We have received concessions from the Macao government to build on a six-acre land site for the Sands Macao and parcels 1, 2, 3 and 5 and 6 on the Cotai Strip, including the sites on which The Venetian Macao (parcel 1), Four Seasons Macao (parcel 2) and Sands Cotai Central (parcels 5 and 6) are located. We do not own these land sites in Macao; however, the land concessions grant us exclusive use of the land. As specified in the land concessions, we are required to pay premiums, which are either payable in a single lump sum upon acceptance of our land concessions by the Macao government or in seven semi-annual installments, as well as annual rent for the term of the land concession, which may be revised every five years by the Macao government. In October 2008, the Macao government amended our land concession to separate the retail and hotel portions of the Four Seasons Macao parcel and allowed us to subdivide the parcel into four separate components, consisting of retail, hotel/casino, Four Seasons Apartments and parking areas. In consideration for the amendment, we paid an additional land premium of approximately $17.8 million and will pay adjusted annual rent over the remaining term of the concession, which increased slightly due to the revised allocation of parcel use. See “Item 8 — Financial Statements and Supplementary Data — Notes to Consolidated Financial Statements — Note 6 — Leasehold Interests in Land, Net” for more information on our payment obligation under these land concessions. In December 2010, we received notice from the Macao government that our application for a land concession for parcels 7 and 8 was not approved and we applied to the Chief Executive of Macao for an executive review of the decision. In January 2011, we filed a judicial appeal with the Court of Second Instance in Macao, which has yet to issue a decision. Should we win our judicial appeal, it is still possible for the Chief Executive of Macao to again deny the land concession based upon public policy considerations. If we do not obtain the land concession or do not receive full reimbursement of our capitalized investment in this project, we would record a charge for all or some portion of the $101.1 million in capitalized construction costs, as of December 31, 2011, related to our development on parcels 7 and 8.

Under our land concession for parcel 3, we were initially required to complete the corresponding development by August 2011. The Macao government has granted us a two-year extension to complete the development of parcel 3, which now must be completed by April 2013. The land concession for Sands Cotai Central contains a similar requirement that the corresponding development be completed by May 2014 (48 months from the date the land concession became effective). We intend to apply for an extension from the Macao government to complete our parcel 3 development as we will be unable to meet the April 2013 deadline. Should we determine that we are unable to complete Sands Cotai Central by May 2014, we also intend to apply for an extension from the government. No assurances can be given that additional extensions will be granted. If we are unable to meet the applicable deadline for Sands Cotai Central and the deadlines for either development are not extended, we could lose our land concessions for parcel 3 or Sands Cotai Central, which would prohibit us from operating any facilities developed under the respective land concessions. As a result, we could record a charge for all or some portion of the $96.0 million and $3.06 billion in capitalized construction costs, as of December 31, 2011, related to our development on parcels 3 or Sands Cotai Central, respectively.

Table of Contents

Under the Development Agreement with the STB to build and operate the Marina Bay Sands in Singapore, we paid SGD 1.2 billion (approximately $923.2 million at exchange rates in effect on December 31, 2011) in premium payments for the 60-year lease of the land on which the integrated resort is being developed plus an additional SGD 105.6 million (approximately $81.2 million at exchange rates in effect on December 31, 2011) for various taxes and other fees.

We own an approximately 63-acre parcel of land on which our Las Vegas Operating Properties are located and an approximately 19-acre parcel of land located to the east of the 63-acre parcel. We own these parcels of land in fee simple, subject to certain easements, encroachments and other non-monetary encumbrances. LVSLLC’s senior secured credit facility and LVSC’s senior notes are, subject to certain exceptions, collateralized by a first priority security interest (subject to permitted liens) in substantially all of LVSLLC’s property.

The Sands Bethlehem resort is located on the site of the historic Bethlehem Steel Works in Bethlehem, Pennsylvania, which is about 70 miles from midtown Manhattan, New York. In September 2008, our joint venture partner, Bethworks Now, LLC, contributed the land on which Sands Bethlehem is being developed to Sands Bethworks Gaming and Sands Bethworks Retail, a portion of which was contributed through a condominium form of ownership.

In March 2004, we entered into a long-term lease with a third party for the airspace over which a portion of The Shoppes at The Palazzo was constructed (the “Leased Airspace”). We acquired fee title from the same third party to the airspace above the Leased Airspace (the “Acquired Airspace”) in order to build the Las Vegas Condo Tower in January 2008. In February 2008, in connection with the sale of The Shoppes at The Palazzo, GGP acquired control of the Leased Airspace. We continue to retain fee title to the Acquired Airspace in order to resume building the Las Vegas Condo Tower when market conditions improve.