Item 3. Legal Proceedings.

4K characters. Original on sec.gov · Markdown

Item 3. Legal Proceedings.

Environmental Matters

From time to time we and our joint ventures receive notices or inquiries from government entities regarding alleged violations of environmental laws and regulations pertaining to, among other things, the disposal, emission and storage of chemical and petroleum substances, including hazardous wastes. Item 103 of the SEC’s Regulation S-K requires disclosure of certain environmental matters when a governmental authority is a party to the proceedings and the proceedings involve potential monetary sanctions that we reasonably believe could exceed $100,000. The matters below are disclosed solely pursuant to that requirement.

In September 2013, the Environmental Protection Agency (“EPA”) Region V issued a Notice and Finding of Violation alleging violations at our Morris, Illinois facility related to flaring activity. The notice generally alleges failures to monitor steam usage and improper flare operations. Region V indicated at a December 2017 meeting that it intends to issue an administrative enforcement order in 2018. We reasonably believe that EPA Region V may assert a penalty demand in excess of $100,000. A Tolling Agreement was signed in November 2018.

In June 2014, EPA Region V issued a Notice and Finding of Violation alleging violations at our Tuscola, Illinois facility related to flaring activity. The notice generally alleges failure to conduct a valid performance test and improper flare operations. In June 2018, Region V issued a draft administrative consent order that requires the completion of certain activities. We are currently engaged in discussions with Region V regarding a proposed penalty. We reasonably believe that the penalty may exceed $100,000. A Tolling Agreement was signed in November 2018.

The EPA has been conducting an enforcement initiative regarding flare emissions at petrochemical plants. In July 2014, we received Clean Air Act section 114 information request regarding flares at four U.S. facilities. In response to the information we provided and subsequent discussions, the EPA and Department of Justice (the “DOJ”) have indicated that they are seeking a consent decree that would require certain corrective measures. We reasonably believe that resolution of this matter will involve payment of a monetary sanction in excess of $100,000. We continue to work with the EPA and DOJ to resolve this matter.

In January 2018, Houston Refining, LP learned that the Texas Commission on Environmental Quality had referred an environmental matter to the Texas Attorney General’s office (“TAGO”) for enforcement. The environmental matter referred to TAGO for enforcement stems from air emissions events sustained at the refinery. In June 2018, Houston Refining, LP and TAGO agreed to a settlement involving $680,000 in penalties, plus attorneys’ fees and certain injunctive relief. To effectuate the settlement, the TAGO filed a complaint along with the proposed agreed final judgment in Travis County Court. The court entered the Agreed Final Judgment in October 2018 and the penalty has been paid in full.

In March 2018, the Morris facility learned that the Illinois EPA referred an environmental matter to the Illinois Attorney General’s Office. The matters referred for enforcement relate to air emission events at the facility. In June 2018, the parties agreed to resolve the matter for a penalty of $125,000, and in August 2018, a consent order requiring the same was entered in Grundy County Court.

On March 21, 2018, the Cologne, Germany local court issued a regulatory fine notice of €1,800,000 arising from a pipeline leak in our Wesseling, Germany facility. We expect the Cologne prosecutor to issue a corresponding payment request, which will resolve the matter.

Litigation and Other Matters

Information regarding our litigation and other legal proceedings can be found in Note 19, Commitments and Contingencies, to the Consolidated Financial Statements.