Item 3. Legal Proceedings
5K characters. Original on sec.gov · Markdown
Item 3. Legal Proceedings
- Yankee Companies v. U.S. Department of Energy
DOE Phase I Damages - In 1998, the Yankee Companies filed separate complaints against the DOE in the Court of Federal Claims seeking monetary damages resulting from the DOE's failure to begin accepting spent nuclear fuel for disposal by January 31, 1998 pursuant to the terms of the 1983 spent fuel and high-level waste disposal contracts between the Yankee Companies and the DOE ("DOE Phase I Damages"). Phase I covered damages for the years 1998 through 2002. Following multiple appeals and cross-appeals in December 2012, the judgment awarding $39.6 million, $38.3 million and $81.7 million to CYAPC, YAEC and MYAPC, respectively, became final.
In January 2013, the proceeds from the DOE Phase I Damages Claim were received by the Yankee Companies and transferred to each Yankee Company's respective decommissioning trust.
In June 2013, FERC approved CYAPC, YAEC and MYAPC to reduce rates in their wholesale power contracts through the application of the DOE proceeds for the benefit of customers. Changes to the terms of the wholesale power contracts became effective on July 1, 2013. In accordance with the FERC order, CL&P, NSTAR Electric, PSNH and WMECO began receiving the benefit of the DOE proceeds, and the benefits have been passed on to customers.
On September 17, 2014, in accordance with the MYAPC refund plan, MYAPC returned a portion of the DOE Phase I Damages proceeds to the member companies, including CL&P, NSTAR Electric, PSNH, and WMECO, in the amount of $3.2 million, $1.1 million, $1.4 million and $0.8 million, respectively.
DOE Phase II Damages - In December 2007, the Yankee Companies each filed subsequent lawsuits against the DOE seeking recovery of actual damages incurred related to the alleged failure of the DOE to provide for a permanent facility to store spent nuclear fuel generated in years 2001 through 2008 for CYAPC and YAEC and from 2002 through 2008 for MYAPC ("DOE Phase II Damages"). In November 2013, the court issued a final judgment awarding $126.3 million, $73.3 million, and $35.8 million to CYAPC, YAEC and MYAPC, respectively. On January 14, 2014, the Yankee Companies received a letter from the U.S. Department of Justice stating that the DOE will not appeal the court's final judgment.
In March and April 2014, CYAPC, YAEC and MYAPC received payment of $126.3 million, $73.3 million and $35.8 million, respectively, of the DOE Phase II Damages proceeds and made the required informational filing with FERC in accordance with the process and methodology outlined in the 2013 FERC order. The Yankee Companies returned the DOE Phase II Damages proceeds to the member companies, including CL&P, NSTAR Electric, PSNH, and WMECO, for the benefit of their respective customers, on June 1, 2014. Refunds to CL&P's, NSTAR Electric's, PSNH's and WMECO's customers for these DOE proceeds began in the third quarter of 2014 and all refunds under these proceedings have been disbursed.
DOE Phase III Damages - In August 2013, the Yankee Companies each filed subsequent lawsuits against the DOE seeking recovery of actual damages incurred in the years 2009 through 2012 ("DOE Phase III"). The DOE Phase III trial concluded on July 1, 2015, followed by a post-trial briefing that concluded on October 4, 2015. On March 25, 2016, the court issued its decision and awarded CYAPC, YAEC and MYAPC damages of $32.6 million, $19.6 million and $24.6 million, respectively. In total, the Yankee Companies were awarded $76.8 million of the $77.9 million in damages sought in the DOE Phase III. The decision became final on July 18, 2016, and the Yankee Companies received the awards from the DOE on October 14, 2016. The Yankee Companies received FERC approval of their proposed distribution of certain amounts of the awarded damages proceeds to member companies, including CL&P, NSTAR Electric, PSNH, and WMECO, which CYAPC and MYAPC made in December 2016. MYAPC also refunded $56.5 million from its spent nuclear fuel trust, a portion of which was also refunded to the Eversource utility subsidiaries. In total, Eversource received $26.1 million, of which CL&P, NSTAR Electric, PSNH and WMECO received $13.6 million, $5.0 million, $3.9 million, and $3.6 million, respectively. These amounts will be refunded to the customers of the respective Eversource utility subsidiaries.
- Other Legal Proceedings
For further discussion of legal proceedings, see Item 1, Business: "– Electric Distribution Segment," "– Electric Transmission Segment," and "– Natural Gas Distribution Segment" for information about various state and federal regulatory and rate proceedings, civil lawsuits related thereto, and information about proceedings relating to power, transmission and pricing issues; "– Nuclear Fuel Storage" for information related to nuclear waste; and "– Other Regulatory and Environmental Matters" for information about proceedings involving water and air quality requirements, toxic substances and hazardous waste, electric and magnetic fields, and other matters. In addition, see Item 1A, Risk Factors, for general information about several significant risks.