Item 2. — PROPERTIES

6K characters. Original on sec.gov · Markdown

Item 2. — PROPERTIES

We own an approximately 63-acre parcel of land on which our Las Vegas Operating Properties are located and an approximately 19-acre parcel of land located to the east of the 63-acre parcel. We own these parcels of land in fee simple, subject to certain easements, encroachments and other non-monetary encumbrances. LVSLLC’s senior secured credit facility and LVSC’s senior notes are, subject to certain exceptions, collateralized by a first priority security interest (subject to permitted liens) in substantially all of LVSLLC’s property.

We have received concessions from the Macau government to build on a six-acre land site for the Sands Macao and parcels 1, 2, 3 and 5 and 6 on the Cotai Strip, including the sites on which The Venetian Macao (parcel 1) and Four Seasons Macao (parcel 2) are located. We do not own these land sites in Macau; however, the land concessions grant us exclusive use of the land. As specified in the land concessions, we are required to pay premiums, which are either payable in a single lump sum upon acceptance of our land concessions by the Macau government or in seven semi-annual installments (provided that the outstanding balance is due upon the completion of the corresponding integrated resort), as well as annual rent for the term of the land concession, which may be revised every five years by the Macau government. In October 2008, the Macau government amended our land concession to separate the retail and hotel portions of the Four Seasons Macao parcel and allowed us to subdivide the parcel into four separate components, consisting of retail, hotel/casino, Four Seasons Apartments and parking areas. In consideration for the amendment, we paid an additional land premium of approximately $17.8 million and will pay adjusted annual rent over the remaining term of the concession, which increased slightly due to the revised allocation of parcel use. See “Item 8 — Financial Statements and Supplementary Data — Notes to Consolidated Financial Statements — Note 6 — Leasehold Interests in Land, Net” for more information on our payment obligation under these land concessions. During December 2010, we received notice from the Macau government that our application for a land concession for parcels 7 and 8 was not approved and we applied to the Chief Executive of Macau for a review of the decision. Subsequent to December 31, 2010, we filed an appeal with the Court of Second Instance in Macau, which has yet to issue a decision. Should we win our appeal, it is still possible for the Chief Executive of Macau to again deny the land concession based upon public policy considerations. If we do not obtain the land concession or do not receive full reimbursement of our capitalized investment in this project, we would record a charge for all or some portion of the $102.1 million in capitalized construction costs, as of December 31, 2010, related to our development on parcels 7 and 8.

Under our land concession for parcel 3, we were initially required to complete the corresponding development by August 2011. The Macau government has granted us a two-year extension to complete the development of parcel 3, which now must be completed by April 2013. The land concession for parcels 5 and 6 contains a similar requirement that the corresponding development be completed by May 2014 (48 months from the date the land concession became effective). We believe that if we are not able to complete the developments by the respective deadlines, we will likely be able to obtain extensions from the Macau government; however, no assurances can be given that additional extensions will be granted. If we are unable to meet the applicable deadlines and those deadlines are not extended, we could lose our land concessions for parcels 3 or 5 and 6, which would prohibit us from operating any facilities developed under the respective land concessions. As a result, we could record a charge for all or some portion of the $34.3 million and $2.01 billion in capitalized construction costs, as of December 31, 2010, related to our developments on parcels 3 or 5 and 6, respectively.

Table of Contents

Under the Development Agreement with the STB to build and operate the Marina Bay Sands in Singapore, we paid SGD 1.2 billion (approximately $930.2 million at exchange rates in effect on December 31, 2010) in premium payments for the 60-year lease of the land on which the integrated resort is being developed plus an additional SGD 105.6 million (approximately $81.9 million at exchange rates in effect on December 31, 2010) for various taxes and other fees.

The Sands Bethlehem resort is located on the site of the historic Bethlehem Steel Works in Bethlehem, Pennsylvania, which is about 70 miles from midtown Manhattan, New York. In September 2008, our joint venture partner, Bethworks Now, contributed the land on which Sands Bethlehem is being developed to Sands Bethworks Gaming and Sands Bethworks Retail, a portion of which was contributed through a condominium form of ownership.

In March 2004, we entered into a long-term lease with a third party for the airspace over which a portion of The Shoppes at The Palazzo was constructed (the “Leased Airspace”). We acquired fee title from the same third party to the airspace above the Leased Airspace (the “Acquired Airspace”) in order to build the Las Vegas Condo Tower in January 2008. In February 2008, in connection with the sale of The Shoppes at The Palazzo, GGP acquired control of the Leased Airspace. We continue to retain fee title to the Acquired Airspace in order to resume building the Las Vegas Condo Tower when market conditions improve.