Item 3. Legal Proceedings
8K characters. Original on sec.gov · Markdown
Item 3. Legal Proceedings
With the exception of the below, we are not a party to any material, pending legal proceedings or claims at December 31, 2023. From time-to-time, we may be a party to, or otherwise involved in, legal proceedings arising in the normal course of business. The nature of our business ordinarily results in a certain amount of pending as well as threatened claims, litigation, investigations, regulatory and legal and administrative cases, matters and proceedings, all of which are considered incidental to the normal conduct of business. When we determine that we have meritorious defenses to the claims asserted, we vigorously defend ourself. We consider settlement of cases when, in management’s judgment, it is in the best interests of both Vertiv and its shareholders to do so.
On August 3, 2021, an American Arbitration Association arbitration hearing commenced with respect to a 2018 claim filed by Vertiv against SVO Building One, LLC (“SVO”) alleging damages of approximately $12.0 with respect to (i) unremitted payment for work and materials in connection with the design, engineering, procurement, installation, construction, and commissioning of a data center located in Sacramento, California and (ii) damages and injunctive relief relating to SVO’s unauthorized use of Vertiv’s intellectual property and work product. SVO filed a counterclaim in 2018 alleging damages of approximately $18.0 relating to (i) allegations that Vertiv was not a duly licensed contractor at all times during the project in violation of California’s contractor license regulations, (ii) breach of warranty, and (iii) gross negligence. On September 3, 2021, the arbitrator issued an interim phase one ruling finding (1) that Vertiv was in violation of California contractor license regulations and was barred from recovery of approximately $9.0 for work performed and equipment delivered in connection with the project, as well as requiring disgorgement plus interest of $10.0, (2) SVO was not in violation of California’s contractor license regulations, and (3) Vertiv and SVO agreed to a traditional baseball arbitration provision under the terms and conditions for the project, wherein each party is required to submit a proposed final award to the arbitrator for consideration, and the arbitrator is required to select one of the proposed awards submitted by the parties as the final award in the arbitration and is prohibited from issuing an alternative award. On December 31, 2021, the parties entered into a settlement agreement on ordinary and customary terms, settling all of the disputes between them. As of December 31, 2022 the settlement was recorded in “Accrued expenses and other liabilities” on the Consolidated Balance Sheet. The settlement was paid in the third quarter of 2023.
On May 3, 2022, a putative securities class action, In re Vertiv Holdings Co Securities Litigation, 22-cv-3572, was filed against Vertiv, certain of the Company’s officers and directors, and other defendants in the Southern District of New York. Plaintiffs filed an amended complaint on September 16, 2022. The amended complaint alleges that certain of the Company’s public statements were materially false and/or misleading with respect to inflationary and supply chain pressures and pricing issues, and asserts claims under Sections 10(b) and 20(a) of the Securities Exchange Act of 1934, as amended, and Sections 11, 12(a)(2), and 15 of the Securities Act of 1933, as amended. These claims are asserted on behalf of a putative class of all persons and entities that (i) purchased Vertiv securities between February 24, 2021 and February 22, 2022; and/or (ii) purchased Vertiv securities in or traceable to the November 4, 2021 secondary public offering by a selling stockholder pursuant to a resale registration statement. On January 31, 2024, the Court issued an order dismissing the claims under Sections 11, 12(a)(2), and 15 of the Securities Act. The motion to dismiss the claims under Sections 10(b) and 20(a) of the Exchange Act remains pending.
On June 9, 2023, two Vertiv shareholders, Matthew Sullivan and Jose Karlo Ocampo Avenido, brought a derivative lawsuit, Sullivan v. Johnson, et al., C.A. No. 2023-0608, against Vertiv (as nominal defendant only) and certain of the Company’s directors and officers in Delaware Court of Chancery for breach of fiduciary duty. The complaint alleges that certain of the named directors and officers caused the Company to issue materially false and/or misleading public statements with respect to inflationary and supply chain pressures and pricing issues, and that the Company suffered damages as a result. This action has been stayed since August 10, 2023, pending the securities class action.
We believe we have meritorious defenses against the allegations made in the aforementioned lawsuits, which are at the preliminary stages. However, we are unable at this time to predict the outcome of these matters or the amount of any cost associated with their resolution.
In November 2023, following the filing of the actions described above, the Company received a subpoena from the U.S. Securities and Exchange Commission (the “SEC”) and a parallel request for documents from the U.S. Attorney’s Office for the Southern District of New York, which relate to the allegations made in the class action complaint and derivative action. The Company is actively responding to these matters.
In January 2024, the Mexican tax administration service, the Servicio de Administracion Tributaria (the "SAT"), initiated a process to suspend the importer registration of one of the Company's wholly owned Mexico subsidiaries, Tecnología del Pacífico S.A. de C.V. (“TDP”), in connection with a contested customs tax audit for the period April 2016 to February 2018. SAT claimed its basis for the suspension was a failure by TDP to provide sufficient evidence of the export of goods temporarily imported at required levels under Mexico's Manufacturing, Maquila and Export Services Industries Program ("IMMEX Program"). The Company and TDP has disputed SAT’s position throughout the customs tax audit, through the filing of various petitions and appeals with appropriate documentation evidencing the complete and timely export of the goods temporarily imported during the audit period. TDP has accepted a proposal from SAT to close the audit by making payments and fees totaling approximately $10.1 which has been recorded in “Accrued expenses and other liabilities” on the Consolidated Balance Sheets as of December 31, 2023. The Company intends to seek reimbursement of this amount as an undue payment in the near future from SAT, for which the outcome is currently unknown and no receivable has been established. Furthermore, the Company remains subject to other customs tax audits concerning other facilities located within Mexico. While we cannot predict with certainty the outcome of other assessments, based on currently known information, we believe a risk of loss, if any, is not currently estimable. Accordingly, no further reserve for loss contingency has been recorded in the Company's financial statements as of December 31, 2023 related to these other matters. In February of 2024 $5.2 was paid to SAT in connection with the accepted proposal.
We are unable at this time to predict the outcome of these matters, including whether any proceedings may be instituted in connection with the government inquiries, or the amount of any cost associated with their resolution.
As of December 31, 2023, other than as described above, there were no known contingent liabilities (including guarantees, taxes and other claims) that management believes were or will be material in relation to the Company’s Consolidated Financial Statements, nor were there any material commitments outside the normal course of business.