Item 2. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

The 28 tables in Item 2. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS as one CSV, figures in aligned columns. For subscribers: paste your API key. One API call. Plans from $19 a month, see pricing.

The following discussion and analysis by management focuses on those factors that had a material effect on Xcel Energy’s financial condition, results of operations and cash flows during the periods presented or are expected to have a material impact in the future. It should be read in conjunction with the accompanying unaudited consolidated financial statements and the related notes to consolidated financial statements. Due to the seasonality of Xcel Energy’s operating results, quarterly financial results are not an appropriate base from which to project annual results.

The demand for electric power and natural gas is affected by seasonal differences in the weather. In general, peak sales of electricity occur in the summer months, and peak sales of natural gas occur in the winter months. As a result, the overall operating results may fluctuate substantially on a seasonal basis. Additionally, Xcel Energy’s operations have historically generated less revenues and income when weather conditions are milder in the winter and cooler in the summer.

Non-GAAP Financial Measures

The following discussion includes financial information prepared in accordance with GAAP, as well as certain non-GAAP financial measures such as ongoing earnings and ongoing diluted EPS. Generally, a non-GAAP financial measure is a measure of a company’s financial performance, financial position or cash flows that adjusts measures calculated and presented in accordance with GAAP. Xcel Energy’s management uses non-GAAP measures for financial planning and analysis, for reporting of results to the Board of Directors, in determining performance-based compensation, and communicating its earnings outlook to analysts and investors. Non-GAAP financial measures are intended to supplement investors’ understanding of our performance and should not be considered alternatives for financial measures presented in accordance with GAAP. These measures are discussed in more detail below and may not be comparable to other companies’ similarly titled non-GAAP financial measures.

Earnings Adjusted for Certain Items (Ongoing Earnings and Ongoing Diluted EPS)

GAAP diluted EPS reflects the potential dilution that could occur if securities or other agreements to issue common stock (i.e., common stock equivalents) were settled. The weighted average number of potentially dilutive shares outstanding used to calculate Xcel Energy Inc.’s diluted EPS is calculated using the treasury stock method.

Ongoing earnings reflect adjustments to GAAP earnings (net income) for certain items. Ongoing diluted EPS for Xcel Energy is calculated by dividing net income or loss, adjusted for certain items, by the weighted average fully diluted Xcel Energy Inc. common shares outstanding for the period. Ongoing diluted EPS for each subsidiary is calculated by dividing the net income or loss for such subsidiary, adjusted for certain items, by the weighted average fully diluted Xcel Energy Inc. common shares outstanding for the period.

We use these non-GAAP financial measures to evaluate and provide details of Xcel Energy’s core earnings and underlying performance. We believe these measurements are useful to investors to evaluate the actual and projected financial performance and contribution of our subsidiaries. For the three and six months ended June 30, 2022 and 2021, there were no such adjustments to GAAP earnings and therefore GAAP earnings equal ongoing earnings for these periods.

Results of Operations

The only common equity securities that are publicly traded are common shares of Xcel Energy Inc. Diluted earnings and EPS of each subsidiary discussed below do not represent a direct legal interest in the assets and liabilities allocated to such subsidiary but rather represent a direct interest in our assets and liabilities as a whole.

Summarized diluted EPS for Xcel Energy:

Three Months Ended June 30Six Months Ended June 30
Diluted Earnings (Loss) Per Share2022202120222021
PSCo$0.24$0.25$0.56$0.56
NSP-Minnesota0.220.210.450.45
SPS0.170.130.270.23
NSP-Wisconsin0.030.030.110.09
Earnings from equity method investments — WYCO0.010.010.020.02
Regulated utility (a)0.670.621.411.35
Xcel Energy Inc. and Other(0.07)(0.04)(0.11)(0.10)
Total (a)$0.60$0.58$1.30$1.25

(a) Amounts may not add due to rounding.

Summary of Earnings

Xcel Energy — Xcel Energy’s GAAP second quarter diluted earnings were $0.60 per share in 2022 compared with $0.58 per share in 2021. The increase was driven by regulatory recovery of capital investment, partially offset by higher depreciation, interest expense and O&M expenses. Costs for natural gas sold and transported significantly increased in 2022 primarily due to market price fluctuations. However, fluctuations in electric and natural gas revenues associated with changes in fuel and purchased power and/or natural gas sold and transported generally do not significantly impact earnings (changes in costs are offset by the related variation in revenues).

PSCo — Earnings decreased $0.01 per share for the second quarter of 2022 and were flat year-to-date. Year-to-date earnings reflect a Winter Storm Uri cost disallowance (see Other section) and unrecovered incremental purchased power costs due to the Comanche Unit 3 outage (see Other section).

NSP-Minnesota — Earnings increased $0.01 per share for the second quarter of 2022 and were flat year-to-date, as regulatory recovery of capital investment was offset by increased depreciation and interest expense.

SPS — Earnings increased $0.04 per share for the second quarter of 2022 and year-to-date, primarily due to regulatory outcomes, strong sales growth and favorable weather.

NSP-Wisconsin — Earnings were flat for the second quarter of 2022 and increased $0.02 per share year-to-date. The year-to-date increase reflects the impact of regulatory rate outcomes, sales growth and favorable weather, partially offset by higher depreciation and O&M expenses.

Xcel Energy Inc. and Other — Primarily includes financing costs at the holding company and earnings from Energy Impact Partners funds equity method investments.

Table of Contents

Changes in GAAP and Ongoing Diluted EPS

Components significantly contributing to changes in 2022 EPS compared to 2021:

Diluted Earnings (Loss) Per ShareThree Months Ended June 30Six Months Ended June 30
GAAP and ongoing diluted EPS — 2021$0.58$1.25
Components of change - 2022 vs. 2021
Higher electric revenues, net of electric fuel and purchased power0.260.34
Lower effective tax rate (ETR) (a)0.060.10
(Lower) higher natural gas revenues, net of cost of natural gas sold and transported(0.01)0.04
Higher depreciation and amortization(0.15)(0.21)
Higher interest charges(0.05)(0.06)
Higher taxes (other than income taxes)(0.03)(0.04)
Higher O&M expenses(0.02)(0.04)
Lower other (expense) income(0.01)(0.02)
Other, net(0.03)(0.06)
GAAP and ongoing diluted EPS — 2022$0.60$1.30

(a)Includes PTCs and plant regulatory amounts, which are primarily offset as a reduction to electric revenues.

Statement of Income Analysis

The following summarizes the items that affected the individual revenue and expense items reported in the consolidated statements of income.

Estimated Impact of Temperature Changes on Regulated Earnings —Unusually hot summers or cold winters increase electric and natural gas sales, while mild weather reduces electric and natural gas sales. The estimated impact of weather on earnings is based on the number of customers, temperature variances, the amount of natural gas or electricity historically used per degree of temperature and excludes any incremental related operating expenses that could result due to storm activity or vegetation management requirements. As a result, weather deviations from normal levels can affect Xcel Energy’s financial performance. However, decoupling mechanisms in Colorado and proposed sales true-up mechanisms in Minnesota predominately mitigate the positive and adverse impacts of weather for the electric utility.

Degree-day or THI data is used to estimate amounts of energy required to maintain comfortable indoor temperature levels based on each day’s average temperature and humidity. HDD is the measure of the variation in the weather based on the extent to which the average daily temperature falls below 65° Fahrenheit. CDD is the measure of the variation in the weather based on the extent to which the average daily temperature rises above 65° Fahrenheit.

Each degree of temperature above 65° Fahrenheit is counted as one CDD, and each degree of temperature below 65° Fahrenheit is counted as one HDD. In Xcel Energy’s more humid service territories, a THI is used in place of CDD, which adds a humidity factor to CDD. HDD, CDD and THI are most likely to impact the usage of Xcel Energy’s residential and commercial customers. Industrial customers are less sensitive to weather. Typically, sales are not impacted in the first or fourth quarter due to THI or CDD.

Normal weather conditions are defined as either the 10, 20 or 30 year average of actual historical weather conditions. The historical period of time used in the calculation of normal weather differs by jurisdiction, based on regulatory practice. To calculate the impact of weather on demand, a demand factor is applied to the weather impact on sales. Extreme weather variations, windchill and cloud cover may not be reflected in weather-normalized estimates.

Percentage increase (decrease) in normal and actual HDD, CDD and THI:

Three Months Ended June 30Six Months Ended June 30
2022 vs. Normal2021 vs. Normal2022 vs. 20212022 vs. Normal2021 vs. Normal2022 vs. 2021
HDD6.3%1.7%3.2%9.1%1.4%7.1%
CDD29.73.531.728.93.031.0
THI21.388.9(33.1)21.088.4(33.0)

Weather — Estimated impact of temperature variations on EPS compared with normal weather conditions:

Three Months Ended June 30Six Months Ended June 30
2022 vs. Normal2021 vs. Normal2022 vs. 20212022 vs. Normal2021 vs. Normal2022 vs. 2021
Retail electric$0.028$0.056$(0.028)$0.049$0.055$(0.006)
Decoupling and sales true-up(0.013)(0.044)0.031(0.023)(0.041)0.018
Electric total$0.015$0.012$0.003$0.026$0.014$0.012
Firm natural gas0.0030.0020.0010.0190.0050.014
Total$0.018$0.014$0.004$0.045$0.019$0.026

Sales — Sales growth (decline) for actual and weather-normalized sales in 2022 compared to 2021:

Three Months Ended June 30
PSCoNSP-MinnesotaSPSNSP-WisconsinXcel Energy
Actual
Electric residential(6.3)%(5.9)%6.5%(3.0)%(4.2)%
Electric C&I(1.1)0.611.72.53.2
Total retail electric sales(2.8)(1.4)10.80.91.2
Firm natural gas sales(9.6)27.3N/A22.52.2
Three Months Ended June 30
PSCoNSP-MinnesotaSPSNSP-WisconsinXcel Energy
Weather-Normalized
Electric residential(5.0)%0.9%(1.6)%1.3%(1.7)%
Electric C&I(0.6)2.410.83.73.9
Total retail electric sales(2.1)2.08.63.02.3
Firm natural gas sales(6.0)12.7N/A11.40.2
Six Months Ended June 30
PSCoNSP-MinnesotaSPSNSP-WisconsinXcel Energy
Actual
Electric residential(3.7)%(0.6)%3.2%2.0%(1.0)%
Electric C&I0.83.511.03.64.7
Total retail electric sales(0.8)2.29.43.13.0
Firm natural gas sales(3.6)22.1N/A22.25.6

Table of Contents

Six Months Ended June 30
PSCoNSP-MinnesotaSPSNSP-WisconsinXcel Energy
Weather-Normalized
Electric residential(3.2)%0.7%(0.8)%1.0%(1.0)%
Electric C&I1.04.110.43.94.8
Total retail electric sales(0.4)3.08.23.03.1
Firm natural gas sales(2.5)6.9N/A8.31.2

Weather-normalized electric sales growth (decline) — year-to-date

  • PSCo — Residential sales declined due to decreased use per customer, partially offset by a 1.1% increase in customers. The growth in C&I sales was due to a 1.1% increase in customers, primarily in the professional services and retail sectors.

  • NSP-Minnesota — Residential sales growth reflects a 1.2% increase in customers, partially offset by decreased use per customer. The growth in C&I sales was primarily due to higher use per customer, particularly in the manufacturing, real estate and leasing, and food service sectors.

  • SPS — Residential sales declined due to a lower use per customer, partially offset by a 1.0% increase in customers. C&I sales increased due to higher use per customer, primarily driven by the energy sector.

  • NSP-Wisconsin — Residential sales growth was driven by a 0.7% increase in customers. C&I sales growth was primarily due to higher use per customer, primarily from increases in the manufacturing and transportation sectors.

Weather-normalized natural gas sales growth (decline) — year-to-date

  • Natural gas sales reflect a higher customer use, primarily in NSP-Minnesota and NSP-Wisconsin, as well as a 1.2% increase in residential customers and a 0.5% increase in C&I customers.

Electric Margin

Electric margin is presented as electric revenues less electric fuel and purchased power expenses. Expenses incurred for electric fuel and purchased power are generally recovered through various regulatory recovery mechanisms. As a result, changes in these expenses are generally offset in operating revenues.

Electric revenues and fuel and purchased power expenses are impacted by fluctuations in the price of natural gas, coal and uranium. However, these price fluctuations generally have minimal earnings impact due to fuel recovery mechanisms that recover fuel expenses. In addition, electric customers receive a credit for PTCs generated, which reduce electric revenue and income taxes.

Electric revenues, fuel and purchased power and margin and explanation of the changes are listed as follows:

Three Months Ended June 30Six Months Ended June 30
(Millions of Dollars)2022202120222021
Electric revenues$2,923$2,597$5,556$5,467
Electric fuel and purchased power(1,181)(1,047)(2,275)(2,433)
Electric margin$1,742$1,550$3,281$3,034
(Millions of Dollars)Three Months Ended June 30, 2022 vs. 2021Six Months Ended June 30, 2022 vs. 2021
Regulatory rate outcomes (Minnesota, Colorado, Texas, New Mexico and Wisconsin)$124$187
Revenue recognition for the Texas rate case surcharge (a)8585
Sales and demand (b)3860
Non-fuel riders741
Conservation and demand side management (offset in expense)922
Estimated impact of weather (net of decoupling/sales true-up)29
PTCs flowed back to customers (offset by lower ETR)(50)(103)
Proprietary commodity trading, net of sharing (c)(8)(33)
Comanche Unit 3 outage unrecovered purchased power cost (d)(8)(18)
Other (net)(7)(3)
Total increase$192$247

(a)Recognition of revenue from the Texas rate case outcome is largely offset by recognition of previously deferred costs, see Public Utility Regulation for additional information.

(b)Sales excludes weather impact, net of decoupling in Colorado and proposed sales true-up mechanism in Minnesota.

(c)Includes $27 million of net gains recognized in the first quarter of 2021, driven by market changes associated with Winter Storm Uri.

(d)See Other section for more information.

Natural Gas Margin

Natural gas margin is presented as natural gas revenues less the cost of natural gas sold and transported. Expenses incurred for the cost of natural gas sold are generally recovered through various regulatory recovery mechanisms. As a result, changes in these expenses are generally offset in operating revenues.

Natural gas revenues, cost of natural gas sold and transported and margin and explanation of the changes are listed as follows:

Three Months Ended June 30Six Months Ended June 30
(Millions of Dollars)2022202120222021
Natural gas revenues$476$449$1,566$1,096
Cost of natural gas sold and transported(251)(218)(961)(517)
Natural gas margin$225$231$605$579
(Millions of Dollars)Three Months Ended June 30, 2022 vs. 2021Six Months Ended June 30, 2022 vs. 2021
Regulatory rate outcomes (Minnesota, Wisconsin, North Dakota, Colorado)$(3)$14
Estimated impact of weather111
Other (net)(4)1
Total (decrease) increase$(6)$26

Table of Contents

Non-Fuel Operating Expenses and Other Items

O&M Expenses — O&M expenses increased $14 million for the second quarter and $32 million year-to-date. O&M costs increased due to recognition of previously deferred amounts related to the Texas Electric Rate Case, additional investments in technology and customer programs and higher costs for storms and vegetation management. These increases were partially offset by a reduction in employee benefit costs and timing of certain power plant overhaul costs.

Depreciation and Amortization — Depreciation and amortization increased $110 million for the second quarter and $151 million year-to-date. The increase was primarily driven by several wind farms going into service, normal system expansion and recognition of previously deferred costs related to the Texas Electric Rate Case.

Other (Expense) Income — Other (expense) income decreased $9 million for the second quarter and $13 million year-to-date, largely related to rabbi trust performance, which is primarily offset in O&M expenses (employee benefit costs).

Interest Charges — Interest charges increased $35 million for the second quarter and $44 million year-to-date, largely due to increased long-term debt levels to fund capital investments and deferred balances related to Winter Storm Uri.

Income Taxes — Income tax benefit increased $36 million for the second quarter and $64 million year-to-date, primarily driven by an increase in wind PTCs due to greater production at existing wind farms and several new wind farms going into service. Wind PTCs are credited to customers (recorded as a reduction to revenue) and do not have a material impact on net income.

In April 2022, the Internal Revenue Service published inflation factors used to determine the PTC rate. As a result, the 2022 PTC rate on the sale of electricity produced from wind is 2.6 cents per kilowatt hour, compared to 2.5 cents for 2021.

Public Utility Regulation and Other

The FERC and various state and local regulatory commissions regulate Xcel Energy Inc.’s utility subsidiaries and West Gas Interstate. Xcel Energy is subject to rate regulation by state utility regulatory agencies, which have jurisdiction with respect to the rates of electric and natural gas distribution companies in Minnesota, North Dakota, South Dakota, Wisconsin, Michigan, Colorado, New Mexico and Texas.

Rates are designed to recover plant investment, operating costs and an allowed return on investment. Our utility subsidiaries request changes in utility rates through commission filings. Changes in operating costs can affect Xcel Energy’s financial results, depending on the timing of rate cases and implementation of final rates. Other factors affecting rate filings are new investments, sales, conservation and demand side management efforts, and the cost of capital.

In addition, the regulatory commissions authorize the ROE, capital structure and depreciation rates in rate proceedings. Decisions by these regulators can significantly impact Xcel Energy’s results of operations.

Except to the extent noted below, the circumstances set forth in Public Utility Regulation included in Item 7 of Xcel Energy’s Annual Report on Form 10-K for the year ended Dec. 31, 2021 appropriately represent, in all material respects, the current status of public utility regulation and are incorporated herein by reference.

NSP-Minnesota

Pending and Recently Concluded Regulatory Proceedings

2022 Minnesota Electric Rate Case — In October 2021, NSP-Minnesota filed a three-year electric rate case with the MPUC. The rate case is based on a requested ROE of 10.2%, a 52.50% equity ratio and forward test years.

The request is detailed as follows:

(Amounts in Millions, Except Percentages)202220232024Total
Rate request$396$150$131$677
Increase percentage12.2%4.8%4.2%21.2%
Rate base$10,931$11,446$11,918N/A

In December 2021, the MPUC approved interim rates, subject to refund, of $247 million, effective Jan. 1, 2022. A current liability that represents NSP-Minnesota’s best estimate of a refund obligation associated with interim rates was recorded as of June 30, 2022.

Next steps in the procedural schedule are expected to be as follows:

  • Intervenor testimony: Oct. 3, 2022.

  • Rebuttal testimony: Nov. 8, 2022.

  • Hearing: Dec. 13-16, 2022.

  • ALJ Report: March 31, 2023.

  • MPUC Order: June 30, 2023.

2022 Minnesota Natural Gas Rate Case — In November 2021, NSP-Minnesota filed a request with the MPUC for an annual natural gas rate increase of $36 million, or 6.6%. The filing is based on a 2022 forecast test year and includes a requested ROE of 10.5%, an equity ratio of 52.5% and a rate base of $934 million.

In December 2021, the MPUC approved interim rates of $25 million, subject to refund, effective Jan. 1, 2022.

Next steps in the procedural schedule are expected to be as follows:

  • Intervenor testimony: Aug. 30, 2022.

  • Rebuttal testimony: Oct. 4, 2022.

  • Hearing: Nov. 1-4, 2022.

  • ALJ Report: Feb. 6, 2023.

  • MPUC Order: April 26, 2023.

2021 North Dakota Natural Gas Rate Case — In September 2021, NSP-Minnesota filed a request with the NDPSC for a natural gas rate increase of $7 million, or 10.5%. The filing is based on a requested ROE of 10.5%, an equity ratio of 52.54%, a 2022 forecast test year and a rate base of $124 million. Interim rates of $7 million, subject to refund, were implemented on Nov. 1, 2021.

In May 2022, NSP-Minnesota and NDPSC Staff reached a natural gas settlement, which reflects a rate increase of $5 million, based on a 9.8% ROE and 52.54% equity ratio. A NDPSC decision is expected in the third quarter of 2022.

2022 South Dakota Electric Rate Case — On June 30, 2022, NSP-Minnesota filed a South Dakota electric rate case (first since 2014) seeking a revenue increase of approximately $44 million. The filing is based on a 2021 historic test year adjusted for certain known and measurable changes for 2022 and 2023, a requested ROE of 10.75%, rate base of approximately $947 million and an equity ratio of 53%. Final rates are expected to be effective in the first quarter of 2023.

Table of Contents

Wind Repowering — In January 2021, the MPUC approved NSP-Minnesota’s request for the repowering of 651 MW of owned wind projects. Two of the four repowering projects, where construction has not yet begun (in-service dates in 2025), now expect costs in excess of the original approval. Evaluation of options to mitigate the impact of these cost increases is on-going. An update to the MPUC is expected in the third or fourth quarter 2022.

Sherco Solar Proposal — In April 2021, NSP-Minnesota proposed to add 460 MW of solar facilities at the Sherco site with an initial estimated investment of approximately $575 million. NSP-Minnesota requested a delay in the procedural schedule due to recent solar supply chain disruptions and potential impact on pricing. An updated request was filed with the MPUC in July 2022 and a decision is now anticipated in the fourth quarter of 2022 or the first quarter of 2023. The proposed facilities are still expected to be in-service by the end of 2025.

Wind PPA Buyout — In July 2022, NSP-Minnesota requested approval from the MPUC for updated agreements with ALLETE Clean Energy to purchase the repowered 100 MW Northern Wind Facility and 22 MW Rock Aetna Facility. The MPUC previously approved NSP-Minnesota’s acquisition of the projects, but the agreements required further approval due to updated terms of the acquisition, including an increase in the purchase price. The price increase is offset by higher expected PTC benefits, resulting in minimal change to the net cost to customers.

2022 RES Electric Rider — In November 2021, NSP-Minnesota filed the RES Rider. The requested amount of $264 million includes a true-up (2020 and 2021 riders) of $154 million and the 2022 requested amount of $110 million. A MPUC decision is pending.

2022 GUIC Natural Gas Rider — In October 2021, NSP-Minnesota filed the GUIC Rider for an amount of $27 million. A MPUC decision is pending.

2021 GUIC Natural Gas Rider — In October 2020, NSP-Minnesota filed the GUIC Rider for an amount of $27 million. A MPUC decision is pending.

2022 TCR Electric Rider — In November 2021, NSP-Minnesota filed the TCR Rider for an amount of $105 million. A MPUC decision is pending.

Nuclear Power Operations

NSP-Minnesota owns two nuclear generating plants: the Monticello plant and the Prairie Island plant. See Note 12 to the consolidated financial statements of Xcel Energy’s Annual Report on Form 10-K for the year ended Dec. 31, 2021 for further information. The circumstances set forth in Nuclear Power Operations included in Item 7 of Xcel Energy’s Annual Report on Form 10-K for the year ended Dec. 31, 2021, appropriately represent, in all material respects, the current status of nuclear power operations, and are incorporated by reference.

NSP-Wisconsin

Pending and Recently Concluded Regulatory Proceedings

Michigan Natural Gas Rate Case —In July 2022, NSP-Wisconsin filed an application with the Public Service Commission of Michigan seeking a revenue increase in base natural gas rates of $1 million for the period of 2023-2025.

PSCo

Pending and Recently Concluded Regulatory Proceedings

Colorado Natural Gas Rate Case — In January 2022, PSCo filed a request with the CPUC seeking a net increase to retail natural gas rates of $107 million. The total change to base rates is $215 million, which reflects the transfer of $108 million previously recovered from customers through the PSIA rider. The request is based on a 10.25% ROE, an equity ratio of 55.66% and a 2022 current test year with a projected rate base of $3.6 billion. PSCo has requested a proposed effective date of Nov. 1, 2022.

Additionally, PSCo’s request includes step revenue increases of $40 million (effective Nov. 1, 2023) and $41 million (effective Nov. 1, 2024) related to continued capital investment.

On June 15, 2022, eight parties filed testimony, with the CPUC Staff and the UCA filing comprehensive testimony. The Staff and UCA both recommended a historic test year with average rate base and no step increases for 2023 and 2024.

Proposed modifications to PSCo's request:

2022 Rate Request (Millions of Dollars)StaffUCA
Filed base revenue request$215$215
Less: previously authorized costs (existing riders)108108
Filed net increase to revenue107107
Recommended adjustments:
Test year adjustments(33)(41)
ROE(42)(42)
Weather normalization adjustment—(7)
Depreciation expense change14—
Other, net(15)(5)
Total recommended adjustments(76)(95)
Total proposed revenue change$31$12

Positions on PSCo's filed gas rate request:

Recommended PositionStaffUCA
ROE9.00%9.00%
Equity55.00%51.50%
Test yearHistoricHistoric

In July 2022, PSCo filed rebuttal testimony and updated its revenue request from $215 million to $202 million.

Next steps in the procedural schedule are expected to be as follows:

  • Settlement deadline: Aug. 3, 2022.

  • Evidentiary hearings: Aug. 17-23, 2022.

  • Statement of position: Sept. 21, 2022.

Colorado Electric Rate Request — In July 2021, PSCo filed a request with the CPUC. In March 2022, the CPUC approved an unopposed settlement that included a net electric rate increase of $177 million, a ROE of 9.3% and an equity ratio of 55.69%. Rates became effective April 1, 2022.

Table of Contents

Colorado Power Pathway Settlement — In June 2022, the CPUC issued a final written order issuing the CPCN for the Pathway Project. Key decisions include:

  • The CPUC approved PSCo’s cost estimate of $1.7 billion and recovery through the transmission rider.

  • The CPUC modified the PIMs proposed in the settlement agreement, which focused on cost controls, to add a separate mechanism to further incentivize timely delivery of the Pathway Project segments. The CPUC also increased the magnitude of the PIMs.

  • The CPUC granted conditional approval for the 345 kilovolt May Valley-Longhorn line extension, pending the level of renewables being added in that region through PSCo’s resource plan. The initial cost estimate for the extension is approximately $250 million.

In July 2022, the CPUC modified the PIMs related to cost controls and project timing.

Colorado Resource Plan Settlement — In June 2022, the CPUC verbally approved a revised settlement, which will result in the further acceleration of the retirement of the Comanche Unit 3 coal plant, an expected carbon reduction of at least 85% and an 80% renewable mix by 2030. The CPUC deferred a decision on the method of cost recovery for the retiring coal units to a separate docket, which will consider accelerated depreciation, creation of regulatory assets and securitization. PSCo expects to file a recovery method docket in the fall.

Key settlement terms include:

  • Early retirement of Hayden: Unit 2 in 2027 (was 2036); and Unit 1 in 2028 (was 2030).

  • Conversion of the Pawnee coal plant to natural gas by no later than Jan. 1, 2026.

  • Early retirement of Comanche Unit 3 by Jan. 1, 2031 (was 2070) with reduced operations beginning in 2025.

  • Addition of ~2,400 MW of wind.

  • Addition of ~1,600 MW of universal-scale solar.

  • Addition of 400 MW of storage.

  • Addition of 1,300 MW of flexible, dispatchable generation.

  • Addition of ~1,200 MW of distributed solar resources through our renewable energy programs.

Colorado Partial Settlement — In October 2021, PSCo filed a comprehensive settlement with the CPUC Staff and the Colorado Energy Office, which proposed to address four outstanding regulatory items, including recovery of fuel costs related to Winter Storm Uri, disputed revenue associated with the 2020 electric decoupling pilot program year, replacement power costs associated with an extended outage at Comanche Unit 3 during 2020 and deferred customer bad debt balances associated with COVID-19. In July 2022, the CPUC approved the settlement, with an $8 million disallowance relating to the Winter Storm Uri fuel costs.

Key settlement terms include:

  • PSCo will recover Winter Storm Uri deferred net natural gas, fuel and purchased energy costs (prior to the $8 million disallowance) of $263 million (electric utility) and $287 million (natural gas utility) over a 24-month and 30-month period, respectively, with no carrying charges through a rider mechanism.

  • PSCo will refund electric customers $41 million (previously deferred) related to the 2020 electric decoupling pilot program.

  • PSCo agreed to forego recovery of $14 million for replacement power costs due to an extended outage at Comanche Unit 3 during 2020 (approved by the CPUC in February 2022 as part of the 2020 retail electric commodity adjustment settlement agreement).

  • PSCo also agreed to not seek recovery of COVID-19 related bad debt expense, previously deferred as a regulatory asset, and recorded an additional $11 million of incremental bad debt expense for the period ended Dec. 31, 2021.

Decoupling Filing — PSCo has a decoupling program, effective April 1, 2020 through Dec. 31, 2023. The program applies to Residential and metered small C&I customers who do not pay a demand charge. The program includes a refund and surcharge cap not to exceed 3% of forecasted base rate revenue for a specified period.

In October 2021, a settlement was reached on Winter Storm Uri costs and also addressed certain components of decoupling. See Colorado Partial Settlement disclosure above.

As of June 30, 2022, PSCo has recognized a refund for Residential customers and a surcharge for small C&I customers based on 2020, 2021 and the first and second quarters of 2022 results.

In April 2022, PSCo made its annual filing. In May 2022 the UCA filed a protest raising issues relating to the Winter Storm Uri settlement and the soft cap components of the decoupling program. On May 25, 2022 the CPUC found merit in UCA’s protest, suspended PSCo’s advice letter and referred the matter to the ALJ.

2019 Electric Rate Case Appeal — In August 2020, PSCo filed an appeal with the Denver District Court seeking a review of CPUC decisions on gains and losses on sales of assets and other items. In January 2022, the court issued its decision that the CPUC’s approach to gains and losses on certain sales of assets was legally erroneous and confiscatory to PSCo and set aside and remanded the issue for further consideration. The CPUC is expected to deliberate in the third quarter of 2022.

GCA NOPR — In June 2021, the CPUC issued a NOPR addressing the recovery of costs through the GCA. The CPUC has reopened the GCA NOPR matter and proposed a 2 step process aimed at 1) considering near term process changes to the GCA used by various utilities and 2) a longer term process to evaluate potential performance incentive GCA structures to be filed by Nov. 1, 2022. In step 1, consensus proposed rule amendments to update the process and filing requirements for GCA and related filings have been submitted to the CPUC for consideration.

Natural Gas Planning NOPR — In October 2021, the CPUC issued a NOPR to implement recent state legislation requiring natural gas utilities to develop clean heat plans as a means to meet state greenhouse gas emission reduction targets, as well as updated demand-side management criteria. Additionally, the proposed rules included new comprehensive natural gas infrastructure planning requirements and related CPCN application procedures, changes in natural gas line extension policy, and details on emission accounting related to clean heat plans.

Table of Contents

SPS

Pending and Recently Concluded Regulatory Proceedings

2021 Texas Electric Rate Case — In 2021, SPS filed an electric rate case with the PUCT and its municipalities seeking an increase in base rates of approximately $140 million. In May 2022, the PUCT approved a settlement between SPS and intervening parties, which reflects the following terms:

  • Base rate increase of $89 million effective retroactively to March 15, 2021.

  • A 9.35% ROE and 7.01% weighted average cost of capital for AFUDC purposes only.

  • Depreciation lives for Tolk accelerated to 2034 and Harrington coal assets accelerated to 2024.

In July 2022, SPS filed to surcharge the final under-recovered amount, estimated to be approximately $85 million, substantially offset by the recognition of previously deferred costs. The impact of the retroactive amounts is as follows:

(Millions of Dollars)Six Months Ended June 30, 2022
Revenue surcharge accrual$85
Depreciation and amortization(43)
O&M expenses(16)
Interest expense(12)
Taxes other than income taxes(10)
Fuel and purchased power(2)

Other

Supply Chain

Xcel Energy’s ability to meet customer energy requirements, respond to storm-related disruptions and execute our capital expenditure program are dependent on maintaining an efficient supply chain. Manufacturing processes have experienced disruptions related to scarcity of certain raw materials and interruptions in production and shipping. These disruptions have been further exacerbated by inflationary pressures, labor shortages and the impact of international conflicts/issues. Xcel Energy continues to monitor the availability of materials and has sought to mitigate impacts by seeking alternative suppliers as necessary.

Advanced Metering Infrastructure Implementation

Supply chain issues associated with semi-conductors have delayed the availability of advanced metering infrastructure electric meters. Impacts are currently being evaluated and the 2022 and 2023 deployment schedule could be impacted.

Solar Resources

In April 2022, the U.S. Department of Commerce initiated an anti-circumvention investigation that would subject CSPV solar panels and cells imported from Malaysia, Vietnam, Thailand, and Cambodia with potential incremental tariffs ranging from 50% to 250%. These countries account for more than 80% of CSPV panel imports.

Uncertainty of the investigation and the adverse impact on potential tariffs has resulted in the cancellation or delay of certain domestic solar projects.

The impacts on Xcel Energy are as follows:

*•*NSP-Minnesota Sherco Solar Project — In April 2021, NSP-Minnesota proposed to add 460 MW of solar facilities at the Sherco site with an initial estimated investment of approximately $575 million. NSP-Minnesota requested a delay in the procedural schedule due to recent solar supply chain disruptions and potential impact on pricing. An updated request was filed with the MPUC in July 2022 and a decision is now anticipated in the fourth quarter of 2022 or the first quarter of 2023. The proposed facilities are still expected to be in-service by the end of 2025.

  • NSP-Wisconsin — In June 2021, the Public Service Commission of Wisconsin approved NSP-Wisconsin’s Western Mustang solar project, a 74 MW facility that would be built by a developer for approximately $100 million. The project was originally scheduled to go into service in 2022. As a result of the disruption of the solar supply chain, the developer has indicated difficulty delivering the project at the contract price and scheduled in-service date. Negotiations on a potential solution are on-going.

  • PSCo PPAs — PSCo has several solar PPAs expected to commence with solar generating assets scheduled to go into service in late 2022 and early 2023. Some developers have indicated difficulty delivering the projects at the contract price and at the scheduled in-service date. Negotiations on a potential solution are on-going. PSCo is developing contingency plans in the event that the solar generating assets are not completed in time to meet the capacity needs of the 2023 summer season.

Marshall Wildfire

In December 2021, a wildfire ignited in Boulder County, Colorado (the “Marshall Fire”), which burned over 6,000 acres and destroyed or damaged over 1,000 structures. Boulder County authorities are currently investigating the fire and have not yet determined a cause. There were no downed power lines in the ignition area, and nothing the Company has seen to this point indicates that our equipment or operations caused the fire.

In Colorado, the standard of review governing liability differs from the “inverse condemnation” or strict liability standard utilized in California. In Colorado, courts look to whether electric power companies have operated their system with a heightened duty of care consistent with the practical conduct of its business, and liability does not extend to occurrences that cannot be reasonably anticipated. In addition, PSCo has been operating under a commission approved wildfire mitigation plan and carries wildfire liability insurance.

In March 2022, a class action suit was filed in Boulder County pertaining to the Marshall Fire. In the remote event PSCo was found liable related to this litigation and were required to pay damages, such amounts could exceed our insurance coverage and have a material adverse effect on our financial condition, results of operations or cash flows. In June 2022, Plaintiffs served the class action lawsuit. In July 2022, PSCo filed a Motion to Dismiss.

Comanche Unit 3 Outage — In late January 2022, PSCo experienced an outage at the Comanche Unit 3 coal plant. The plant returned to service in June 2022. PSCo will not seek recovery of the approximately $18 million of incremental replacement power costs, subject to true-up, incurred during the outage.

Table of Contents

Colorado Ballot Initiative — In April 2022, a proposed ballot initiative was filed in the state of Colorado, which if approved, would require at least 5% of all gas and electric rates to be paid from profits as determined by the CPUC. At the end of April 2022, the initiative was approved by the Colorado Title Board for petition. If the petitioners receive 125,000 voter signatures by August 8, 2022, this initiative will be added to the ballot for the Colorado general election in November.

MISO Capacity Credits — The NSP System offered 1,500 MW of excess capacity into the MISO planning resource auction for June 2022 through May 2023. Due to a projected overall capacity shortfall in the MISO region, the 1,500 MWs offered cleared the auction at maximum pricing and is expected to generate revenues of approximately $89 million in 2022 and approximately $64 million in 2023. During the second quarter of 2022, the NSP System received approximately $13 million of capacity credits. These amounts will primarily be used to mitigate customer rate increases or returned through earnings sharing or other mechanisms.

Winter Storm Uri

In February 2021, the United States experienced Winter Storm Uri. Extreme cold temperatures impacted certain operational assets as well as the availability of renewable generation. The cold weather also affected the country’s supply and demand for natural gas. These factors contributed to extremely high market prices for natural gas and electricity. As a result of the extremely high market prices, Xcel Energy incurred net natural gas, fuel and purchased energy costs of approximately $1 billion (largely deferred as regulatory assets).

Regulatory Overview — Xcel Energy has natural gas, fuel and purchased energy mechanisms in each jurisdiction for recovering incurred costs. However, the utility subsidiaries have deferred February 2021 cost increases for future recovery and sought recovery of the cost increases over a period of up to 63 months to mitigate the impact to customer bills. Additionally, we did not request recovery of financing costs in order to further limit the impact to our customers. Xcel Energy currently has approval for recovery of Winter Storm Uri costs in Wisconsin, Michigan, North Dakota and New Mexico. There were no material costs for South Dakota.

A summary of the pending regulatory requests for Winter Storm Uri cost recovery in the other states is listed below.

Proceedings initiated:

Utility SubsidiaryJurisdictionRegulatory Status
NSP-MinnesotaMinnesotaIn 2021, the MPUC allowed recovery of $179 million of costs (with no financing charge) starting in September 2021, with a potential true-up pending a prudency review. The C&I class ($82 million) will be recovered over 27 months and the residential class ($97 million) will be recovered over a 63-month recovery period. The Department of Commerce recommended a disallowance of $122 million, the Office of the Attorney General recommended disallowances of $110 million to $148 million and the CUB recommended a $69 million disallowance. In May 2022, the ALJs found the Winter Storm Uri fuel costs were prudently incurred and recommended no disallowances. A MPUC decision is expected in August 2022.
Utility SubsidiaryJurisdictionRegulatory Status
PSCoColoradoIn May 2021, PSCo filed a request with the CPUC to recover $263 million in weather-related electric costs, $287 million in incremental natural gas costs and $4 million in incremental steam costs over 24 months with no financing charge. In October, a partial settlement was reached with the Staff and the Colorado Energy Office, allowing full recovery of the Winter Storm Uri costs over a 24-month (electric) and 30-month period (natural gas), with no carrying charges. In May 2022, an ALJ recommended full recovery of all costs with no cost disallowances. In July 2022, the CPUC approved the partial settlement, but included an $8 million disallowance.
SPSTexasIn 2021, SPS filed to recover $88 million of Winter Storm Uri costs over 24 months, as part of the Texas fuel surcharge filing, with total under-recovered costs of $121 million. In April 2022, interim rates designed to recover $121 million over 30 months were implemented. The interim rate recovery does not address the prudence of costs nor the retention of approximately $10 million related to market sales during the event. These items will be reviewed through the triennial Fuel Reconciliation proceeding and are subject to a final PUCT decision. In July 2022, the intervenors filed recommendations in the Fuel Reconciliation proceeding. The Texas Industrial Energy Consumers and PUCT staff recommended disallowances of approximately $10 million (off-system sales margins). The Office of Public Utility Counsel recommended disallowances of approximately $15 million (off-system sales margins and adjustment to energy loss factors). The Alliance of Xcel Municipalities recommended disallowances of approximately $100 million (natural gas storage, contracted capability and off-system sales margins). A hearing is scheduled to begin in August and a recommendation from the ALJ is expected in the fourth quarter of 2022.
Environmental

Affordable Clean Energy

In July 2019, the EPA adopted the ACE rule, which requires states to develop plans by 2022 for greenhouse gas reductions from coal-fired power plants. In January 2021, the U.S. Court of Appeals for the D.C. Circuit issued a decision vacating and remanding the ACE rule. That decision essentially held that EPA’s previous economy-wide regulatory approach taken in the 2015 CPP was consistent with the Clean Air Act. If upheld, that decision would have allowed the EPA to proceed with alternate regulation of coal-fired power plants consistent with the CPP approach. However, the Court of Appeals decision was appealed to the U.S Supreme Court. In a June 30, 2022, ruling, the Supreme Court held that a CPP economy-wide approach is not consistent with the Clean Air Act. Thus, if EPA is to proceed with new rules, they must be consistent with this ruling and be more similar to the ACE rule “inside the fenceline” approach. If any new rules require additional investment, Xcel Energy believes that the cost of these initiatives or replacement generation would be recoverable through rates based on prior state commission practices.

Derivatives, Risk Management and Market Risk

We are exposed to a variety of market risks in the normal course of business. Market risk is the potential loss that may occur as a result of adverse changes in the market or fair value of a particular instrument or commodity. All financial and commodity-related instruments, including derivatives, are subject to market risk.

Table of Contents

See Note 8 to the consolidated financial statements for further discussion of market risks associated with derivatives.

Xcel Energy is exposed to the impact of adverse changes in price for energy and energy-related products, which is partially mitigated by the use of commodity derivatives. In addition to ongoing monitoring and maintaining credit policies intended to minimize overall credit risk, management takes steps to mitigate changes in credit and concentration risks associated with its derivatives and other contracts, including parental guarantees and requests of collateral. While we expect that the counterparties will perform under the contracts underlying its derivatives, the contracts expose us to some credit and non-performance risk.

Distress in the financial markets may impact counterparty risk, the fair value of the securities in the nuclear decommissioning fund and pension fund and Xcel Energy’s ability to earn a return on short-term investments.

Commodity Price Risk — We are exposed to commodity price risk in our electric and natural gas operations. Commodity price risk is managed by entering into long- and short-term physical purchase and sales contracts for electric capacity, energy and energy-related products and fuels used in generation and distribution activities. Commodity price risk is also managed through the use of financial derivative instruments. Our risk management policy allows us to manage commodity price risk within each rate-regulated operation per commission approved hedge plans.

Wholesale and Commodity Trading Risk — Xcel Energy conducts various wholesale and commodity trading activities, including the purchase and sale of electric capacity, energy, energy-related instruments and natural gas-related instruments, including derivatives. Our risk management policy allows management to conduct these activities within guidelines and limitations as approved by our risk management committee.

Fair value of net commodity trading contracts as of June 30, 2022:

Futures / Forwards Maturity
(Millions of Dollars)Less Than 1 Year1 to 3 Years4 to 5 YearsGreater Than 5 YearsTotal Fair Value
NSP-Minnesota (a)$(4)$(12)$(5)$(3)$(24)
NSP- Minnesota (b)35(2)(3)3
PSCo (a)1492126
PSCo (b)(33)(39)—1(71)
$(20)$(37)$(5)$(4)$(66)
Options Maturity
(Millions of Dollars)Less Than 1 Year1 to 3 Years4 to 5 YearsGreater Than 5 YearsTotal Fair Value
NSP-Minnesota (b)$3$—$—$11$14
PSCo (b)2024——44
$23$24$—$11$58

(a) Prices actively quoted or based on actively quoted prices.

(b) Prices based on models and other valuation methods.

Changes in the fair value of commodity trading contracts before the impacts of margin-sharing for the six months ended June 30:

(Millions of Dollars)20222021
Fair value of commodity trading net contracts outstanding at Jan. 1$(33)$(54)
Contracts realized or settled during the period6(37)
Commodity trading contract additions and changes during the period1956
Fair value of commodity trading net contracts outstanding at March 31$(8)$(35)

At June 30, 2022, a 10% increase in market prices for commodity trading contracts through the forward curve would increase pre-tax income from continuing operations by approximately $13 million, whereas a 10% decrease would decrease pre-tax income from continuing operations by approximately $13 million. At June 30, 2021, a 10% increase in market prices for commodity trading contracts would increase pre-tax income from continuing operations by approximately $19 million, whereas a 10% decrease would decrease pre-tax income from continuing operations by approximately $19 million. Market price movements can exceed 10% under abnormal circumstances.

The utility subsidiaries’ commodity trading operations measure the outstanding risk exposure to price changes on contracts and obligations that have been entered into, but not closed, using an industry standard methodology known as VaR. VaR expresses the potential change in fair value on the outstanding contracts and obligations over a particular period of time under normal market conditions.

The VaRs for the NSP-Minnesota and PSCo commodity trading operations, excluding both non-derivative transactions and derivative transactions designated as normal purchase, normal sales, calculated on a consolidated basis using a Monte Carlo simulation with a 95% confidence level and a one-day holding period, were as follows:

(Millions of Dollars)Three Months Ended June 30AverageHighLow
2022$1.8$2.0$3.3$1.1
20211.71.21.90.7

Nuclear Fuel Supply — NSP-Minnesota has contracted for and has its 2022 and 2023 enriched nuclear material requirements in various stages of processing in Canada, Europe and the United States. We will continue to monitor the evolving situation in Ukraine and its global impacts and will take necessary actions to ensure a secure supply of enriched nuclear material. NSP-Minnesota is scheduled to take delivery of approximately 30% of its average enriched nuclear material requirements from Russia through 2030.

Interest Rate Risk — Xcel Energy is subject to interest rate risk. Our risk management policy allows interest rate risk to be managed through the use of fixed rate debt, floating rate debt and interest rate derivatives such as swaps, caps, collars and put or call options.

At June 30, 2022 and 2021, a 100-basis-point change in the benchmark rate on Xcel Energy’s variable rate debt would impact pre-tax interest expense annually by approximately $2 million and $18 million, respectively.

See Note 8 to the consolidated financial statements for a discussion of Xcel Energy’s interest rate derivatives.

NSP-Minnesota maintains a nuclear decommissioning fund, as required by the NRC. The nuclear decommissioning fund is subject to interest rate risk and equity price risk. The fund is invested in a diversified portfolio of cash equivalents, debt securities, equity securities and other investments. These investments may be used only for the purpose of decommissioning NSP-Minnesota’s nuclear generating plants.

Realized and unrealized gains on the decommissioning fund investments are deferred as an offset of NSP-Minnesota’s regulatory asset for nuclear decommissioning costs. Fluctuations in equity prices or interest rates affecting the nuclear decommissioning fund do not have a direct impact on earnings due to the application of regulatory accounting.

Changes in discount rates and expected return on plan assets impact the value of pension and postretirement plan assets and/or benefit costs.

Table of Contents

Credit Risk — Xcel Energy is also exposed to credit risk. Credit risk relates to the risk of loss resulting from counterparties’ nonperformance on their contractual obligations. Xcel Energy maintains credit policies intended to minimize overall credit risk and actively monitors these policies to reflect changes and scope of operations.

At June 30, 2022, a 10% increase in commodity prices would have resulted in an increase in credit exposure of $86 million, while a decrease in prices of 10% would have resulted in a decrease in credit exposure of $73 million. At June 30, 2021, a 10% increase in commodity prices would have resulted in an increase in credit exposure of $64 million, while a decrease in prices of 10% would have resulted in a decrease in credit exposure of $24 million.

Xcel Energy conducts credit reviews for all counterparties and employs credit risk control, such as letters of credit, parental guarantees, master netting agreements and termination provisions. Credit exposure is monitored and when necessary, the activity with a specific counterparty is limited until credit enhancement is provided. Distress in the financial markets could increase our credit risk.

FAIR VALUE MEASUREMENTS

Xcel Energy uses derivative contracts such as futures, forwards, interest rate swaps, options and FTRs to manage commodity price and interest rate risk. Derivative contracts, with the exception of those designated as normal purchase-normal sale contracts, are reported at fair value.

The Company’s investments held in the nuclear decommissioning fund, rabbi trusts, pension and other postretirement funds are also subject to fair value accounting.

See Note 8 to the consolidated financial statements for further discussion of the fair value hierarchy and the amounts of assets and liabilities measured at fair value that have been assigned to Level 3.

Commodity Derivatives — Xcel Energy monitors the creditworthiness of the counterparties to its commodity derivative contracts and assesses each counterparty’s ability to perform on the transactions. The impact of discounting commodity derivative assets for counterparty credit risk was not material to the fair value of commodity derivative assets at June 30, 2022.

Adjustments to fair value for credit risk of commodity trading instruments are recorded in electric revenues. Credit risk adjustments for other commodity derivative instruments are deferred as other comprehensive income or deferred as regulatory assets and liabilities. Classification as a regulatory asset or liability is based on commission approved regulatory recovery mechanisms. The impact of discounting commodity derivative liabilities for credit risk was immaterial at June 30, 2022.

LIQUIDITY AND CAPITAL RESOURCES

Cash Flows

Operating Cash Flows

(Millions of Dollars)Six Months Ended June 30
Cash provided by operating activities — 2021$489
Components of change — 2022 vs. 2021
Higher net income35
Non-cash transactions (a)106
Changes in working capital (b)256
Changes in net regulatory and other assets and liabilities1,102
Cash provided by operating activities — 2022$1,988

(a)Non-cash transactions applicable to net income (e.g., depreciation and amortization, nuclear fuel amortization, changes in deferred income taxes, allowance for equity funds used during construction, etc.).

(b)Working capital includes accounts receivable, accrued unbilled revenues, inventories, accounts payable, other current assets and other current liabilities.

Net cash provided by operating activities increased $1,499 million for the six months ended June 30, 2022 compared with the prior year. The increase was primarily due to the net natural gas, fuel and purchased energy costs related to Winter Storm Uri in the first quarter of 2021.

Investing Cash Flows

(Millions of Dollars)Six Months Ended June 30
Cash used in investing activities — 2021$(2,202)
Components of change — 2022 vs. 2021
Increased capital expenditures(73)
Other investing activities220
Cash used in investing activities — 2022$(2,055)

Net cash used in investing activities decreased $147 million for the six months ended June 30, 2022 compared with the prior year. The increase in capital expenditures was largely due to timing and normal system expansion.

Financing Cash Flows

(Millions of Dollars)Six Months Ended June 30
Cash provided by financing activities — 2021$2,122
Components of change — 2022 vs. 2021
Higher net short-term debt repayments(2,030)
Higher long-term debt issuances, net of repayments44
Higher proceeds from issuance of common stock140
Other financing activities(40)
Cash provided by financing activities — 2022$236

Net cash provided by financing activities decreased $1,886 million for the six months ended June 30, 2022 compared with the prior year. The decrease was primarily related to the amount/timing of debt issuances and repayments associated with Winter Storm Uri.

Capital Requirements

Xcel Energy expects to meet future financing requirements by periodically issuing short-term debt, long-term debt, common stock, hybrid and other securities to maintain desired capitalization ratios.

Table of Contents

Pension Fund — Xcel Energy’s pension assets are invested in a diversified portfolio of domestic and international equity securities, short-term to long-duration fixed income securities, and alternative investments, including private equity, real estate and hedge funds.

  • In January 2022, contributions of $50 million were made across four of Xcel Energy’s pension plans.

  • In 2021, contributions of $131 million were made across four of Xcel Energy’s pension plans.

  • For future years, contributions will be made as deemed appropriate based on evaluation of various factors including the funded status of the plans, minimum funding requirements, interest rates and expected investment returns.

Capital Sources

Short-Term Funding Sources — Xcel Energy uses a number of sources to fulfill short-term funding needs, including operating cash flow, notes payable, commercial paper and bank lines of credit. The amount and timing of short-term funding needs depend on financing needs for construction expenditures, working capital and dividend payments.

Short-Term Investments — Xcel Energy Inc., NSP-Minnesota, NSP-Wisconsin, PSCo and SPS maintain cash operating and short-term investment accounts.

Revolving Credit Facilities — Xcel Energy Inc., NSP-Minnesota, PSCo and SPS each have the right to request an extension of the revolving credit facility for two additional one-year periods beyond the June 2024 termination date. NSP-Wisconsin has the right to request an extension of the revolving credit facility termination date for an additional one-year period. All extension requests are subject to majority bank group approval.

As of July 25, 2022, Xcel Energy Inc. and its utility subsidiaries had the following committed credit facilities available to meet liquidity needs:

(Millions of Dollars)Credit Facility (a)Drawn (b)AvailableCashLiquidity
Xcel Energy Inc.$1,250$73$1,177$5$1,182
PSCo7001965042506
NSP-Minnesota500114892491
SPS50024985503
NSP-Wisconsin1508664165
Total$3,100$368$2,732$15$2,747

(a)Credit facilities expire in June 2024.

(b)Includes outstanding commercial paper and letters of credit.

Bilateral Credit Agreement

In April 2022, NSP-Minnesota’s uncommitted $75 million bilateral credit agreement was renewed for an additional one-year term. The credit agreement is limited in use to support letters of credit.

As of June 30, 2022, NSP-Minnesota had $43 million of outstanding letters of credit under the $75 million bilateral credit agreement.

Short-Term Debt — Xcel Energy Inc., NSP-Minnesota, NSP-Wisconsin, PSCo and SPS each have individual commercial paper programs. The authorized levels for these commercial paper programs are:

  • $1.25 billion for Xcel Energy Inc.

  • $700 million for PSCo.

  • $500 million for NSP-Minnesota.

  • $500 million for SPS.

  • $150 million for NSP-Wisconsin.

Short-term debt outstanding for Xcel Energy was as follows:

(Amounts in Millions, Except Interest Rates)Three Months Ended June 30, 2022Year Ended Dec. 31, 2021
Borrowing limit$3,100$3,100
Amount outstanding at period end1361,005
Average amount outstanding5541,399
Maximum amount outstanding1,1362,054
Weighted average interest rate, computed on a daily basis1.05%0.57%
Weighted average interest rate at period end1.900.31

Money Pool — Xcel Energy received FERC approval to establish a utility money pool arrangement with the utility subsidiaries, subject to receipt of required state regulatory approvals. The utility money pool allows for short-term investments in and borrowings between the utility subsidiaries.

Xcel Energy may make investments in the utility subsidiaries at market-based interest rates; however, the money pool arrangement does not allow the utility subsidiaries to make investments in Xcel Energy. The money pool balances are eliminated in consolidation. NSP-Minnesota, NSP-Wisconsin, PSCo and SPS participate in the money pool pursuant to approval from their respective state regulatory commissions.

2022 Planned Financing Activity — During 2022, Xcel Energy Inc. plans to issue approximately $75 to $80 million of equity through the DRIP and benefit programs. In addition, Xcel Energy Inc. may issue up to $800 million in equity from 2022-2026. In 2022, approximately $150 million of equity has been issued through an ATM program. Xcel Energy Inc. and its utility subsidiaries issued or plan to issue the following long-term debt:

IssuerSecurityAmountStatusTenorCoupon
Xcel EnergyUnsecured Senior Notes$700millionCompleted10 Year4.60%
PSCoFirst Mortgage Bonds300millionCompleted10 Year4.10%
PSCoFirst Mortgage Bonds400millionCompleted30 Year4.50%
SPSFirst Mortgage Bonds200millionCompleted30 Year5.15%
NSP-MinnesotaFirst Mortgage Bonds500millionCompleted30 Year4.50%
NSP-WisconsinFirst Mortgage Bonds100millionQ3 (a)30 Year4.86%

(a)The NSP-Wisconsin private placement first mortgage bonds have been priced and the transaction is expected to close on Sept. 12, 2022.

Financing plans are subject to change, depending on legislative initiatives (e.g., federal tax law changes), capital expenditures, regulatory outcomes, internal cash generation, market conditions and other factors.

Off-Balance-Sheet Arrangements

Xcel Energy does not have any off-balance-sheet arrangements, other than those currently disclosed, that have or are reasonably likely to have a current or future effect on financial condition, changes in financial condition, revenues or expenses, results of operations, liquidity, capital expenditures or capital resources that is material to investors.

Table of Contents

Earnings Guidance and Long-Term EPS and Dividend Growth Rate Objectives

Xcel Energy 2022 Earnings Guidance — Xcel Energy’s 2022 GAAP and ongoing earnings guidance is a range of $3.10 to $3.20 per share.(a)

Key assumptions as compared with 2021 levels unless noted:

  • Constructive outcomes in all rate case and regulatory proceedings.

  • Normal weather patterns for the remainder of the year.

  • Weather-normalized retail electric sales are projected to increase ~2%.

  • Weather-normalized retail firm natural gas sales are projected to increase ~1%.

  • Capital rider revenue is projected to increase $0 million to $10 million (net of PTCs).

  • O&M expenses are projected to increase approximately 2%.

  • Depreciation expense is projected to increase approximately $300 million to $310 million. The change in assumption is primarily a result of new rates going into effect in Texas and will be offset by revenue with minimal impact on earnings.

  • Property taxes are projected to increase approximately $35 million to $45 million.

  • Interest expense (net of AFUDC - debt) is projected to increase $100 million to $110 million. The assumption change reflects higher interest rates and slightly larger debt issuances.

  • AFUDC - equity is projected to be relatively flat.

  • ETR is projected to be ~(6%) to (8%).

(a) Ongoing earnings is calculated using net income and adjusting for certain nonrecurring or infrequent items that are, in management’s view, not reflective of ongoing operations. Ongoing earnings could differ from those prepared in accordance with GAAP for unplanned and/or unknown adjustments. Xcel Energy is unable to forecast if any of these items will occur or provide a quantitative reconciliation of the guidance for ongoing EPS to corresponding GAAP EPS.

Long-Term EPS and Dividend Growth Rate Objectives — Xcel Energy expects to deliver an attractive total return to our shareholders through a combination of earnings growth and dividend yield, based on the following long-term objectives:

  • Deliver long-term annual EPS growth of 5% to 7% based off of a 2021 base of $2.96 per share, which represents the mid-point of the revised 2021 guidance range of $2.94 to $2.98 per share.

  • Deliver annual dividend increases of 5% to 7%.

  • Target a dividend payout ratio of 60% to 70%.

  • Maintain senior secured debt credit ratings in the A range.