc. (formerly known as Dominion Energy Questar Pipeline Services, Inc.)
DESDominion Energy Services, Inc.
DESCThe legal entity, Dominion Energy South Carolina, Inc., one or more of its consolidated entities or operating segment, or the entirety of Dominion Energy South Carolina, Inc. and its consolidated entities
DGIDominion Generation, Inc.
DOEU.S. Department of Energy
Dominion EnergyThe legal entity, Dominion Energy, Inc., one or more of its consolidated subsidiaries (other than Virginia Power) or operating segments, or the entirety of Dominion Energy, Inc. and its consolidated subsidiaries
Dominion Energy Direct®A dividend reinvestment and open enrollment direct stock purchase plan
Dominion Energy Questar PipelineThe legal entity, MountainWest Pipeline, LLC (formerly known as Dominion Energy Questar Pipeline, LLC), one or more of its consolidated subsidiaries (including its 50% noncontrolling interest in White River Hub, LLC), or the entirety of Dominion Energy Questar Pipeline, LLC and its consolidated subsidiaries
Dominion Energy South CarolinaDominion Energy South Carolina operating segment
Dominion Energy VirginiaDominion Energy Virginia operating segment
Dominion PrivatizationDominion Utility Privatization, LLC, a joint venture between Dominion Energy and Patriot
DSMDemand-side management
DthDekatherm
Duke EnergyThe legal entity, Duke Energy Corporation, one or more of its consolidated subsidiaries, or the entirety of Duke Energy Corporation and its consolidated subsidiaries
East OhioThe East Ohio Gas Company, doing business as Dominion Energy Ohio
East Ohio TransactionThe proposed sale by Dominion Energy to Enbridge of all issued and outstanding capital stock in Dominion Energy Questar Corporation and its consolidated subsidiaries, which following a proposed reorganization will include East Ohio and Dominion Energy Gas Distribution, LLC, pursuant to a purchase and sale agreement entered into on September 5, 2023
EnbridgeThe legal entity, Enbridge Inc., one or more of its consolidated subsidiaries (including Enbridge Elephant Holdings, LLC, Enbridge Parrot Holdings, LLC, and Enbridge Quail Holdings, LLC), or the entirety of Enbridge Inc. and its consolidated subsidiaries
EnergySolutionsEnergySolutions, LLC
EPAU.S. Environmental Protection Agency
EPSEarnings per common share
FCCFederal Communications Commission
FERCFederal Energy Regulatory Commission
FTRsFinancial transmission rights
GAAPU.S. generally accepted accounting principles
Gas DistributionGas Distribution operating segment
GENCOSouth Carolina Generating Company, Inc.
GHGGreenhouse gas
Greensville CountyA 1,629 MW combined-cycle, natural gas-fired power station in Greensville County, Virginia
GTSAVirginia Grid Transformation and Security Act of 2018
GWGigawatt
Heating degree daysUnits measuring the extent to which the average daily temperature is less than 65 degrees Fahrenheit, or 60 degrees Fahrenheit in DESC’s service territory, calculated as the difference between 65 or 60 degrees, as applicable, and the average temperature for that day
HopeHope Gas, Inc., doing business as Dominion Energy West Virginia through August 2022
ISOIndependent system operator
Jones ActThe Coastwise Merchandise Statute (commonly known as the Jones Act) 46 U.S.C. §55102 regulating U.S. maritime commerce
KewauneeKewaunee nuclear power station
kVKilovolt
LNGLiquefied natural gas
MD&AManagement’s Discussion and Analysis of Financial Condition and Results of Operations
MGDMillion gallons per day
MillstoneMillstone nuclear power station
MWMegawatt
MWhMegawatt hour
NAVNet asset value
NND ProjectV.C. Summer Units 2 and 3 nuclear development project under which DESC and Santee Cooper undertook to construct two Westinghouse AP1000 Advanced Passive Safety nuclear units in Jenkinsville, South Carolina
North AnnaNorth Anna nuclear power station
North Carolina CommissionNorth Carolina Utilities Commission
NOXNitrogen oxide
NRCU.S. Nuclear Regulatory Commission
Ohio CommissionPublic Utilities Commission of Ohio
Order 1000Order issued by FERC adopting requirements for electric transmission planning, cost allocation and development
ozone seasonThe period May 1st through September 30th, as determined on a federal level
PatriotPatriot Utility Privatizations, LLC, a joint venture between Foundation Infrastructure Partners, LLC and John Hancock Life Insurance Company (U.S.A.) and affiliates
PFASPer- and polyfluorinated substances, a group of widely used chemicals that break down very slowly over time in the environment
PIPPPercentage of Income Payment Plan deployed by East Ohio
PIRPipeline Infrastructure Replacement program deployed by East Ohio
PJMPJM Interconnection, LLC
PSDPrevention of significant deterioration
PSNCPublic Service Company of North Carolina, Incorporated, doing business as Dominion Energy North Carolina
PSNC TransactionThe proposed sale by Dominion Energy to Enbridge of all of its membership interests in Fall North Carolina Holdco LLC and its consolidated subsidiaries, which following a proposed reorganization will include PSNC, pursuant to a purchase and sale agreement entered into on September 5, 2023
Q-Pipe GroupCollectively, Dominion Energy Questar Pipeline, DEQPS and MountainWest Energy Holding Company, LLC (formerly known as QPC Holding Company, LLC and its subsidiary MountainWest Southern Trails Pipeline Company (formerly known as Questar Southern Trails Pipeline Company))
Questar GasQuestar Gas Company, doing business as Dominion Energy Utah, Dominion Energy Wyoming and Dominion Energy Idaho
Questar Gas TransactionThe proposed sale by Dominion Energy to Enbridge of all of its membership interests in Fall West Holdco LLC and its consolidated subsidiaries, which following a proposed reorganization will include Questar Gas, Wexpro, Wexpro II Company, Wexpro Development Company, Dominion Energy Wexpro Services Company, Questar InfoComm Inc. and Dominion Gas Projects Company, LLC, pursuant to a purchase and sale agreement entered into on September 5, 2023
Regulation ActLegislation effective July 1, 2007, that amended the Virginia Electric Utility Restructuring Act and fuel factor statute, which legislation is also known as the Virginia Electric Utility Regulation Act, as amended in 2015, 2018 and 2023
RGGIRegional Greenhouse Gas Initiative
Rider CCRA rate adjustment clause associated with the recovery of costs related to the removal of CCR at certain power stations
Rider CEA rate adjustment clause associated with the recovery of costs related to certain renewable generation, energy storage and related transmission facilities in Virginia as well as certain small-scale distributed generation projects and related transmission facilities
Rider DA rate mechanism which allows PSNC to recover from customers all prudently incurred gas costs and the related portion of uncollectible expenses as well as losses on negotiated gas and transportation sales
Rider EA rate adjustment clause associated with the recovery of costs related to certain capital projects at Virginia Power's electric generating stations to comply with federal and state environmental laws and regulations
Rider GTA rate adjustment clause associated with the recovery of costs associated with electric distribution grid transformation projects that the Virginia Commission has approved as authorized by the GTSA
Rider GVA rate adjustment clause associated with the recovery of costs related to Greensville County
Rider OSWA rate adjustment clause associated with costs incurred to construct, own and operate the CVOW Commercial Project
Rider PPAA rate adjustment clause associated with the recovery of costs associated with power purchase agreements for the energy, capacity, ancillary services and renewable energy credits owned by third parties
Rider RA rate adjustment clause associated with the recovery of costs related to Bear Garden
Rider RBBA rate adjustment clause associated with the recovery of costs related to installation of broadband capacity in certain unserved rural areas
Rider RGGIA rate adjustment clause associated with the recovery of costs related to the purchase of allowances through the RGGI market-based trading program for CO2
Rider RPSA rate adjustment clause associated with the recovery of costs related to the mandatory renewable portfolio standard program established by the VCEA
Rider SA rate adjustment clause associated with the recovery of costs related to the Virginia City Hybrid Energy Center
Rider SNAA rate adjustment clause associated with costs relating to the preparation of the applications for subsequent license renewal to the NRC to extend the operating licenses of Surry and North Anna and related projects
Rider T1A rate adjustment clause to recover the difference between revenues produced from transmission rates included in base rates, and the new total revenue requirement developed annually for the rate years effective September 1
Rider UA rate adjustment clause associated with the recovery of costs of new underground distribution facilities
Rider US-3A rate adjustment clause associated with the recovery of costs related to Colonial Trail West and Spring Grove 1
Rider US-4A rate adjustment clause associated with the recovery of costs related to Sadler Solar
Rider WA rate adjustment clause associated with the recovery of costs related to Warren County
ROEReturn on equity
RTORegional transmission organization
Sadler SolarA 100 MW utility-scale solar power station located in Greensville County, Virginia
Santee CooperSouth Carolina Public Service Authority
SCANAThe legal entity, SCANA Corporation, one or more of its consolidated subsidiaries, or the entirety of SCANA Corporation and its consolidated subsidiaries
SCANA CombinationDominion Energy’s acquisition of SCANA completed on January 1, 2019 pursuant to the terms of the agreement and plan of merger entered on January 2, 2018 between Dominion Energy and SCANA
SCANA Merger Approval OrderFinal order issued by the South Carolina Commission on December 21, 2018 setting forth its approval of the SCANA Combination
SCDORSouth Carolina Department of Revenue
SECU.S. Securities and Exchange Commission
SEEMSoutheast Energy Exchange Market
Series A Preferred StockDominion Energy’s Series A Cumulative Perpetual Convertible Preferred Stock, without par value, with a liquidation preference of $1,000 per share (previously designated the 1.75% Series A Cumulative Perpetual Convertible Preferred Stock)
Series B Preferred StockDominion Energy’s 4.65% Series B Fixed-Rate Cumulative Redeemable Perpetual Preferred Stock, without par value, with a liquidation preference of $1,000 per share
Series C Preferred StockDominion Energy’s 4.35% Series C Fixed-Rate Cumulative Redeemable Perpetual Preferred Stock, without par value, with a liquidation preference of $1,000 per share
South Carolina CommissionPublic Service Commission of South Carolina
Southwest GasThe legal entity, Southwest Gas Holdings, Inc., one or more of its consolidated subsidiaries, or the entirety of Southwest Gas Holdings, Inc. and its consolidated subsidiaries
Spring Grove 1A 98 MW utility-scale solar power station located in Surry County, Virginia
Spruce PowerThe legal entity, Spruce Power Holding Corporation, one or more of its consolidated subsidiaries, or the entirety of Spruce Power Holding Corporation and its consolidated subsidiaries
Standard & Poor’sStandard & Poor’s Ratings Services, a division of S&P Global Inc.
SummerV.C. Summer nuclear power station
SurrySurry nuclear power station
UEXUncollectible Expense Rider deployed by East Ohio
Utah CommissionUtah Public Service Commission
VCEAVirginia Clean Economy Act of March 2020
VEBAVoluntary Employees’ Beneficiary Association
VIEVariable interest entity
Virginia City Hybrid Energy CenterA 610 MW baseload carbon-capture compatible, clean coal powered electric generation facility in Wise County, Virginia
Virginia CommissionVirginia State Corporation Commission
Virginia PowerThe legal entity, Virginia Electric and Power Company, one or more of its consolidated subsidiaries or operating segment, or the entirety of Virginia Electric and Power Company and its consolidated subsidiaries
Warren CountyA 1,349 MW combined-cycle, natural gas-fired power station in Warren County, Virginia
WexproThe legal entity, Wexpro Company, one or more of its consolidated subsidiaries, or the entirety of Wexpro Company and its consolidated subsidiaries
Wisconsin CommissionPublic Service Commission of Wisconsin
WP&LWisconsin Power and Light Company, a subsidiary of Alliant Energy Corporation
WPSCWisconsin Public Service Corporation, a subsidiary of WEC Energy Group
WranglerWrangler Retail Gas Holdings, LLC, a partnership between Dominion Energy (through March 2022) and Interstate Gas Supply, Inc.

PART I. FINANCI****AL INFORMATION

Item 1. FINANCIAL STATEMENTS

DOMINION ENERGY, INC.

CONSOLIDATED STATEMENTS OF INCOME

(Unaudited)

Three Months Ended September 30,Nine Months Ended September 30,
2023202220232022
(millions, except per share amounts)
Operating Revenue$3,810$3,963$10,859$10,135
Operating Expenses
Electric fuel and other energy-related purchases1,0491,2173,0102,625
Purchased electric capacity19164245
Purchased gas4091212331
Other operations and maintenance8488492,3652,589
Depreciation, depletion and amortization6636301,8841,832
Other taxes162172517531
Impairment of assets and other charges (benefits)**(**6)20136425
Losses (gains) on sales of assets—(27)**(**23)581
Total operating expenses2,7752,9688,1438,959
Income from operations1,0359952,7161,176
Other income (expense)5661646(181)
Interest and related charges1923601,066673
Income from continuing operations including noncontrolling interests before income tax expense8996962,296322
Income tax expense1827043261
Net Income From Continuing Operations7176261,864261
Net Income (Loss) From Discontinued Operations**(1)****(**554)152**(**105)775
Net Income Including Noncontrolling Interests1637781,7591,036
Noncontrolling Interests————
Net Income Attributable to Dominion Energy$163$778$1,759$1,036
Amounts attributable to Dominion Energy
Net income from continuing operations$717$626$1,864$261
Net income (loss) from discontinued operations**(**554)152**(**105)775
Net income attributable to Dominion Energy$163$778$1,759$1,036
EPS - Basic
Net income from continuing operations$0.83$0.73$2.16$0.23
Net income (loss) from discontinued operations**(**0.66)0.18**(**0.13)0.95
Net income attributable to Dominion Energy$0.17$0.91$2.03$1.18
EPS - Diluted
Net income from continuing operations$0.83$0.73$2.16$0.23
Net income (loss) from discontinued operations**(**0.66)0.18**(**0.13)0.94
Net income attributable to Dominion Energy$0.17$0.91$2.03$1.17

(1)

*Includes income tax expense of $*1.2 *billion and $53 million for the three months ended September 30, 2023 and 2022, respectively, and $*1.3 billion and $185 million for the nine months ended September 30, 2023 and 2022, respectively.

The accompanying notes are an integral part of Dominion Energy’s Consolidated Financial Statements.

DOMINION ENERGY, INC.

CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME

(Unaudited)

Three Months Ended September 30,Nine Months Ended September 30,
2023202220232022
(millions)
Net income including noncontrolling interests$163$778$1,759$1,036
Other comprehensive income (loss), net of taxes:
Net deferred gains (losses) on derivatives-hedging activities(1)19101664
Changes in unrealized net gains (losses) on investment securities(2)**(**22)(27)**(**6)(116)
Changes in net unrecognized pension and other postretirement benefit costs(3)———30
Amounts reclassified to net income (loss):
Net derivative (gains) losses-hedging activities(4)8122433
Net realized (gains) losses on investment securities(5)21113
Net pension and other postretirement benefit costs (credits)(6)**(**8)26**(**31)59
Net earnings from equity method investees(7)3—3—
Changes in other comprehensive income from equity method investees(8)**(**1)——1
Total other comprehensive income122784
Comprehensive income including noncontrolling interests1648001,7661,120
Comprehensive income attributable to noncontrolling interests————
Comprehensive income attributable to Dominion Energy$164$800$1,766$1,120

(1) Net of $**(6) million and $**(4) million tax for the three months ended September 30, 2023 and 2022, respectively, and net of $**(5) million and $**(22) million tax for the nine months ended September 30, 2023 and 2022*, respectively.*

(2) *Net of $*6 *million and $*9 *million tax for the three months ended September 30, 2023 and 2022, respectively, and net of $*2 million and $37 million tax for the nine months ended September 30, 2023 and 2022, respectively.

(3) Net of $— million and $— million tax for the three months ended September 30, 2023 and 2022, respectively, and net of $— million and $(8) million tax for the nine months ended September 30, 2023 and 2022*, respectively.*

(4) Net of $**(3) million and $**(4) million tax for the three months ended September 30, 2023 and 2022, respectively, and net of $**(8)

Showing the first 8K of 296K characters. Open the full section

Item 2. MANAGEMENT’S DISCUSSION AND ANALYSIS

OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

MD&A discusses Dominion Energy’s results of operations and general financial condition and Virginia Power’s results of operations. MD&A should be read in conjunction with the Companies’ Consolidated Financial Statements. Virginia Power meets the conditions to file under the reduced disclosure format, and therefore has omitted certain sections of MD&A.

Contents of MD&A

MD&A consists of the following information:

Forward-Looking Statements—Dominion Energy and Virginia Power

Accounting Matters—Dominion Energy

Results of Operations—Dominion Energy and Virginia Power

Segment Results of Operations—Dominion Energy

Outlook—Dominion Energy

Liquidity and Capital Resources—Dominion Energy

Future Issues and Other Matters—Dominion Energy

Forward-Looking Statements

This report contains statements concerning the Companies’ expectations, plans, objectives, future financial performance and other statements that are not historical facts. These statements are “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995. In most cases, the reader can identify these forward-looking statements by such words as “anticipate,” “estimate,” “forecast,” “expect,” “believe,” “should,” “could,” “plan,” “may,” “continue,” “target” or other similar words.

The Companies make forward-looking statements with full knowledge that risks and uncertainties exist that may cause actual results to differ materially from predicted results. Factors that may cause actual results to differ are often presented with the forward-looking statements themselves. Additionally, other factors may cause actual results to differ materially from those indicated in any forward-looking statement. These factors include but are not limited to:

Unusual weather conditions and their effect on energy sales to customers and energy commodity prices;

Extreme weather events and other natural disasters, including, but not limited to, hurricanes, high winds, severe storms, earthquakes, flooding, climate changes and changes in water temperatures and availability that can cause outages and property damage to facilities;

The impact of extraordinary external events, such as the current pandemic health event resulting from COVID-19, and their collateral consequences, including extended disruption of economic activity in our markets and global supply chains;

Federal, state and local legislative and regulatory developments, including changes in or interpretations of federal and state tax laws and regulations;

The direct and indirect impacts of implementing recommendations resulting from the business review announced in November 2022;

Risks of operating businesses in regulated industries that are subject to changing regulatory structures;

Changes to regulated electric rates collected by the Companies and regulated gas distribution, transportation and storage rates collected by Dominion Energy;

Changes in rules for RTOs and ISOs in which the Companies join and/or participate, including changes in rate designs, changes in FERC’s interpretation of market rules and new and evolving capacity models;

Risks associated with Virginia Power’s membership and participation in PJM, including risks related to obligations created by the default of other participants;

Risks associated with entities in which Dominion Energy shares ownership with third parties, including risks that result from lack of sole decision making authority, disputes that may arise between Dominion Energy and third party participants and difficulties in exiting these arrangements;

Changes in future levels of domestic and international natural gas production, supply or consumption;

Timing and receipt of regulatory approvals necessary for planned construction or growth projects and compliance with conditions associated with such regulatory approvals;

The inability to complete planned construction, conversion or growth projects at all, or with the outcomes or within the terms and time frames initially anticipated, including as a result of increased public involvement, intervention or litigation in such projects;

Risks and uncertainties that may impact the Companies’ ability to develop and construct the CVOW Commercial Project within the currently proposed timeline, or at all, and consistent with current cost estimates along with the ability to recover such costs from customers;

Changes to federal, state and local environmental laws and regulations, including those related to climate change, the tightening of emission or discharge limits for GHGs and other substances, more extensive permitting requirements and the regulation of additional substances;

Cost of environmental strategy and compliance, including those costs related to climate change;

Changes in implementation and enforcement practices of regulators relating to environmental standards and litigation exposure for remedial activities;

Difficulty in anticipating mitigation requirements associated with environmental and other regulatory approvals or related appeals;

Unplanned outages at facilities in which the Companies have an ownership interest;

The impact of operational hazards, including adverse developments with respect to pipeline and plant safety or integrity, equipment loss, malfunction or failure, operator error and other catastrophic events;

Risks associated with the operation of nuclear facilities, including costs associated with the disposal of spent nuclear fuel, decommissioning, plant maintenance and changes in existing regulations governing such facilities;

Changes in operating, maintenance and construction costs;

Domestic terrorism and other threats to the Companies’ physical and intangible assets, as well as threats to cybersecurity;

Additional competition in industries in which the Companies operate, including in electric markets in which Dominion Energy’s nonregulated generation facilities operate and potential competition from the development and deployment of alternative energy sources, such as self-generation and distributed generation technologies, and availability of market alternatives to large commercial and industrial customers;

Competition in the development, construction and ownership of certain electric transmission facilities in the Companies’ service territory in connection with Order 1000;

Changes in technology, particularly with respect to new, developing or alternative sources of generation and smart grid technologies;

Changes in demand for the Companies’ services, including industrial, commercial and residential growth or decline in the Companies’ service areas, changes in supplies of natural gas delivered to Dominion Energy’s pipeline system, failure to maintain or replace customer contracts on favorable terms, changes in customer growth or usage patterns, including as a result of energy conservation programs, the availability of energy efficient devices and the use of distributed generation methods;

Receipt of approvals for, and timing of, closing dates for acquisitions and divestitures;

Impacts of acquisitions, divestitures, transfers of assets to joint ventures and retirements of assets based on asset portfolio reviews;

The expected timing and likelihood of the completion of any or all of the East Ohio, PSNC and Questar Gas Transactions, including the ability to obtain the requisite regulatory approvals and the terms and conditions of such approvals;

Adverse outcomes in litigation matters or regulatory proceedings;

Counterparty credit and performance risk;

Fluctuations in the value of investments held in nuclear decommissioning trusts by the Companies and in benefit plan trusts by Dominion Energy;

Fluctuations in energy-related commodity prices and the effect these could

Showing the first 8K of 96K characters. Open the full section

Item 4. CONTROLS AND PROCEDURES

Senior management of both Dominion Energy and Virginia Power, including Dominion Energy and Virginia Power’s CEO and CFO, evaluated the effectiveness of each company’s disclosure controls and procedures as of the end of the period covered by this report. Based on this evaluation process, each of Dominion Energy and Virginia Power’s CEO and CFO have concluded that each company’s disclosure controls and procedures are effective.

There were no changes that occurred during the last fiscal quarter that materially affected, or are reasonably likely to materially affect, Dominion Energy or Virginia Power’s internal control over financial reporting.

PART II. OTHER INFORMATION

ITEM 1. LEGAL PROCEEDINGS

From time to time, the Companies are parties to various legal, environmental or other regulatory proceedings, including in the ordinary course of business. SEC regulations require disclosure of certain environmental matters when a governmental authority is a party to the proceedings and such proceedings involve potential monetary sanctions that the Companies reasonably believe will exceed a specified threshold. Pursuant to the SEC regulations, the Companies use a threshold of $1 million for such proceedings.

See the following for discussions on various legal, environmental and other regulatory proceedings to which the Companies are a party, which information is incorporated herein by reference:

Notes 13 and 23 to the Consolidated Financial Statements and Future Issues and Other Matters in MD&A in the Companies’ Annual Report on Form 10-K for the year ended December 31, 2022.

Notes 13 and 17 to the Consolidated Financial Statements and Future Issues and Other Matters in MD&A in this report.

Item 1A. RISK FACTORS

The Companies’ businesses are influenced by many factors that are difficult to predict, involve uncertainties that may materially affect actual results and are often beyond the Companies’ control. A number of these risk factors have been identified in the Companies’ Annual Report on Form 10-K for the year ended December 31, 2022, which should be taken into consideration when reviewing the information contained in this report. Other than the risk factor discussed below, there have been no material changes with regard to the risk factors previously disclosed in the Companies’ Annual Report on Form 10-K for the year ended December 31, 2022. For other factors that may cause actual results to differ materially from those indicated in any forward-looking statement or projection contained in this report, see Forward-Looking Statements in MD&A in this report.

Dominion Energy may be unable to complete one or all the proposed sales of certain regulated gas distribution operations to Enbridge under the current terms and/or expected timing. The ability of Dominion Energy to complete the East Ohio, PSNC and Questar Gas Transactions, each of which are not conditioned upon the completion of the others, is dependent upon receiving clearance or approval under or by the Hart-Scott-Rodino Act, CFIUS, FCC and applicable state utility commissions, including the North Carolina, Utah and Wyoming Commissions, as well as other customary closing and regulatory conditions. The ability to obtain the requisite regulatory approvals for each sale as well as the timing of such approvals is outside of Dominion Energy’s control. In addition, the terms and conditions associated with such approvals may result in additional requirements or obligations which may be burdensome or potentially result in the inability to complete one or all of the proposed sales under the current terms and/or expected timing. Such events could negatively impact Dominion Energy’s ability to implement certain of the recommendations in connection with the comprehensive business review announced in November 2022 as well as have a material adverse effect on Dominion Energy’s reputation, its financial condition, results of operations or cash flows.

ITEM 2. UNREGISTERED SALES OF EQUITY SECURITIES AND USE OF PROCEEDS

Dominion Energy

Purchases of Equity Securities

PeriodTotal Number of Shares (or Units) Purchased**(1)**Average Price Paid per Share (or Unit)****(2)Total Number of Shares (or Units) Purchased as Part of Publicly Announced Plans or ProgramsMaximum Number (or Approximate Dollar Value) of Shares (or Units that May Yet Be Purchased under the Plans or Programs**(3)**
7/1/23 - 7/31/231,059$51.79—$ 0.92 billion
8/1/23 - 8/31/236,59452.30—0.92 billion
9/1/23 - 9/30/239547.88—0.92 billion
Total7,748$52.18—$ 0.92 billion

(1)

Represents shares of common stock that were tendered by employees to satisfy tax withholding obligations on vested restricted stock.

(2)

Represents the weighted-average price paid per share.

(3)

In November 2020, the Dominion Energy Board of Directors authorized the repurchase of up to $1.0 billion of shares of common stock. This repurchase program has no expiration date or price or volume targets and may be modified, suspended or terminated at any time. Shares may be purchased through open market or privately negotiated transactions or otherwise at the discretion of management subject to prevailing market conditions, applicable securities laws and other factors.

ITEM 5. OTHER INFORMATION

During the last fiscal quarter, none of the Companies’ directors or officers (as defined in Rule 16a-1(f) under the Exchange Act) adopted or terminated a “Rule 10b5-1 trading arrangement” or “non-Rule 10b5-1 trading arrangement,” as each term is defined in Item 408(a) of Regulation S-K.

On November 2, 2023, Virginia Power issued 8,256 shares of its common stock to Dominion Energy, the sole holder of Virginia Power’s common stock, for an aggregate purchase price of approximately $539 million in a transaction exempt from registration under Section 4(a)(2) of the Securities Act of 1933, as amended. Virginia Power used the proceeds from the sale of the shares to reduce the aggregate amount outstanding under its intercompany credit facility with Dominion Energy. Virginia Power issued the shares pursuant to a Virginia Commission order authorizing Virginia Power to issue up to $3.25 billion of common stock to Dominion Energy through the end of 2023 in order to maintain a common equity capitalization to total capitalization ratio of 52.10% in accordance with legislation enacted in Virginia in April 2023.

Item 6. EXHIBITS

Exhibit NumberDescriptionDominion EnergyVirginia Power
2.1Purchase and Sale Agreement, dated as of September 5, 2023, by and between Dominion Energy, Inc. and Enbridge Elephant Holdings, LLC (Exhibit 2.1, Form 8-K filed September 5, 2023, File No. 1-8489).X
2.2Purchase and Sale Agreement, dated as of September 5, 2023, by and between Dominion Energy, Inc. and Enbridge Parrot Holdings, LLC (Exhibit 2.2, Form 8-K filed September 5, 2023, File No. 1-8489).X
2.3Purchase and Sale Agreement, dated as of September 5, 2023, by and between Dominion Energy, Inc. and Enbridge Quail Holdings, LLC (Exhibit 2.3, Form 8-K filed September 5, 2023, File No. 1-8489).X
3.1.aDominion Energy, Inc. Amended and Restated Articles of Incorporation, dated as of September 2, 2022 (Exhibit 3.1, Form 8-K filed September 2, 2022, File No.1-8489).X
3.1.bVirginia Electric and Power Company Amended and Restated Articles of Incorporation, as in effect on October 30, 2014 (Exhibit 3.1.b, Form 10-Q filed November 3, 2014, File No. 1-2255).X
3.2.aDominion Energy, Inc. Bylaws, as amended and restated, effective May 10, 2023 (Exhibit 3.1, Form 8-K filed May 11, 2023, File No. 1-8489).X
3.2.bVirginia Electric and Power Company Amended and Restated Bylaws, effective June 1, 2009 (Exhibit 3.1, Form 8-K filed June 3, 2009, File No. 1-2255).X
4Dominion Energy, Inc. and Virginia Electric and Power Company agree to furnish to the Securities and Exchange Commission upon request any other instrument with respect to long-term debt as to which the total amount of securities authorized does not exceed 10% of any of their total consolidated assets.XX
4.1Senior Indenture, dated as of September 1, 2017, between Virginia Electric and Power Company and U.S. Bank National Association, as Trustee (Exhibit 4.1, Form 8-K filed September 13, 2017, File No.000-55337); First Supplemental Indenture, dated as of September 1, 2017 (Exhibit 4.2, Form 8-K filed September 13, 2017, File No.000-55337); Second Supplemental Indenture, dated as of March 1, 2018 (Exhibit 4.2, Form 8-K filed March 22, 2018, File No. 000-55337); Third Supplemental Indenture, dated as of November 1, 2018 (Exhibit 4.2, Form 8-K filed November 28, 2018, File No. 000-55337); Fourth Supplemental Indenture, dated as of July 1, 2019 (Exhibit 4.2, Form 8-K filed July 10, 2019, File No. 00-55337); Fifth Supplemental Indenture, dated as of December 1, 2019 (Exhibit 4.2, Form 8-K filed December 5, 2019, File No. 000-55337); Sixth Supplemental Indenture, dated as of December 1, 2020 (Exhibit 4.2, Form 8-K filed December 15, 2020, File No. 00-55337); Seventh Supplemental Indenture, dated as of November 1, 2021 (Exhibit 4.2, Form 8-K filed November 22, 2021, File No.000-55337); Eighth Supplemental Indenture, dated as of November 1, 2021 (Exhibit 4.3, Form 8-K filed November 22, 2021, File No.000-55337); Ninth Supplemental Indenture, dated as of January 1, 2022 (Exhibit 4.3, Form 8-K filed January 13, 2022, File No.000-55337); Tenth Supplemental Indenture, dated as of May 1, 2022, (Exhibit 4.2, Form 8-K filed May 31, 2022, File No. 000-55337); Eleventh Supplemental Indenture, dated as of May 1, 2022, (Exhibit 4.3, Form 8-K filed May 31, 2022, File No. 000-55337); Twelfth Supplemental Indenture, dated March 1, 2023 (Exhibit 4.2, Form 8-K filed March 30, 2023, File No. 000-55337); Thirteenth Supplemental Indenture, dated March 1, 2023 (Exhibit 4.3, Form 8-K filed March 30, 2023, File No. 000-55337); Fourteenth Supplemental Indenture, dated August 1, 2023 (Exhibit 4.2, Form 8-K filed August 10, 2023, File No. 000-55337); Fifteenth Supplemental Indenture, dated August 1, 2023 (Exhibit 4.3, Form 8-K filed August 10, 2023, File No. 000-55337).XX
31.aCertification by Chief Executive Officer of Dominion Energy, Inc. pursuant to Section 302 of the Sarbanes-Oxley Act of 2002 (filed herewith).X
Exhibit NumberDescriptionDominion EnergyVirginia Power
31.bCertification by Chief Financial Officer of Dominion Energy, Inc. pursuant to Section 302 of the Sarbanes-Oxley Act of 2002 (filed herewith).X
31.cCertification by Chief Executive Officer of Virginia Electric and Power Company pursuant to Section 302 of the Sarbanes-Oxley Act of 2002 (filed herewith).X
31.dCertification by Chief Financial Officer of Virginia Electric and Power Company pursuant to Section 302 of the Sarbanes-Oxley Act of 2002 (filed herewith).X
32.aCertification to the Securities and Exchange Commission by Chief Executive Officer and Chief Financial Officer of Dominion Energy, Inc. as required by Section 906 of the Sarbanes-Oxley Act of 2002 (furnished herewith).X
32.bCertification to the Securities and Exchange Commission by Chief Executive Officer and Chief Financial Officer of Virginia Electric and Power Company as required by Section 906 of the Sarbanes-Oxley Act of 2002 (furnished herewith).X
99Condensed consolidated earnings statements (filed herewith).XX
101The following financial statements from Dominion Energy, Inc.’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2023, filed on November 8, 2023, formatted in iXBRL (Inline eXtensible Business Reporting Language): (i) Consolidated Statements of Income, (ii) Consolidated Statements of Comprehensive Income (iii) Consolidated Balance Sheets, (iv) Consolidated Statements of Equity, (v) Consolidated Statements of Cash Flows, and (vi) the Notes to Consolidated Financial Statements. The following financial statements from Virginia Electric and Power Company’s Quarterly Report on Form 10-Q for the quarter ended September 30, 2023, filed on November 8, 2023, formatted in iXBRL (Inline eXtensible Business Reporting Language): (i) Consolidated Statements of Income, (ii) Consolidated Statements of Comprehensive Income, (iii) Consolidated Balance Sheets, (iv) Consolidated Statements of Common Shareholder’s Equity (v) Consolidated Statements of Cash Flows, and (vi) the Notes to Consolidated Financial Statements.XX
104Cover Page Interactive Data File formatted in iXBRL (Inline eXtensible Business Reporting Language) and contained in Exhibit 101.XX

SIGNATURE

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned thereunto duly authorized.

DOMINION ENERGY, INC. Registrant
November 8, 2023/s/ Michele L. Cardiff
Michele L. Cardiff Senior Vice President, Controller and Chief Accounting Officer
VIRGINIA ELECTRIC AND POWER COMPANY Registrant
November 8, 2023/s/ Michele L. Cardiff
Michele L. Cardiff Senior Vice President, Controller and Chief Accounting Officer