Item 3. Legal Proceedings

4K characters. Original on sec.gov · Markdown

Item 3. Legal Proceedings

Environmental

Certain reportable legal proceedings involving governmental authorities under federal, state, and local laws regulating the discharge of materials into the environment are described below. While it is not possible for us to predict the final outcome of the proceedings which are still pending, we do not anticipate a material effect on our consolidated financial position if we receive an unfavorable outcome in any one or more of such proceedings.

On June 13, 2013, an explosion and fire occurred at our formerly owned Geismar olefins plant and rendered the facility temporarily inoperable (Geismar Incident). On October 21, 2013, the EPA, Region 6, issued an Inspection Report pursuant to the Clean Air Act’s Risk Management Program following its inspection of the facility on June 24 through June 28, 2013. The report notes the EPA’s preliminary determinations about the facility’s documentation regarding process safety, process hazard analysis, as well as operating procedures, employee training, and other matters. On June 16, 2014, we received a request for information related to the Geismar Incident from the EPA under Section 114 of the Clean Air Act to which we responded on August 13, 2014. We have worked with the agency to resolve these matters and in the second half of 2019, entered into a Stipulation of Settlement, which includes a penalty of $750,000 that will be due within thirty days of the Court’s entry of the settlement. The Court set a fairness hearing on the settlement for December 11, 2019. Prior to the scheduled hearing, the Court continued the hearing without setting a new date.

On May 5, 2017, we entered into a Consent Order with the Georgia Department of Natural Resources, Environmental Protection Division (GADNR) pertaining to alleged violations of the Georgia Water Quality Control Act and associated rules arising from a permit issued by GADNR for construction of Transco’s Dalton expansion project. Pursuant to the Consent Order, we paid a fine of $168,750 and agreed to a Corrective Action Plan.

On January 19, 2016, we received a Notice of Noncompliance with certain Leak Detection and Repair (LDAR) regulations under the Clean Air Act at our Moundsville Fractionator Facility from the EPA, Region 3. Subsequently, the EPA alleged similar violations of certain LDAR regulations at our Oak Grove Gas Plant. On March 19, 2018, we received a Notice of Violation of certain LDAR regulations at our former Ignacio Gas Plant from the EPA, Region 8, following an on-site inspection of the facility. On March 20, 2018, we also received a Notice of Violation of certain LDAR regulations at our Parachute Creek Gas Plant from the EPA, Region 8. All Notices were subsequently referred to a common attorney at the Department of Justice (DOJ). We are exploring global resolution of the claims at these facilities, as well as alleged violations at certain other facilities, with the DOJ. Global resolution would include both

payment of a civil penalty and an injunctive relief component. We continue to work with the DOJ and the other agencies to resolve these claims, whether individually or globally, and negotiations are ongoing.

Other environmental matters called for by this Item are described under the caption “Environmental Matters” in Note 19 – Contingent Liabilities and Commitments of Notes to Consolidated Financial Statements included under Part II, Item 8 Financial Statements of this report, which information is incorporated by reference into this Item.

Other litigation

The additional information called for by this Item is provided in Note 19 – Contingent Liabilities and Commitments of Notes to Consolidated Financial Statements included under Part II, Item 8 Financial Statements of this report, which information is incorporated by reference into this Item.

Previous: Item 2. Properties · Next: Item 4. Mine Safety Disclosures