Item 2. Properties

Our executive offices are located in Redwood City, California, with additional offices in several cities throughout the Americas, EMEA and Asia-Pacific regions.

The following tables present the locations of our leased and owned IBX data centers and xScaleTM data centers as of December 31, 2025.

AMERICAS
MetroLeased (1)Owned (1) (2)
Atlanta●●
Bogotá●
AM.jpgBoston●
Calgary●●
Chicago●●
Culpeper●
Dallas●●
Washington, D.C./Ashburn●●
Denver●●
Houston●
Kamloops●
Lima●
Los Angeles●●
Mexico City●
Miami●●
Monterrey●●
Montreal●
New York●●
Ottawa●
Philadelphia●
Rio de Janeiro●●
Saint John●
Santiago●
São Paulo●
Seattle●●
Silicon Valley●●
Toronto●●
Vancouver●
Winnipeg●
EMEA
MetroLeased (1)Owned (1) (2)
Abidjan●
Abu Dhabi●
Accra●
Amsterdam●●
EU.jpgBarcelona●●
Bordeaux●
Dubai●●
Dublin●●
Düsseldorf●
East Netherlands●
Frankfurt●●
Geneva●●
Genoa●
Hamburg●
Helsinki●●
Istanbul●
Johannesburg●
Lagos●
Lisbon●
London●●
Madrid●●
Manchester●●
Milan●●
Munich●●
Muscat●
Paris●●
Salalah●
Sofia●
Stockholm●●
Warsaw●●
Zurich●●
AP.jpg
Asia-Pacific
MetroLeased (1)Owned (1) (2)
Adelaide●
Brisbane●
Canberra●
Chennai●
Hong Kong●
Jakarta●
Johor●
Kuala Lumpur●
Manila●
Melbourne●
Mumbai●●
Osaka●●
Perth●
Seoul●●
Shanghai●●
Singapore●●
Sydney●●
Tokyo●●

(1)"●" denotes locations with one or more data centers.

(2)Owned sites include IBX data centers and xScale data centers subject to long-term ground leases.

The following table presents an overview of our portfolio of IBX data centers as of December 31, 2025:

# of IBXs (1)Total Cabinet Capacity (1)(2)Cabinets Billed (1)Cabinet Utilization % (1)(3)MRR per Cabinet (1)(4)
Americas109157,400123,70079%$2,694
EMEA88141,300107,20076%2,418
Asia-Pacific5893,60068,40073%2,355
Total255392,300299,300

(1)Excludes 25 unconsolidated data centers (23 xScale data centers and the MC1 and SN1 IBX data centers).

(2)Cabinets represent a specific amount of space within an IBX data center. Customers can combine and use multiple adjacent cabinets within an IBX data center, depending on their space requirements.

(3)The cabinet utilization rate represents the percentage of cabinet space billed versus total cabinet capacity, taking into consideration power limitations.

(4)MRR per cabinet represents average monthly recurring revenue recognized divided by the average number of cabinets billed during the fourth quarter of the year. Americas MRR per cabinet excludes Infomart non-IBX tenant income.

The following table presents a summary of our significant IBX data center projects under construction as of December 31, 2025:

PropertyProperty LocationTarget Open DateSellable CabinetsTotal Capex (in millions) (1)
Americas:
NY11 phase 5New YorkQ1 2026600$38
BG2 phase 2BogotáQ2 202655028
SV18 phase 1Silicon ValleyQ2 20262,100260
MI1 redevelopmentMiamiQ3 202647559
MT1 phase 3MontrealQ4 202630037
RJ3 phase 2Rio de JaneiroQ4 202655046
SP7 phase 1São PauloQ4 202660035
SP4 phase 5São PauloQ2 202770074
DC17 phases 1 and 2Washington, D.C.Q2 20274,700622
DC22 phase 2Washington, D.C.Q2 20272,125144
SV18 phase 2Silicon ValleyQ2 2027850180
TR6 phase 3TorontoQ3 20271,075123
CH5 phase 2ChicagoQ3 20271,625165
DA12 phase 1DallasQ2 20283,700837
19,9502,648
EMEA:
LG3 phase 1LagosQ1 202622522
DX3 phase 2DubaiQ2 202680081
MD5 phase 1MadridQ2 20261,650115
IL3 phase 1IstanbulQ3 20261,325116
FR8 phase 3FrankfurtQ4 20261,400107
LD14 phase 1LondonQ1 20271,425242
PA14 phase 1ParisQ2 2027675104
LS2 phase 2LisbonQ3 202732531
ZH4 phase 6ZurichQ3 202720047
LG4 phase 1LagosQ4 202797578
DB10 phase 1DublinQ1 202847514
LD14 phase 2LondonQ1 20281,425122
FR12 phase 1FrankfurtQ2 20281,750381
MU4 phase 3MunichQ2 20281,375342
PA14 phase 2ParisQ2 202860049
FR15 phase 1FrankfurtQ3 20281,550487
16,1752,338
Asia-Pacific:
HK6 phase 1Hong KongQ1 20261,000124
OS3 phase 4OsakaQ1 202655030
JK1 phase 2JakartaQ4 20261,12539
SG6 phase 1SingaporeQ1 20271,550290
SY5 phase 4SydneyQ1 20271,35096
KL2 phases 1 and 2Kuala LumpurQ2 20272,200192
MB3 phase 2MumbaiQ2 20271,37538
BK1 phase 1BangkokQ3 20271,175110
JH2 phases 1 and 2JohorQ3 20272,225201
CN1 phase 2ChennaiQ4 20271,37588
OS6 phase 1OsakaQ4 20281,850355
15,7751,563
Total51,900$6,549

(1)Capital expenditures are approximate and may change based on final construction details.