DUKE ENERGY

General

Duke Energy was incorporated on May 3, 2005, and is an energy company headquartered in Charlotte, North Carolina, subject to regulation by the FERC and other regulatory agencies listed below. Duke Energy operates in the U.S. primarily through its direct and indirect subsidiaries. Certain Duke Energy subsidiaries are also Subsidiary Registrants, including Duke Energy Carolinas, Progress Energy, Duke Energy Progress, Duke Energy Florida, Duke Energy Ohio, Duke Energy Indiana and Piedmont. Operations in Kentucky are conducted through Duke Energy Ohio's wholly owned subsidiary, Duke Energy Kentucky. References herein to Duke Energy Ohio include Duke Energy Ohio and its subsidiaries, unless otherwise noted. When discussing Duke Energy’s consolidated financial information, it necessarily includes the results of its separate Subsidiary Registrants, which along with Duke Energy, are collectively referred to as the Duke Energy Registrants.

The Duke Energy Registrants electronically file reports with the SEC, including Annual Reports on Form 10-K, quarterly reports on Form 10-Q, current reports on Form 8-K, proxy statements and amendments to such reports.

The SEC maintains an internet site that contains reports, proxy and information statements and other information regarding issuers that file electronically with the SEC at sec.gov. Additionally, information about the Duke Energy Registrants, including reports filed with the SEC, is available through Duke Energy’s website at duke-energy.com. Such reports are accessible at no charge and are made available as soon as reasonably practicable after such material is filed with or furnished to the SEC.

Business Segments

Duke Energy's segment structure includes two reportable business segments: Electric Utilities and Infrastructure (EU&I) and Gas Utilities and Infrastructure (GU&I). The remainder of Duke Energy’s operations is presented as Other. Commercial Renewables is reported as discontinued operations and is no longer a reportable segment beginning in the fourth quarter of 2022. See Note 2 to the Consolidated Financial Statements, “Dispositions," for further details. Duke Energy's chief operating decision-maker routinely reviews financial information about each of these business segments in deciding how to allocate resources and evaluate the performance of the business. For additional information on each of these business segments, including financial and geographic information, see Note 3 to the Consolidated Financial Statements, “Business Segments.” The following sections describe the business and operations of each of Duke Energy’s business segments, as well as Other.

ELECTRIC UTILITIES AND INFRASTRUCTURE

EU&I conducts operations primarily through the regulated public utilities of Duke Energy Carolinas, Duke Energy Progress, Duke Energy Florida, Duke Energy Indiana and Duke Energy Ohio. EU&I provides retail electric service through the generation, transmission, distribution and sale of electricity to approximately 8.4 million customers within the Southeast and Midwest regions of the U.S. The service territory is approximately 90,000 square miles across six states with a total estimated population of 27 million. The operations include electricity sold wholesale to municipalities, electric cooperative utilities and other load-serving entities.

During 2021, Duke Energy executed an agreement providing for an investment by an affiliate of GIC in Duke Energy Indiana in exchange for a 19.9% minority interest issued by Duke Energy Indiana Holdco, LLC, the holding company for Duke Energy Indiana. The transaction was completed following two closings. Additionally, in November 2022, Duke Energy committed to a plan to sell the Commercial Renewables business segment, excluding the offshore wind contract for Carolina Long Bay, which was moved to EU&I. Duke Energy entered into purchase and sale agreements with affiliates of Brookfield for the sale of the utility-scale solar and wind group in June 2023 and with affiliates of ArcLight for the distributed generation group in July 2023. Both transactions closed in October 2023. See Note 2 to the Consolidated Financial Statements, “Dispositions," for additional information.

EU&I is also a joint owner in certain electric transmission projects. EU&I has a 50% ownership interest in DATC, a partnership with American Transmission Company, formed to design, build and operate transmission infrastructure. DATC owns 72% of the transmission service rights to Path 15, an 84-mile transmission line in central California. EU&I also has a 50% ownership interest in Pioneer, which builds, owns and operates electric transmission facilities in North America. The following map shows the service territory for EU&I as of December 31, 2023.

BUSINESS

euimap2018001a02.jpg

The electric operations and investments in projects are subject to the rules and regulations of the FERC, the NRC, the NCUC, the PSCSC, the FPSC, the IURC, the PUCO and the KPSC.

The following table represents the distribution of GWh billed sales by customer class for the year ended December 31, 2023.

DukeDukeDukeDukeDuke
EnergyEnergyEnergyEnergyEnergy
CarolinasProgressFloridaOhioIndiana
Residential32%26%50%37%28%
General service34%22%36%38%26%
Industrial23%15%8%23%31%
Total retail sales89%63%94%98%85%
Wholesale and other sales11%37%6%2%15%
Total sales100%100%100%100%100%

The number of residential and general service customers within the EU&I service territory is expected to increase over time. Growth in weather-normal sales volumes, however, was lower in 2023 compared to 2022 due primarily to the continuation of energy efficiency adoption, rooftop solar and broad weakness across industrial sectors. While migration to EU&I's service territory remained strong, residential sales decreased due primarily to the return to more normal post-pandemic activities and economic conditions throughout the year. Lower industrial sales continued due to overall industrial weakness, including some manufacturing plant closings across certain jurisdictions, continuation of supply chain constraints and higher inventory levels, as well as higher interest rates. This was partially offset by higher data center usage, which contributed to growth in commercial sales volumes. The impact on customer's usage from these factors and other potential economic dynamics continues to be monitored. Over the longer time frame, it is still expected that the continued adoption of more efficient housing and appliances will have a negative impact on average usage per residential customer over time.

Seasonality and the Impact of Weather

Revenues and costs are influenced by seasonal weather patterns. Peak sales of electricity occur during the summer and winter months, which results in higher revenue and cash flows during these periods. By contrast, lower sales of electricity occur during the spring and fall, allowing for scheduled plant maintenance. Although decoupling mechanisms may mitigate some weather impacts, residential and general service customers are typically more impacted by weather than industrial customers. Estimated weather impacts are based on actual current period weather compared to normal weather conditions. Normal weather conditions are defined as the long-term average of actual historical weather conditions.

BUSINESS

The estimated impact of weather on earnings is based on the temperature variances from a normal condition and customers’ historic usage patterns. The methodology used to estimate the impact of weather does not consider all variables that may impact customer response to weather conditions such as humidity in the summer or wind chill in the winter. The precision of this estimate may also be impacted by applying long-term weather trends to shorter-term periods. Estimates of weather impacts may be more difficult to determine during periods of extreme or more volatile weather.

Heating degree days measure the variation in weather based on the extent the average daily temperature falls below a base temperature. Cooling degree days measure the variation in weather based on the extent the average daily temperature rises above the base temperature. Each degree of temperature below the base temperature counts as one heating degree day and each degree of temperature above the base temperature counts as one cooling degree day.

Competition

Retail

EU&I’s businesses operate as the sole supplier of electricity within their service territories, with the exception of Ohio, which has a competitive electricity supply market for generation service. EU&I owns and operates facilities necessary to generate, transmit, distribute and sell electricity. Services are priced by state commission-approved rates designed to include the costs of providing these services and a reasonable return on invested capital. This regulatory policy is intended to provide safe and reliable electricity at fair prices.

In Ohio, EU&I conducts competitive auctions for electricity supply. The cost of energy purchased through these auctions is recovered from retail customers. EU&I earns retail margin in Ohio on the transmission and distribution of electricity, but not on the cost of the underlying energy.

Competition in the regulated electric distribution business is primarily from the development and deployment of alternative energy sources including on-site generation from industrial customers and distributed generation, such as private solar, at residential, general service and/or industrial customer sites.

Wholesale

Duke Energy competes with other utilities and merchant generators for bulk power sales, sales to municipalities and cooperatives and wholesale transactions under primarily cost-based contracts approved by FERC. The principal factors in competing for these sales are availability of capacity and power, reliability of service and price. Prices are influenced primarily by market conditions and fuel costs.

Increased competition in the wholesale electric utility industry and the availability of transmission access could affect EU&I’s load forecasts, plans for power supply and wholesale energy sales and related revenues. Wholesale energy sales will be impacted by the extent to which additional generation is available to sell to the wholesale market and the ability of EU&I to attract new customers and to retain existing customers.

Energy Capacity and Resources

EU&I owns approximately 54,772 MW of generation capacity. For additional information on owned generation facilities, see Item 2, “Properties.”

Energy and capacity are also supplied through contracts with other generators and purchased on the open market. Factors that could cause EU&I to purchase power for its customers may include, but are not limited to, generating plant outages, extreme weather conditions, generation reliability, demand growth and price. EU&I has interconnections and arrangements with its neighboring utilities to facilitate planning, emergency assistance, sale and purchase of capacity and energy and reliability of power supply.

EU&I’s generation portfolio is a balanced mix of energy resources having different operating characteristics and fuel sources designed to provide energy at the lowest possible cost to meet its obligation to serve retail customers. All options, including owned generation resources and purchased power opportunities, are continually evaluated on a real-time basis to select and dispatch the lowest-cost resources available to meet system load requirements.

Sources of Electricity

EU&I relies principally on natural gas, nuclear fuel and coal for its generation of electricity. The following table lists sources of electricity and fuel costs for the three years ended December 31, 2023.

Cost of Delivered Fuel per Net
Generation by SourceKilowatt-hour Generated (Cents)
202320222021202320222021
Natural gas and fuel oil(a)33.3%34.2%31.8%3.816.353.89
Nuclear(a)28.4%26.6%29.8%0.580.580.58
Coal(a)12.8%13.5%18.2%4.073.432.84
All fuels (cost based on weighted average)(a)74.5%74.3%79.8%2.633.752.42
Hydroelectric and solar(b)1.8%1.5%1.5%
Total generation76.3%75.8%81.3%
Purchased power and net interchange23.7%24.2%18.7%
Total sources of energy100.0%100.0%100.0%

(a) Statistics related to all fuels reflect EU&I's public utility ownership interest in jointly owned generation facilities.

(b) Generating figures are net of output required to replenish pumped-storage facilities during off-peak periods.

BUSINESS

Natural Gas and Fuel Oil

Natural gas and fuel oil supply, transportation and storage for EU&I’s generation fleet is purchased under standard industry agreements from various suppliers, including Piedmont. Natural gas supply agreements typically provide for a percentage of forecasted burns being procured over time, with varied expiration dates. EU&I believes it has access to an adequate supply of natural gas and fuel oil for the reasonably foreseeable future.

EU&I has certain dual-fuel generating facilities that can operate utilizing both natural gas and fuel oil. The cost of EU&I’s natural gas and fuel oil is fixed price or determined by published market prices as reported in certain industry publications, plus any transportation and freight costs. Duke Energy Carolinas, Duke Energy Progress, Duke Energy Florida and Duke Energy Indiana use derivative instruments to manage a portion of their exposure to price fluctuations for natural gas. Duke Energy Florida has temporarily agreed to not hedge natural gas prices, but retains an ability to propose hedging again in annual fuel docket filings.

EU&I has firm interstate and intrastate natural gas transportation agreements and storage agreements in place to support generation needed for load requirements. EU&I may purchase additional shorter-term natural gas transportation and utilize natural gas interruptible transportation agreements to support generation needed for load requirements. The EU&I natural gas plants are served by various supply zones and multiple pipelines.

Nuclear

The industrial processes for producing nuclear generating fuel generally involve the mining and milling of uranium ore to produce uranium concentrates and services to convert, enrich and fabricate fuel assemblies.

EU&I has contracted for uranium materials and services to fuel its nuclear reactors. Uranium concentrates, conversion services and enrichment services are primarily met through a diversified portfolio of long-term supply contracts. The contracts are diversified by supplier, country of origin and pricing. EU&I staggers its contracting so that its portfolio of long-term contracts covers the majority of its fuel requirements in the near term and decreasing portions of its fuel requirements over time thereafter. Near-term requirements not met by long-term supply contracts have been and are expected to be fulfilled with spot market purchases. Due to the technical complexities of changing suppliers of fuel fabrication services, EU&I generally source these services to a single domestic supplier on a plant-by-plant basis using multiyear contracts.

EU&I has entered into fuel contracts that cover 100% of its uranium concentrates through at least 2027, 100% of its conversion services through at least 2029, 100% of its enrichment services through at least 2027, and 100% of its fabrication services requirements for these plants through at least 2027. For future requirements not already covered under long-term contracts, EU&I believes it will be able to renew contracts as they expire or enter into similar contractual arrangements with other suppliers of nuclear fuel materials and services.

Coal

EU&I meets its coal demand through a portfolio of long-term purchase contracts and short-term spot market purchase agreements. Large amounts of coal are purchased under long-term contracts with mining operators who mine both underground and at the surface. EU&I uses spot market purchases to meet coal requirements not met by long-term contracts. Expiration dates for its long-term contracts, which may have various price adjustment provisions and market reopeners, range from 2024 to 2027 for Duke Energy Carolinas, Duke Energy Progress and Duke Energy Indiana, 2024 to 2026 for Duke Energy Florida and 2024 to 2025 for Duke Energy Ohio. EU&I expects to renew these contracts or enter into similar contracts with other suppliers as existing contracts expire, though prices will fluctuate over time as coal markets change. EU&I has an adequate supply of coal under contract to meet its risk management guidelines regarding projected future consumption. Coal inventory levels may fluctuate as a result of volatility in natural gas prices and the associated impacts on coal-fired dispatch within the generation fleet. EU&I continues to actively manage its portfolio and has worked with suppliers to obtain increased flexibility in its coal contracts.

Coal purchased for the Carolinas is primarily produced from mines in Central Appalachia, Northern Appalachia and the Illinois Basin. Coal purchased for Florida is primarily produced from mines in the Illinois Basin. Coal purchased for Kentucky is primarily produced from mines along the Ohio River in Illinois, Kentucky, Ohio, West Virginia and Pennsylvania. Coal purchased for Indiana is primarily produced in Indiana and Illinois. There are adequate domestic coal reserves to serve EU&I's coal generation needs through end of life. The current average sulfur content of coal purchased by EU&I is between 0.5% and 3.5% for Duke Energy Carolinas and Duke Energy Progress, between 1% and 3.5% for Duke Energy Florida, and between 0.5% and 4.0% for Duke Energy Ohio and Duke Energy Indiana. EU&I's environmental controls, in combination with the use of sulfur dioxide (SO2) emission allowances, enable EU&I to satisfy current SO2 emission limitations for its existing facilities.

Purchased Power

EU&I purchases a portion of its capacity and system requirements through purchase obligations, leases and purchase capacity contracts. EU&I believes it can obtain adequate purchased power capacity to meet future system load needs. However, during periods of high demand, the price and availability of purchased power may be significantly affected.

The following table summarizes purchased power for the previous three years:

202320222021
Purchase obligations and leases (in millions of MWh)(a)37.641.236.0
Purchase capacity under contract (in MW)(b)3,9974,0284,259

(a) Represents approximately 15% of total system requirements for 2023, 16% for 2022 and 14% for 2021.

(b) For 2023, 2022 and 2021, these agreements include approximately 412 MW of firm capacity under contract by Duke Energy Florida with QFs.

BUSINESS

Inventory

EU&I must maintain an adequate stock of fuel and materials and supplies in order to ensure continuous operation of generating facilities and reliable delivery to customers. As of December 31, 2023, the inventory balance for EU&I was approximately $4.1 billion. For additional information on inventory, see Note 1 to the Consolidated Financial Statements, “Summary of Significant Accounting Policies.”

Ash Basin Management

The EPA has issued regulations related to the management of CCR from power plants including the CCR Rule. These regulations classify CCR as nonhazardous waste under the Resource Conservation and Recovery Act (RCRA) and apply to electric generating sites with new and existing landfills and new and existing surface impoundments and establish requirements regarding landfill design, structural integrity design and assessment criteria for surface impoundments, groundwater monitoring, protection and remedial procedures and other operational and reporting procedures for the disposal and management of CCR. In addition to the federal regulations, CCR landfills and surface impoundments (ash basins or impoundments) will continue to be regulated by existing state laws, regulations and permits, such as the North Carolina Coal Ash Management Act of 2014 (Coal Ash Act).

EU&I has and will periodically submit to applicable authorities required site-specific coal ash impoundment remediation or closure plans. Closure plans must be approved and all associated permits issued before any work can begin. Closure activities have begun in all of Duke Energy's jurisdictions. Excavation began in 2015 at the four sites specified as high priority by the Coal Ash Act and at the W.S. Lee Steam Station site in South Carolina in connection with other legal requirements. Excavation at these sites involves movement of CCR materials to appropriate engineered off-site or on-site lined landfills or for reuse in an approved beneficial application. Duke Energy has completed excavation of coal ash at the four high-priority North Carolina sites. At other sites where CCR management is required, planning and closure methods have been studied and factored into the estimated retirement and management costs, and closure activities have commenced.

The EPA CCR rule and the Coal Ash Act leave the decision on cost recovery determinations related to closure of coal ash surface impoundments to the normal ratemaking processes before utility regulatory commissions. Duke Energy's electric utilities have included compliance costs associated with federal and state requirements in their respective rate proceedings. During 2017, Duke Energy Carolinas' and Duke Energy Progress’ wholesale contracts were amended to include the recovery of expenditures related to AROs for the closure of coal ash basins. The amended contracts have retail disallowance parity or provisions limiting challenges to CCR cost recovery actions at FERC. FERC approved the amended wholesale rate schedules in 2017. For additional information on the ash basins and recovery, see Item 7, "Other Matters" and Notes 4, 5 and 10 to the Consolidated Financial Statements, "Regulatory Matters," "Commitments and Contingencies" and "Asset Retirement Obligations," respectively.

Nuclear Matters

Duke Energy owns, wholly or partially, 11 operating nuclear reactors located at six operating stations. The Crystal River Unit 3 permanently ceased operation in February 2013. Nuclear insurance includes: nuclear liability coverage; property damage coverage; nuclear accident decontamination and premature decommissioning coverage; and accidental outage coverage for losses in the event of a major accidental outage. Joint owners reimburse Duke Energy for certain expenses associated with nuclear insurance in accordance with joint owner agreements. The Price-Anderson Act requires plant owners to provide for public nuclear liability claims resulting from nuclear incidents to the maximum total financial protection liability, which is approximately $16.2 billion. For additional information on nuclear insurance, see Note 5 to the Consolidated Financial Statements, “Commitments and Contingencies.”

Duke Energy has a significant future financial commitment to dispose of spent nuclear fuel and decommission and decontaminate each plant safely. The NCUC and the PSCSC require Duke Energy Carolinas and Duke Energy Progress update cost estimates for decommissioning their nuclear plants every five years. The nuclear decommissioning liabilities are assessed and updated based on changes in cash flows provided in new studies as well as annual assessments to evaluate whether any indicators suggest a change in the estimate of the ARO is necessary.

The following table summarizes the fair value of NDTF investments and the most recent site-specific nuclear decommissioning cost studies. Decommissioning costs are stated in 2023 or 2019 dollars, depending on the year of the cost study, and include costs to decommission plant components not subject to radioactive contamination.

NDTF**(a)**Decommissioning
(in millions)December 31, 2023December 31, 2022Costs**(a)**Year of Cost Study
Duke Energy$10,143$8,637$8,8142023 or 2019
Duke Energy Carolinas(b)(c)5,6864,7834,4392023
Duke Energy Progress(d)4,0753,4304,1812019
Duke Energy Florida(e)382424194N/A

(a) Amounts for Progress Energy equal the sum of Duke Energy Progress and Duke Energy Florida.

(b) Decommissioning cost for Duke Energy Carolinas reflects its ownership interest in jointly owned reactors. Other joint owners are responsible for decommissioning costs related to their interest in the reactors.

(c) Duke Energy Carolinas' site-specific nuclear decommissioning cost study completed in 2023 was filed with the NCUC and PSCSC in 2024. A funding study was last completed and filed in 2019. An updated funding study will be completed and filed with the NCUC and PSCSC in 2024.

BUSINESS

(d) Duke Energy Progress' site-specific nuclear decommissioning cost study completed in 2019 was filed with the NCUC and PSCSC in March 2020. Duke Energy Progress also completed a funding study, which was filed with the NCUC and PSCSC in July 2020. In October 2021, Duke Energy Progress filed the 2019 nuclear decommissioning cost study with the FERC, as well as a revised date schedule for decommissioning expense to be collected from wholesale customers. The FERC accepted the filing, as filed on December 9, 2021.

(e) During 2019, Duke Energy Florida reached an agreement to transfer decommissioning work for Crystal River Unit 3 to a third party and decommissioning costs are based on the agreement with this third party rather than a cost study. Regulatory approval was received from the NRC and the FPSC in April 2020 and August 2020, respectively. Duke Energy Florida provides the FPSC periodic reports on the status and progress of decommissioning activities.

The NCUC, PSCSC, FPSC and FERC have allowed EU&I to recover estimated decommissioning costs through retail and wholesale rates over the expected remaining service periods of their nuclear stations. EU&I believes the decommissioning costs being recovered through rates, when coupled with the existing fund balances and expected fund earnings, will be sufficient to provide for the cost of future decommissioning. For additional information, see Note 10 to the Consolidated Financial Statements, “Asset Retirement Obligations.”

The Nuclear Waste Policy Act of 1982 (as amended) provides the framework for development by the federal government of interim storage and permanent disposal facilities for high-level radioactive waste materials. The government has not yet developed a storage facility or disposal capacity, so EU&I will continue to store spent fuel on its reactor sites.

Under federal law, the DOE is responsible for the selection and construction of a facility for the permanent disposal of spent nuclear fuel and high-level radioactive waste. The DOE terminated the project to license and develop a geologic repository at Yucca Mountain, Nevada in 2010, and is currently taking no action to fulfill its responsibilities to dispose of spent fuel.

Until the DOE begins to accept the spent nuclear fuel, Duke Energy Carolinas, Duke Energy Progress and Duke Energy Florida will continue to safely manage their spent nuclear fuel. Under current regulatory guidelines, Harris has sufficient storage capacity in its spent fuel pools through the expiration of its renewed operating license. With certain modifications and approvals by the NRC to expand the on-site dry cask storage facilities, spent nuclear fuel dry storage facilities will be sufficient to provide storage space of spent fuel through the expiration of the operating licenses, including any license renewals, for Brunswick, Catawba, McGuire, Oconee and Robinson. Crystal River Unit 3 ceased operation in 2013 and was placed in a SAFSTOR condition in January 2018. As of January 2018, all spent fuel at Crystal River Unit 3 has been transferred from the spent fuel pool to dry storage at an on-site independent spent fuel storage installation.

The nuclear power industry faces uncertainties with respect to the cost and long-term availability of disposal sites for spent nuclear fuel and other radioactive waste, compliance with changing regulatory requirements, capital outlays for modifications and new plant construction.

EU&I is subject to the jurisdiction of the NRC for the design, construction and operation of its nuclear generating facilities. The following table includes the current year of expiration of nuclear operating licenses for nuclear stations in operation. In June 2021, Duke Energy Carolinas filed a subsequent license renewal application for Oconee with the U.S. Nuclear Regulatory Commission to renew Oconee's operating license for an additional 20 years. Duke Energy has announced its intention to seek 20-year operating license renewals for each of the reactors it operates in Duke Energy Carolinas and Duke Energy Progress. See Note 4 to the Consolidated Financial Statements, "Regulatory Matters,” for additional information.

UnitYear of Expiration
Duke Energy Carolinas
Catawba Units 1 and 22043
McGuire Unit 12041
McGuire Unit 22043
Oconee Units 1 and 22033
Oconee Unit 32034
Duke Energy Progress
Brunswick Unit 12036
Brunswick Unit 22034
Harris2046
Robinson2030

The NRC has acknowledged permanent cessation of operation and permanent removal of fuel from the reactor vessel at Crystal River Unit 3. Therefore, the license no longer authorizes operation of the reactor. For additional information on nuclear decommissioning activity, see Note 10 to the Consolidated Financial Statements, "Asset Retirement Obligations."

Regulation

State

The state electric utility commissions approve rates for Duke Energy's retail electric service within their respective states. The state electric utility commissions, to varying degrees, have authority over the construction and operation of EU&I’s generating facilities. CPCNs issued by the state electric utility commissions, as applicable, authorize EU&I to construct and operate its electric facilities and to sell electricity to retail and wholesale customers. Prior approval from the relevant state electric utility commission is required for the entities within EU&I to issue securities. The underlying concept of utility ratemaking is to set rates at a level that allows the utility to collect revenues equal to its cost of providing service plus earn a reasonable rate of return on its invested capital, including equity.

BUSINESS

In addition to rates approved in base rate cases, each of the state electric utility commissions allow recovery of certain costs through various cost recovery clauses to the extent the respective commission determines in periodic hearings that such costs, including any past over or under-recovered costs, are prudent.

Fuel, fuel-related costs and certain purchased power costs are eligible for recovery by EU&I. EU&I uses coal, hydroelectric, natural gas, oil, renewable generation and nuclear fuel to generate electricity, thereby maintaining a diverse fuel mix that helps mitigate the impact of cost increases in any one fuel. Due to the associated regulatory treatment and the method allowed for recovery, changes in fuel costs from year to year have no material impact on operating results of EU&I, unless a commission finds a portion of such costs to have been imprudent. However, delays between the expenditure for fuel costs and recovery from customers can adversely impact the timing of cash flows of EU&I.

The table below reflects significant electric rate case applications approved and effective in the past three years and applications currently pending approval.

Regulatory BodyAnnual Increase (Decrease) (in millions)Return on EquityEquity Component of Capital StructureEffective Date
Approved Rate Cases:
Duke Energy Carolinas 2023 North Carolina Rate Case(a)NCUC$76810.1%53%January 2024
Duke Energy Kentucky 2022 Kentucky Electric Rate Case(b)KPSC489.75%52.145%October 2023
Duke Energy Progress 2022 North Carolina Rate Case(c)NCUC4949.8%53%October 2023
Duke Energy Progress 2022 South Carolina Rate CasePSCSC529.6%52.43%April 2023
Duke Energy Ohio 2021 Ohio Electric Rate CasePUCO239.5%50.5%January 2023
Duke Energy Progress 2019 North Carolina Rate CaseNCUC1789.6%52%June 2021
Duke Energy Carolinas 2019 North Carolina Rate CaseNCUC339.6%52%June 2021
Pending Rate Cases:
Duke Energy Carolinas 2024 South Carolina Rate CasePSCSC23910.5%53%August 2024

(a) Of the total rate case increase, Year 1, 2 and 3 rates are approximately 57%, 22% and 21%, respectively.

(b) An ROE of 9.65% for electric riders was approved.

(c) Of the total rate increase, Year 1, 2 and 3 rates are approximately 49%, 24% and 27%, respectively.

Additionally, in January 2021, Duke Energy Florida filed the 2021 Settlement with the FPSC that will allow annual increases to its base rates, an agreed upon return on equity (ROE) and includes a base rate stay-out provision through 2024, among other provisions. The FPSC approved the 2021 Settlement on May 4, 2021, issuing an order on June 4, 2021. Revised customer rates became effective January 1, 2022, with subsequent base rate increases effective January 1, 2023, and January 1, 2024. In January 2024, Duke Energy Florida notified the FPSC that it expects to file a formal request for new base rates in April 2024. For more information on rate matters and other regulatory proceedings, see Note 4 to the Consolidated Financial Statements, “Regulatory Matters.”

Federal

The FERC approves EU&I’s cost-based rates for electric sales to certain power and transmission wholesale customers. Regulations of FERC and the state electric utility commissions govern access to regulated electric and other data by nonregulated entities and services provided between regulated and nonregulated energy affiliates. These regulations affect the activities of nonregulated affiliates with EU&I.

RTOs

PJM and MISO are the ISOs and FERC-approved RTOs for the regions in which Duke Energy Ohio and Duke Energy Indiana operate. PJM and MISO operate energy, capacity and other markets, and control the day-to-day operations of bulk power systems through central dispatch.

Duke Energy Ohio is a member of PJM and Duke Energy Indiana is a member of MISO. Transmission owners in these RTOs have turned over control of their transmission facilities and their transmission systems are currently under the dispatch control of the RTOs. Transmission service is provided on a regionwide, open-access basis using the transmission facilities of the RTO members at rates based on the costs of transmission service.

Environmental

EU&I is subject to the jurisdiction of the EPA and state and local environmental agencies. For a discussion of environmental regulation, see “Environmental Matters” in this section. See the “Other Matters” section of Item 7 Management's Discussion and Analysis for a discussion about potential Global Climate Change legislation and other EPA regulations under development and the potential impacts such legislation and regulation could have on Duke Energy’s operations.

BUSINESS

GAS UTILITIES AND INFRASTRUCTURE

GU&I conducts natural gas operations primarily through the regulated public utilities of Piedmont, Duke Energy Ohio and Duke Energy Kentucky. The natural gas operations are subject to the rules and regulations of the NCUC, PSCSC, PUCO, KPSC, TPUC, PHMSA and the FERC. GU&I serves residential, commercial, industrial and power generation natural gas customers, including customers served by municipalities who are wholesale customers. GU&I has over 1.7 million total customers, including approximately 1.2 million customers located in North Carolina, South Carolina and Tennessee, and an additional 560,000 customers located within southwestern Ohio and northern Kentucky. In the Carolinas, Ohio and Kentucky, the service areas are comprised of numerous cities, towns and communities. In Tennessee, the service area is the metropolitan area of Nashville. The following map shows the service territory and investments in operating pipelines for GU&I as of December 31, 2023.

200477-A%20Gas%20Service%20Map%20with%20pipelines-final.jpg

The number of residential, commercial and industrial customers within the GU&I service territory is expected to increase over time. Average usage per residential customer is expected to remain flat or decline for the foreseeable future; however, decoupled rates in North Carolina and various rate design mechanisms in other jurisdictions partially mitigate the impact of the declining usage per customer on overall profitability.

GU&I also has investments in various pipeline transmission projects, renewable natural gas projects and natural gas storage facilities.

BUSINESS

Natural Gas for Retail Distribution

GU&I is responsible for the distribution of natural gas to retail customers in its North Carolina, South Carolina, Tennessee, Ohio and Kentucky service territories. GU&I’s natural gas procurement strategy is to contract primarily with major and independent producers and marketers for natural gas supply. It also purchases a diverse portfolio of transportation and storage service from interstate pipelines. This strategy allows GU&I to assure reliable natural gas supply and transportation for its firm customers during peak winter conditions. When firm pipeline services or contracted natural gas supplies are temporarily not needed due to market demand fluctuations, GU&I may release these services and supplies in the secondary market under FERC-approved capacity release provisions and/or make wholesale secondary market sales. In 2023, firm supply purchase commitment agreements provided for approximately 96% of the natural gas supply for both Piedmont and Duke Energy Ohio during the winter months and 100% of forecasted demand was under contract prior to the winter heating season.

Impact of Weather

GU&I revenues are generally protected from the impact of weather fluctuations due to the regulatory mechanisms that are available in most service territories. In North Carolina, margin decoupling provides protection from both weather and other usage variations like conservation for residential and small and medium general service customers. Margin decoupling provides a set margin per customer independent of actual usage. In South Carolina, Tennessee and Kentucky, weather normalization adjusts revenues either up or down depending on how much warmer or colder than normal a given month has been. Weather normalization adjustments occur from November through March in South Carolina, from October through April in Tennessee and from November through April in Kentucky. Duke Energy Ohio collects most of its non-fuel revenue through a fixed monthly charge that is not impacted by usage fluctuations that result from weather changes or conservation.

Competition

GU&I’s businesses operate as the sole provider of natural gas service within their retail service territories. GU&I owns and operates facilities necessary to transport and distribute natural gas. GU&I earns retail margin on the transmission and distribution of natural gas and not on the cost of the underlying commodity. Services are priced by state commission-approved rates designed to include the costs of providing these services and a reasonable return on invested capital. This regulatory policy is intended to provide safe and reliable natural gas service at fair prices.

In residential, commercial and industrial customer markets, natural gas distribution operations compete with other companies that supply energy, primarily electric companies, propane and fuel oil dealers, renewable energy providers and coal companies in relation to sources of energy for electric power plants, as well as nuclear energy. A significant competitive factor is price. GU&I's primary product competition is with electricity for space heating, water heating and cooking. Increases in the price of natural gas or decreases in the price of other energy sources could negatively impact competitive position by decreasing the price benefits of natural gas to the consumer. In the case of industrial customers, such as manufacturing plants, adverse economic or market conditions, including higher natural gas costs, could cause these customers to suspend business operations or to use alternative sources of energy in favor of energy sources with lower per-unit costs.

Higher natural gas costs or decreases in the price of other energy sources may allow competition from alternative energy sources for applications that have traditionally used natural gas, encouraging some customers to move away from natural gas-fired equipment to equipment fueled by other energy sources. Competition between natural gas and other forms of energy is also based on efficiency, performance, reliability, safety and other non-price factors. Technological improvements in other energy sources and events that impair the public perception of the non-price attributes of natural gas could erode our competitive advantage. These factors in turn could decrease the demand for natural gas, impair our ability to attract new customers and cause existing customers to switch to other forms of energy or to bypass our systems in favor of alternative competitive sources. This could result in slow or no customer growth and could cause customers to reduce or cease using our product, thereby reducing our ability to make capital expenditures and otherwise grow our business, adversely affecting our earnings.

Natural Gas Investments

Duke Energy, through its GU&I segment, has a 7.5% equity ownership interest in Sabal Trail. Sabal Trail is a joint venture that owns the Sabal Trail Natural Gas Pipeline (Sabal Trail pipeline) to transport natural gas to Florida, regulated by FERC. The Sabal Trail Phase I mainline was placed into service in July 2017 and traverses Alabama, Georgia and Florida. The remaining lateral line to the Duke Energy Florida's Citrus County CC was placed into service in March 2018. Phase II of Sabal Trail went into service in May 2020, adding approximately 200,000 Dth of capacity to the Sabal Trail pipeline.

Duke Energy, through its GU&I segment, has a 47% equity ownership interest in ACP, which planned to build the ACP pipeline, an approximately 600-mile interstate natural gas pipeline. The ACP pipeline was intended to transport diverse natural gas supplies into southeastern markets and would be regulated by FERC. Dominion Energy owns 53% of ACP and was contracted to construct and operate the ACP pipeline upon completion. On July 5, 2020, Dominion announced a sale of substantially all of its natural gas transmission and storage segment assets, which were critical to the ACP pipeline. Further, permitting delays and legal challenges had materially affected the timing and cost of the pipeline. As a result, Duke Energy determined that they would no longer invest in the construction of the ACP pipeline.

Duke Energy, also through its GU&I segment, has investments in various renewable natural gas joint ventures.

GU&I has a 21.49% equity ownership interest in Cardinal, an intrastate pipeline located in North Carolina regulated by the NCUC, a 45% equity ownership in Pine Needle, an interstate liquefied natural gas storage facility located in North Carolina and a 50% equity ownership interest in Hardy Storage, an underground interstate natural gas storage facility located in Hardy and Hampshire counties in West Virginia. Pine Needle and Hardy Storage are regulated by FERC.

KO Transmission Company (KO Transmission), a wholly owned subsidiary of Duke Energy Ohio, is an interstate pipeline company engaged in the business of transporting natural gas and is subject to the rules and regulations of FERC. KO Transmission's 90-mile pipeline supplies natural gas to Duke Energy Ohio and interconnects with the Columbia Gulf Transmission pipeline and Tennessee Gas Pipeline. An approximately 70-mile portion of KO Transmission's pipeline facilities was co-owned by Columbia Gas Transmission, LLC. KO Transmission sold all of its pipeline facilities and related real property to Columbia Gas Transmission, LLC on February 1, 2023, for approximately book value.

See Notes 4, 13 and 18 to the Consolidated Financial Statements, "Regulatory Matters," "Investments in Unconsolidated Affiliates" and "Variable Interest Entities," respectively, for further information on Duke Energy's and GU&I's natural gas investments.

BUSINESS

Inventory

GU&I must maintain adequate natural gas inventory in order to provide reliable delivery to customers. As of December 31, 2023, the inventory balance for GU&I was $129 million. For more information on inventory, see Note 1 to the Consolidated Financial Statements, "Summary of Significant Accounting Policies."

Regulation

State

The state gas utility commissions approve rates for Duke Energy's retail natural gas service within their respective states. The state gas utility commissions, to varying degrees, have authority over the construction and operation of GU&I’s natural gas distribution facilities. CPCNs issued by the state gas utility commissions or other government agencies, as applicable, authorize GU&I to construct and operate its natural gas distribution facilities and to sell natural gas to retail and wholesale customers. Prior approval from the relevant state gas utility commission is required for GU&I to issue securities. The underlying concept of utility ratemaking is to set rates at a level that allows the utility to collect revenues equal to its cost of providing service plus a reasonable rate of return on its invested capital, including equity.

In addition to amounts collected from customers through approved base rates, each of the state gas utility commissions allow recovery of certain costs through various cost recovery clauses to the extent the respective commission determines in periodic hearings that such costs, including any past over- or under-recovered costs, are prudent.

Natural gas costs are eligible for recovery by GU&I. Due to the associated regulatory treatment and the method allowed for recovery, changes in natural gas costs from year to year have no material impact on operating results of GU&I, unless a commission finds a portion of such costs to have been imprudent. However, delays between the expenditure for natural gas and recovery from customers can adversely impact the timing of cash flows of GU&I.

The following table summarizes certain components underlying significant recently approved and effective base rates or ARM filings in the last three years.

Regulatory BodyAnnual Increase (Decrease) (in millions)Return on EquityEquity Component of Capital StructureEffective Date
Approved Rate Cases:
Duke Energy Ohio 2022 Natural Gas Base Rate CasePUCO$329.6%52.32%November 2023
Piedmont 2023 Tennessee Annual Review MechanismTPUC409.8%48.67%October 2023
Duke Energy Kentucky 2021 Natural Gas Base Rate Case(a)KPSC99.375%51.344%January 2022
Piedmont 2021 North Carolina Natural Gas Base Rate CaseNCUC679.6%51.60%November 2021
Piedmont 2020 Tennessee Natural Gas Base Rate CaseTPUC169.8%50.50%January 2021

(a) An ROE of 9.3% for natural gas riders was approved.

GU&I has an IMR mechanism in North Carolina designed to separately track and recover certain costs associated with capital investments incurred to comply with federal pipeline safety and integrity programs. Piedmont has withdrawn from the Tennessee IMR mechanism subsequent to the authorization of the Tennessee Annual Review Mechanism effective January 2022. The following table summarizes information related to the recently approved IMR filing.

CumulativeAnnualEffective
(in millions)InvestmentRevenuesDate
Piedmont 2022 IMR Filing – North Carolina$213$20December 2022

In Ohio, GU&I has a CEP Rider designed to recover costs between rate cases on PUCO approved capital expenditures. Duke Energy Ohio submits a filing each year for incremental investments to increase the revenue requirement up to the approved annual residential rate cap increase. The cumulative investment under the CEP Rider is $164 million with total annual revenue requirement of $17 million with rates effective November 1, 2023.

For more information on rate matters and other regulatory proceedings, see Note 4 to the Consolidated Financial Statements, “Regulatory Matters.”

BUSINESS

Federal

GU&I is subject to various federal regulations, including regulations that are particular to the natural gas industry. These federal regulations include but are not limited to the following:

  • Regulations of the FERC affect the certification and siting of new interstate natural gas pipeline projects, the purchase and sale of, the prices paid for, and the terms and conditions of service for the interstate transportation and storage of natural gas.

  • Regulations of the PHMSA affect the design, construction, operation, maintenance, integrity, safety and security of natural gas distribution and transmission systems.

  • Regulations of the EPA relate to the environment including proposed air emissions regulations that would expand to include emissions of methane.

Regulations of the FERC and the state gas utility commissions govern access to regulated natural gas and other data by nonregulated entities and services provided between regulated and nonregulated energy affiliates. These regulations affect the activities of nonregulated affiliates with GU&I.

Environmental

GU&I is subject to the jurisdiction of the EPA and state and local environmental agencies. For a discussion of environmental regulation, see “Environmental Matters” in this section. See “Other Matters” section of Item 7 Management's Discussion and Analysis for a discussion about potential Global Climate Change legislation and other EPA regulations under development and the potential impacts such legislation and regulation could have on Duke Energy’s operations.

OTHER

The remainder of Duke Energy’s operations is presented as Other. While it is not a business segment, Other primarily includes interest expense on holding company debt, unallocated corporate costs, certain income tax amounts, amounts related to certain companywide initiatives and contributions made to the Duke Energy Foundation. Other also includes Bison and an investment in NMC.

The Duke Energy Foundation is a nonprofit organization funded by Duke Energy shareholders that makes charitable contributions to selected nonprofits and government subdivisions.

Bison, a wholly owned subsidiary of Duke Energy, is a captive insurance company with the principal activity of providing Duke Energy subsidiaries with indemnification for financial losses primarily related to property, workers’ compensation and general liability.

Duke Energy owns a 17.5% equity interest in NMC. The joint venture company has production facilities in Jubail, Saudi Arabia, where it manufactures certain petrochemicals and plastics. NMC annually produces approximately 1 million metric tons each of MTBE and methanol and has the capacity to produce 50,000 metric tons of polyacetal. The main feedstocks to produce these products are natural gas and butane. Duke Energy records the investment activity of NMC using the equity method of accounting and retains 25% of NMC's board of directors' representation and voting rights.

Human Capital Management

Governance

Our employees are critical to the success of our company. Our Human Resources organization is responsible for our human capital management strategy, which includes recruiting and hiring, onboarding and training, diversity and inclusion, workforce planning, talent and succession planning, performance management and employee development. Key areas of focus include fostering a high-performance and inclusive culture built on strong leadership and highly engaged and diverse employees, building a pipeline of skilled workers and ensuring knowledge transfer as employees retire.

Our Board of Directors provides oversight on certain human capital management matters, primarily through the Compensation and People Development Committee, which is responsible for reviewing strategies and policies related to human capital management, including with respect to matters such as diversity and inclusion, employee engagement and talent development.

Employees

On December 31, 2023, Duke Energy had a total of 27,037 full-time, part-time and temporary employees, the majority of which were full-time employees. The total includes 5,054 employees who are represented by labor unions under various collective bargaining agreements that generally cover wages, benefits, working practices, and other terms and conditions of employment.

Compensation

The Company seeks to attract and retain an appropriately qualified workforce and leverages Duke Energy’s leadership imperatives to foster a culture focused on customers, innovation, and highly engaged employees. Our compensation program is market driven and designed to link pay to performance with the goal of attracting and retaining talented employees, rewarding individual performance, and encouraging long-term commitment to our business. Our market competitive pay program includes short-term and long-term variable pay components that help to align the interests of Duke Energy to our customers and shareholders. In addition to competitive base pay, we provide eligible employees with compensation and benefits under a variety of plans and programs, including health care benefits, retirement savings, pension, health savings and flexible spending accounts, wellness, family leaves, employee assistance, as well as other benefits including a charitable matching program. The Company is committed to providing market competitive, fair, and equitable compensation and regularly conducts internal pay equity reviews, and benchmarking against peer companies to ensure our pay is competitive.

BUSINESS

Diversity and Inclusion

Duke Energy is committed to continuing to build a diverse workforce that reflects the communities we serve while strengthening a culture of inclusion where all employees and customers feel respected and valued. Our goals include attracting and retaining the talent needed and rewarding performance to enable us to reach our strategic objectives. The Enterprise Diversity and Inclusion Council, chaired by our Executive Vice President and Chief Executive Officer, Duke Energy Florida and Midwest in 2023, monitors the effectiveness and execution of our diversity and inclusion strategy and programs. Employee-led councils are also embedded across the Company in our business units and focus on the specific diversity and inclusion needs of the business and help drive inclusion deeper into the employee experience. Leaders and individual contributors also have the opportunity to participate in voluntary diversity and inclusion training and facilitated conversations on insightful topics offered to further our commitment to building and enabling an inclusive work environment.

In 2022, our aspirational goals included achieving workforce representation of at least 25% for women and 20% for people of color. In 2023, we established new aspirational goals of 28% for women and 23% for people of color. We continue to strive toward reaching these aspirational goals and as of December 31, 2023, our workforce consisted of approximately 23.6% women and 20.5% people of color.

The Company also has 10 Employee Resource Groups (ERGs), with 38 chapters and more than 6,700 employees participating. ERGs are networks of employees formed around a common dimension of diversity whose goals and objectives align with the Company's goals and objectives. These groups focus on employee professional development and networking, community outreach, cultural awareness, recruiting and retention. They also serve as a resource to the Company for advocacy and community outreach and improving customer service through innovation. ERG-sponsored forums include networking events, mentoring, scholarship banquets for aspiring college students, and workshops on topics such as time management, stress reduction, career planning and work-life balance. Our ERGs are open to all employees.

Among other efforts, the Company has developed partnerships with community organizations, community colleges and historically Black colleges and universities (HBCUs) to support our strategy of building a diverse and highly skilled talent pipeline.

Operational Excellence

The foundation for our growth and success is our continued focus on operational excellence, the leading indicator of which is safety. As such, the safety of our workforce remains our top priority. The Company closely monitors the total incident case rate (TICR), which is a metric based on strict OSHA definitions that measures the number of occupational injuries and illnesses per 100 employees. This objective emphasizes our focus on achieving an event-free and injury-free workplace. As an indication of our commitment to safety, we include safety metrics in both the short-term and long-term incentive plans based on the TICR for employees. Our employees delivered strong safety results in 2023, consistent with our industry-leading performance levels since 2018.

BUSINESS

Information about Our Executive Officers

The following table sets forth the individuals who currently serve as executive officers. Executive officers serve until their successors are duly elected or appointed.

NameAge**(a)**Current and Recent Positions Held
Lynn J. Good64Chair, President and Chief Executive Officer. Ms. Good has served as Chair, President and Chief Executive Officer of Duke Energy since January 1, 2016, and was Vice Chairman, President and Chief Executive Officer of Duke Energy from July 2013 through December 2015. Prior to that, she served as Executive Vice President and Chief Financial Officer since 2009.
Brian D. Savoy48Executive Vice President and Chief Financial Officer. Mr. Savoy assumed his current position in September 2022. Prior to that, he served as Executive Vice President, Chief Strategy and Commercial Officer from May 2021 through August 2022; Senior Vice President, Chief Transformation and Administrative Officer from October 2019 through April 2021; Senior Vice President, Business Transformation and Technology from May 2016 through September 2019; Senior Vice President, Controller and Chief Accounting Officer from September 2013 to May 2016; Director, Forecasting and Analysis from 2009 to September 2013; and Vice President and Controller of the Commercial Power segment from 2006 to 2009.
Kodwo Ghartey-Tagoe60Executive Vice President, Chief Legal Officer and Corporate Secretary. Mr. Ghartey-Tagoe assumed his current position in May 2020. He was appointed Executive Vice President and Chief Legal Officer in October 2019 after serving as President, South Carolina since 2017. Mr. Ghartey-Tagoe joined Duke Energy in 2002 and has held numerous leadership positions in Duke Energy’s Legal Department, including Duke Energy's Senior Vice President of State and Federal Regulatory Legal Support.
T. Preston Gillespie61Executive Vice President, Chief Generation Officer and Enterprise Operational Excellence. Mr. Gillespie assumed his current position in January 2023. Prior to that, he served as the Chief Generation Officer since 2020.
R. Alexander Glenn58Executive Vice President and Chief Executive Officer, Duke Energy Florida and Midwest. Mr. Glenn assumed his current position in March 2023. Prior to that, he served as Senior Vice President and Chief Executive Officer, Duke Energy Florida and Midwest from May 2021 to March 2023; Senior Vice President, State and Federal Regulatory Legal Support from 2017 to May 2021; and State President of Duke Energy Florida's operations from 2012 to 2017.
Julia S. Janson59Executive Vice President and Chief Executive Officer, Duke Energy Carolinas. Ms. Janson assumed her current position in May 2021. Prior to that, she served as Executive Vice President, External Affairs and President, Carolinas Region since October 2019 and the position of Executive Vice President, External Affairs and Chief Legal Officer since November 2018. She originally assumed the position of Executive Vice President, Chief Legal Officer and Corporate Secretary in December 2012 and then assumed the responsibilities for External Affairs in February 2016.
Cynthia S. Lee57Vice President, Chief Accounting Officer and Controller. Ms. Lee assumed her current position in May 2021. Prior to that, she served as Director, Investor Relations since June 2019 and in various roles within the Corporate Controller's organization after joining the Corporation and its affiliates in 2002.
Ronald R. Reising63Adviser to the Chair, President, and Chief Executive Officer. Mr. Reising assumed his current position in January 2024. Prior to that, he served as Executive Vice President and Chief Human Resources Officer from April 2023 to December 2023; Senior Vice President and Chief Human Resource Officer from July 2020 to March 2023; Senior Vice President of Operations Support from 2014 to July 2020; and Chief Procurement Officer from 2006 to 2014.
Louis E. Renjel50Executive Vice President, External Affairs and Communications. Mr. Renjel assumed his current position in March 2023. Prior to that, he served as Senior Vice President, External Affairs and Communications from May 2021 to March 2023; Senior Vice President of Federal Government and Corporate Affairs from 2019 to May 2021; and Vice President, Federal Government Affairs and Strategic Policy from March 2017 to 2019. Prior to joining Duke Energy, Mr. Renjel served as Vice President of Strategic Infrastructure from 2009 to March 2017 for CSX Corp and as their Director of Environmental and Government Affairs from 2006 to 2008.
Harry K. Sideris53Executive Vice President, Customer Experience, Solutions and Services. Mr. Sideris assumed his current position in October 2019. Prior to that, he served as Senior Vice President and Chief Distribution Officer from June 2018 to October 2019; State President, Florida from January 2017 to June 2018; Senior Vice President of Environmental Health and Safety from August 2014 to January 2017; and Vice President of Power Generations for the Company's Fossil/Hydro Operations in the western portions of North Carolina and South Carolina from July 2012 to August 2014.
Steven K. Young65Executive Vice President and Chief Commercial Officer. Mr. Young assumed his current position in September 2022. Prior to that, he held the position of Executive Vice President and Chief Financial Officer from August 2013 through August 2022; Vice President, Chief Accounting Officer and Controller, assuming the role of Chief Accounting Officer in July 2012 and the role of Controller in December 2006.

(a) The ages of the officers provided are as of January 31, 2024.

There are no family relationships between any of the executive officers, nor any arrangement or understanding between any executive officer and any other person involved in officer selection.

BUSINESS

Environmental Matters

The Duke Energy Registrants are subject to federal, state and local laws and regulations with regard to air and water quality, hazardous and solid waste disposal and other environmental matters. Environmental laws and regulations affecting the Duke Energy Registrants include, but are not limited to:

  • The Clean Air Act, as well as state laws and regulations impacting air emissions, including State Implementation Plans related to existing and new national ambient air quality standards for ozone and particulate matter. Owners and/or operators of air emission sources are responsible for obtaining permits and for annual compliance and reporting.

  • The Clean Water Act, which requires permits for facilities that discharge wastewaters into navigable waters.

  • The Comprehensive Environmental Response, Compensation and Liability Act, which can require any individual or entity that currently owns or in the past owned or operated a disposal site, as well as transporters or generators of hazardous substances sent to a disposal site, to share in remediation costs.

  • The National Environmental Policy Act, which requires federal agencies to consider potential environmental impacts in their permitting and licensing decisions, including siting approvals.

  • The CCR Rule, a 2015 EPA rule establishing national regulations to provide a comprehensive set of requirements for the management and disposal of CCR from coal-fired power plants.

  • Coal Ash Act, as amended, which establishes requirements regarding the use and closure of existing ash basins, the disposal of ash at active coal plants and the handling of surface water and groundwater impacts from ash basins in North Carolina.

  • The Solid Waste Disposal Act, as amended by RCRA, which creates a framework for the proper management of hazardous and nonhazardous solid waste; classifies CCR as nonhazardous waste; and establishes standards for landfill and surface impoundment placement, design, operation and closure, groundwater monitoring, corrective action, and post-closure care.

  • The Toxic Substances Control Act, which gives EPA the authority to require reporting, recordkeeping and testing requirements, and to place restrictions relating to chemical substances and/or mixtures, including polychlorinated biphenyls.

For more information on environmental matters, see Notes 5 and 10 to the Consolidated Financial Statements, “Commitments and Contingencies – Environmental” and "Asset Retirement Obligations," respectively, and the “Other Matters” section of Item 7 Management's Discussion and Analysis. Except as otherwise described in these sections, costs to comply with current federal, state and local provisions regulating the discharge of materials into the environment or other potential costs related to protecting the environment are incorporated into the routine cost structure of our various business segments and are not expected to have a material adverse effect on the competitive position, consolidated results of operations, cash flows or financial position of the Duke Energy Registrants.

The "Other Matters" section of Item 7 Management's Discussion and Analysis includes more information on certain environmental regulations and a discussion of Global Climate Change including the potential impact of current and future legislation related to GHG emissions on the Duke Energy Registrants' operations. Recently passed and potential future environmental statutes and regulations could have a significant impact on the Duke Energy Registrants’ results of operations, cash flows or financial position. However, if and when such statutes and regulations become effective, the Duke Energy Registrants will seek appropriate regulatory recovery of costs to comply within its regulated operations.

DUKE ENERGY CAROLINAS

Duke Energy Carolinas is a regulated public utility primarily engaged in the generation, transmission, distribution and sale of electricity in portions of North Carolina and South Carolina. Duke Energy Carolinas’ service area covers approximately 24,000 square miles and supplies electric service to approximately 2.9 million residential, commercial and industrial customers. For information about Duke Energy Carolinas’ generating facilities, see Item 2, “Properties.” Duke Energy Carolinas is subject to the regulatory provisions of the NCUC, PSCSC, NRC and FERC.

Substantially all of Duke Energy Carolinas' operations are regulated and qualify for regulatory accounting. Duke Energy Carolinas operates one reportable business segment, EU&I. For additional information regarding this business segment, including financial information, see Note 3 to the Consolidated Financial Statements, “Business Segments.”

PROGRESS ENERGY

Progress Energy is a public utility holding company primarily engaged in the regulated electric utility business and is subject to regulation by the FERC. Progress Energy conducts operations through its wholly owned subsidiaries, Duke Energy Progress and Duke Energy Florida. When discussing Progress Energy’s financial information, it necessarily includes the results of Duke Energy Progress and Duke Energy Florida.

Substantially all of Progress Energy’s operations are regulated and qualify for regulatory accounting. Progress Energy operates one reportable business segment, EU&I. For additional information regarding this business segment, including financial information, see Note 3 to the Consolidated Financial Statements, “Business Segments.”

DUKE ENERGY PROGRESS

Duke Energy Progress is a regulated public utility primarily engaged in the generation, transmission, distribution and sale of electricity in portions of North Carolina and South Carolina. Duke Energy Progress’ service area covers approximately 28,000 square miles and supplies electric service to approximately 1.7 million residential, commercial and industrial customers.

For information about Duke Energy Progress’ generating facilities, see Item 2, “Properties.” Duke Energy Progress is subject to the regulatory provisions of the NCUC, PSCSC, NRC and FERC. Substantially all of Duke Energy Progress’ operations are regulated and qualify for regulatory accounting. Duke Energy Progress operates one reportable business segment, EU&I. For additional information regarding this business segment, including financial information, see Note 3 to the Consolidated Financial Statements, “Business Segments.”

PART I

DUKE ENERGY FLORIDA

Duke Energy Florida is a regulated public utility primarily engaged in the generation, transmission, distribution and sale of electricity in portions of Florida. Duke Energy Florida’s service area covers approximately 13,000 square miles and supplies electric service to approximately 2 million residential, commercial and industrial customers. For information about Duke Energy Florida’s generating facilities, see Item 2, “Properties.” Duke Energy Florida is subject to the regulatory provisions of the FPSC, NRC and FERC.

Substantially all of Duke Energy Florida’s operations are regulated and qualify for regulatory accounting. Duke Energy Florida operates one reportable business segment, EU&I. For additional information regarding this business segment, including financial information, see Note 3 to the Consolidated Financial Statements, “Business Segments.”

DUKE ENERGY OHIO

Duke Energy Ohio is a regulated public utility primarily engaged in the transmission and distribution of electricity in portions of Ohio and Kentucky, in the generation and sale of electricity in portions of Kentucky and the transportation and sale of natural gas in portions of Ohio and Kentucky. Duke Energy Ohio also conducts competitive auctions for retail electricity supply in Ohio whereby recovery of the energy price is from retail customers. Operations in Kentucky are conducted through Duke Energy Ohio's wholly owned subsidiary, Duke Energy Kentucky. References herein to Duke Energy Ohio include Duke Energy Ohio and its subsidiaries, unless otherwise noted. Duke Energy Ohio is subject to the regulatory provisions of the PUCO, KPSC, PHMSA and FERC.

Duke Energy Ohio’s service area covers approximately 3,000 square miles and supplies electric service to approximately 910,000 residential, commercial and industrial customers and provides transmission and distribution services for natural gas to approximately 560,000 customers. For information about Duke Energy Ohio's generating facilities and natural gas distribution facilities, see Item 2, “Properties.”

KO Transmission, a wholly owned subsidiary of Duke Energy Ohio, is an interstate pipeline company engaged in the business of transporting natural gas and is subject to the rules and regulations of FERC. KO Transmission's 90-mile pipeline supplies natural gas to Duke Energy Ohio and interconnects with the Columbia Gulf Transmission pipeline and Tennessee Gas Pipeline. An approximately 70-mile portion of KO Transmission's pipeline facilities was co-owned by Columbia Gas Transmission, LLC. KO Transmission sold all of its pipeline facilities and related real property to Columbia Gas Transmission, LLC on February 1, 2023, for approximately book value.

Substantially all of Duke Energy Ohio's operations are regulated and qualify for regulatory accounting. Duke Energy Ohio has two reportable segments, EU&I and GU&I. For additional information on these business segments, including financial information, see Note 3 to the Consolidated Financial Statements, “Business Segments.”

DUKE ENERGY INDIANA

Duke Energy Indiana is a regulated public utility primarily engaged in the generation, transmission, distribution and sale of electricity in portions of Indiana. Duke Energy Indiana’s service area covers approximately 23,000 square miles and supplies electric service to approximately 900,000 residential, commercial and industrial customers. For information about Duke Energy Indiana's generating facilities, see Item 2, “Properties.” Duke Energy Indiana is subject to the regulatory provisions of the IURC and FERC.

In 2021, Duke Energy executed an agreement providing for an investment in Duke Energy Indiana by GIC. The transaction was completed following two closings. For additional information, see Note 2 to the Consolidated Financial Statements, "Dispositions."

Substantially all of Duke Energy Indiana’s operations are regulated and qualify for regulatory accounting. Duke Energy Indiana operates one reportable business segment, EU&I. For additional information regarding this business segment, including financial information, see Note 3 to the Consolidated Financial Statements, “Business Segments.”

PIEDMONT

Piedmont is a regulated public utility primarily engaged in the distribution of natural gas to approximately 1.2 million residential, commercial, industrial and power generation customers in portions of North Carolina, South Carolina and Tennessee, including customers served by municipalities who are wholesale customers. For information about Piedmont's natural gas distribution facilities, see Item 2, "Properties." Piedmont is subject to the regulatory provisions of the NCUC, PSCSC, TPUC, PHMSA and FERC.

Substantially all of Piedmont’s operations are regulated and qualify for regulatory accounting. Piedmont operates one reportable business segment, GU&I. For additional information regarding this business segment, including financial information, see Note 3 to the Consolidated Financial Statements, “Business Segments.”

Previous: Cover and table of contents · Next: Item 1A. RISK FACTORS