Item 2. — PROPERTIES
7K characters. Original on sec.gov · Markdown
Item 2. — PROPERTIES
We own an approximately 63-acre parcel of land on which our Las Vegas Operating Properties are located and an approximately 19-acre parcel of land located to the east of the 63-acre parcel. We own these parcels of land in fee simple, subject to certain easements, encroachments and other non-monetary encumbrances. LVSLLC’s senior secured credit facility and LVSC’s senior notes are, subject to certain exceptions, collateralized by a first priority security interest (subject to permitted liens) in substantially all of LVSLLC’s property.
We have received concessions from the Macau government to build on a six-acre land site for the Sands Macao and parcels 1, 2 and 3 on the Cotai Strip, including the sites on which The Venetian Macao (parcel 1) and Four Seasons Macao (parcel 2) are located. We do not own these land sites in Macau; however, the land concessions grant us exclusive use of the land. As specified in the land concessions, we are required to pay premiums, which are either payable in a single lump sum upon acceptance of our land concession by the Macau government or in seven semi-annual installments (provided that the outstanding balance is due upon the completion of the corresponding integrated resort), as well as annual rent for the term of the land concession, which may be revised every five years by the Macau government. In October 2008, the Macau government amended our land concession to separate the retail and hotel portions of the Four Seasons Macao parcel and allowed us to subdivide the parcel into four separate components, consisting of retail, hotel/casino, Four Seasons Apartments and parking areas. In consideration for the amendment, we paid an additional land premium of approximately $17.8 million and will pay adjusted annual rent over the remaining term of the concession, which increased slightly due to the revised allocation of parcel use. See “Item 8 — Financial Statements and Supplementary Data — Notes to Consolidated Financial Statements — Note 6 — Leasehold Interests in Land, Net” for more information on our payment obligation under these land concessions.
Under our land concession for parcel 3, we were initially required to complete the corresponding development by August 2011. The Macau government has granted us a two-year extension to complete the development of parcel 3, which now must be completed by April 2013. We believe that if we are not able to complete the development by the revised deadline, we will be able to obtain another extension from the Macau government; however, no assurances can be given that an additional extension will be granted. If we are unable to meet the April 2013 deadline and that deadline is not extended, we could lose our land concession for parcel 3, which would prohibit us from operating any facilities developed under the land concession for parcel 3. As a result, we could forfeit all or a substantial portion of our $35.7 million in capitalized costs, as of December 31, 2009, related to our development on parcel 3.
In November 2009, we received the final draft of the land concession agreement from the Macau government for parcels 5 and 6. We have formally accepted the terms and conditions of the draft land concession and have made an initial premium payment of 700.0 million patacas (approximately $87.6 million at exchange rates in effect on December 31, 2009). The land concession will not become effective until the date it is published in Macau’s Official Gazette. Once the land concession becomes effective, we will be required to make additional land premium and annual rent payments in the amounts and at the times specified in the land concession. The land concession requires us to complete the development of the integrated resort on parcels 5 and 6 within 48 months of the date it is published in Macau’s Official Gazette. If we are not able to meet this deadline, we will need to obtain an extension to complete the development on parcels 5 and 6; however, no assurances can be given that such extension will be granted. If we are unable to the meet the deadline and that deadline is not extended, we could lose our land concession for parcels 5 and 6, which would prohibit us from operating any facilities developed under the land concession. As a result, we could forfeit all or a substantial part of our $1.73 billion in capitalized costs, as of December 31, 2009, related to our development on parcels 5 and 6.
We do not yet have all of the necessary Macau government approvals to develop our planned Cotai Strip developments on parcels 3, 5, 6, 7 and 8. We have received a land concession for parcel 3 and will negotiate the land concession for parcels 7 and 8 once the land concession for parcels 5 and 6, as previously noted, is finalized. Based on historical experience with the Macau government with respect to our land concessions for the Sands Macao and parcels 1, 2, 3, 5 and 6, management believes that the land concessions for parcels 7 and 8 will be granted; however, if we do not obtain these land concessions, we could forfeit all or a substantial part of our $116.2 million in capitalized costs, as of December 31, 2009, related to our developments on parcels 7 and 8.
Table of Contents
Under the Development Agreement with the STB to build and operate the Marina Bay Sands in Singapore, we paid SGD 1.2 billion (approximately $854.3 million at exchange rates in effect on December 31, 2009) in premium payments for the 60-year lease of the land on which the integrated resort is being developed plus an additional SGD 105.6 million (approximately $75.2 million at exchange rates in effect on December 31, 2009) for various taxes and other fees. Of this combined amount, $880.2 million has been capitalized on the consolidated balance sheet as leasehold interest in land with $49.3 million amortized as of December 31, 2009.
The Sands Bethlehem development is located on the site of the historic Bethlehem Steel Works in Bethlehem, Pennsylvania, which is about 70 miles from midtown Manhattan, New York. In September 2008, our joint venture partner, Bethworks Now, contributed the land on which Sands Bethlehem is being developed to Sands Bethworks Gaming and Sands Bethworks Retail, a portion of which was contributed through a condominium form of ownership.
In March 2004, we entered into a long-term lease with a third party for the airspace over which a portion of The Shoppes at The Palazzo was constructed (the “Leased Airspace”). We acquired fee title from the same third party to the airspace above the Leased Airspace (the “Acquired Airspace”) in order to build the St. Regis Residences in January 2008. In February 2008, in connection with the sale of The Shoppes at The Palazzo, GGP acquired control of the Leased Airspace. We continue to retain fee title to the Acquired Airspace in order to resume building the St. Regis Residences when market conditions improve.
Previous: Item 1B. — UNRESOLVED STAFF COMMENTS · Next: Item 3. — LEGAL PROCEEDINGS