Item 2. PROPERTIES
5K characters. Original on sec.gov · Markdown
Item 2. PROPERTIES
Note – Information in this section is as of December 31, 2019, unless otherwise noted.
We own the following facilities in Winona, Minnesota:
| Purpose | Tote Locations (ASRS)(1) | Approximate Square Feet | ||||
| Distribution center and home office (2) | 246,000 | 259,000 | ||||
| Manufacturing facility | 100,000 | |||||
| Computer support center | 13,000 | |||||
| Winona branch | 15,000 | |||||
| Winona product support facility | 55,000 | |||||
| Rack and shelving storage | 42,000 | |||||
| Multi-building complex which houses certain operations of the distribution group, the support services group, and the home office support group | 30,000 | |||||
| Customer Experience Center | 100,000 |
(1) Total number of tote locations for small parts storage included in facilities with an ASRS.
(2) During 2018, we acquired land for future expansion of our home office.
We own the following facilities, excluding selling locations, outside of Winona, Minnesota:
| Purpose | Location | Tote Locations (ASRS)(1) | Approximate Square Feet | |||
| Distribution center | Indianapolis, Indiana | 547,000 | (2) | 1,039,000 | ||
| Manufacturing facility | Indianapolis, Indiana | 220,000 | ||||
| Distribution center | Akron, Ohio | 103,000 | 182,000 | |||
| Distribution center | Scranton, Pennsylvania | 104,000 | 189,000 | |||
| Distribution center | Denton, Texas | 41,000 | (3) | 176,000 | ||
| Manufacturing facility (built in 2019) | Houston, Texas | 120,000 | ||||
| Distribution center | Atlanta, Georgia | 77,000 | 198,000 | |||
| Distribution center (built in 2019) | Seattle, Washington | 140,000 | 246,000 | |||
| Distribution center and manufacturing facility | Modesto, California | 69,000 | 328,000 | |||
| Distribution center | High Point, North Carolina | 132,000 | 301,000 | |||
| Distribution center (4) | High Point, North Carolina | — | 350,000 | |||
| Distribution center | Kansas City, Kansas | 170,000 | 468,000 | |||
| Distribution center (5) | Kitchener, Ontario, Canada | 128,000 | 142,000 | |||
| Distribution center (built in 2019) | Jackson, Mississippi | — | 269,000 | |||
| Manufacturing facility | Wallingford, Connecticut | 187,000 | ||||
| Manufacturing facility | Rockford, Illinois | 100,000 | ||||
| Local re-distribution center and manufacturing facility | Johor, Malaysia | 27,000 |
(1) Total number of tote locations for small parts storage included in facilities with an ASRS.
(2) This property contains an ASRS with capacity of 52,000 pallet locations, in addition to the 547,000 tote locations for small parts.
(3) This facility contains an ASRS with capacity of 14,000 pallet locations, in addition to the 41,000 tote locations for small parts.
(4) In late December 2018, we purchased an additional distribution center in High Point, North Carolina with approximately 750,000 total square feet. Approximately 400,000 square feet will continue to be leased by the previous owner for three years. We began utilizing approximately 350,000 square feet for distribution activities in early 2019.
(5) In late 2019, we began an expansion project at our Kitchener, Ontario, Canada distribution center. This project will add approximately 80,000 square feet of distribution capacity and is scheduled for completion in 2020.
In addition, we own 173 buildings that house our in-market locations in various cities throughout North America.
All other buildings we occupy are leased. Leased branches range from approximately 3,000 to 10,000 square feet, with lease terms of up to 60 months (most initial lease terms are for 36 to 48 months). In addition to our leased branch locations, we also lease the following facilities:
| Purpose | Location | Approximate Square Feet | Lease Expiration Date | Remaining Lease Renewal Options | ||||
| Distribution center | Salt Lake City, Utah | 74,000 | July 2022 | One | ||||
| Distribution center | Salt Lake City, Utah | 56,000 | July 2022 | One | ||||
| Distribution center and packaging facility | Salt Lake City, Utah | 26,000 | July 2022 | One | ||||
| Distribution center and manufacturing facility | Edmonton, Alberta, Canada | 45,000 | July 2020 | None | ||||
| Distribution center | Apodaca, Nuevo Leon, Mexico | 46,000 | March 2020 | Three | ||||
| Local re-distribution center and manufacturing facility | Modrice, Czech Republic | 17,000 | April 2022 | None |
We currently own land for future distribution center expansion and development. If economic conditions are suitable in the future, we will consider purchasing branch locations to house our older branches. It is anticipated the majority of new branch locations will continue to be leased. It is our policy to negotiate relatively short lease terms to facilitate relocation of particular branch operations, when desirable. Our experience has been that there is sufficient space suitable for our needs and available for leasing.
Previous: Item 1B. UNRESOLVED STAFF COMMENTS · Next: Item 3. LEGAL PROCEEDINGS