Item 2. PROPERTIES

23K characters. Original on sec.gov ·

Item 2. PROPERTIES

GENERATION FACILITIES

As of December 31, 2021, the AEP System owned (or leased where indicated) generation plants, with locations and net maximum power capabilities (winter rating), are shown in the following tables:

Vertically Integrated Utilities Segment

AEGCo
Plant NameUnitsStateFuel TypeNet Maximum Capacity (MWs)Year Plant or First Unit Commissioned
Rockport, Units 1 and 2 – 50% of each (a)2INSteam - Coal1,3101984

(a)Rockport Plant, Unit 2 is leased. In April 2021, AEGCo and I&M executed an agreement to purchase 100% of the interests in Rockport Plant, Unit 2 effective at the end of the lease term in December 2022.

APCo
Plant NameUnitsStateFuel TypeNet Maximum Capacity (MWs)Year Plant or First Unit Commissioned
Buck3VAHydro111912
Byllesby4VAHydro191912
Claytor4VAHydro761939
Leesville2VAHydro501964
London3WVHydro141935
Marmet3WVHydro141935
Niagara2VAHydro11906
Winfield3WVHydro151938
Ceredo6WVNatural Gas5162001
Dresden3OHNatural Gas6652012
Smith Mountain5VAPumped Storage5851965
Amos3WVSteam - Coal2,9301971
Mountaineer1WVSteam - Coal1,3201980
Clinch River2VASteam - Natural Gas4651958
Total MWs6,681
I&M
Plant NameUnitsStateFuel TypeNet Maximum Capacity (MWs)Year Plant or First Unit Commissioned
Berrien Springs12MIHydro71908
Buchanan10MIHydro31919
Constantine4MIHydro11921
Elkhart3INHydro31913
Mottville4MIHydro21923
Twin Branch Hydro8INHydro41904
Deer Creek Solar FarmNAINSolar32016
Olive Solar FarmNAINSolar52016
St. JosephNAINSolar202021
Twin Branch Solar FarmNAINSolar32016
WatervlietNAMISolar52016
Rockport (Units 1 and 2, 50% of each) (a)2INSteam - Coal1,3101984
Cook2MISteam - Nuclear2,2961975
Total MWs3,662

(a)Rockport Plant, Unit 2 is leased. In April 2021, AEGCo and I&M executed an agreement to purchase 100% of the interests in Rockport Plant, Unit 2 effective at the end of the lease term in December 2022.

NA Not applicable.

The following table provides operating information related to the Cook Plant:

Cook Plant
Unit 1Unit 2
Year Placed in Operation19751978
Year of Expiration of NRC License20342037
Nominal Net Electrical Rating in MWs1,0841,212
Annual Capacity Utilization
202196.0%84.2%
202087.2%94.2%
201977.3%84.3%
KPCo
Plant NameUnitsStateFuel TypeNet Maximum Capacity (MWs)Year Plant or First Unit Commissioned
Mitchell (a)(b)2WVSteam - Coal7801971
Big Sandy1KYSteam - Natural Gas2951963
Total MWs1,075

(a)KPCo owns a 50% interest in the Mitchell Plant units. WPCo owns the remaining 50%. Figures presented reflect only the portion owned by KPCo.

(b)In November 2021, KPCo made filings with KPSC, WVPSC and FERC to approve a new proposed Mitchell Plant Operations and Maintenance Agreement and Mitchell Plant Ownership Agreement between KPCo and WPCo pursuant to which WPCo will replace KPCo as the operator of Mitchell Plant. See “Dispositions of KPCo and KTCo” section of Note 7 included in the 2021 Annual Report for additional information.

PSO
Plant NameUnitsStateFuel TypeNet Maximum Capacity (MWs)Year Plant or First Unit Commissioned
Comanche3OKNatural Gas2481973
Northeastern, Unit 11OKNatural Gas4701961
Riverside, Units 3 and 42OKNatural Gas1602008
Southwestern, Units 4 and 52OKNatural Gas1682008
Weleetka2OKNatural Gas1001975
Northeastern, Unit 31OKSteam - Coal4651979
Northeastern, Unit 21OKSteam - Natural Gas4341961
Riverside, Units 1 and 22OKSteam - Natural Gas8961974
Southwestern, Units 1, 2 and 33OKSteam - Natural Gas4461952
Tulsa2OKSteam - Natural Gas3221956
Maverick (a)NAOKWind1312021
Sundance (a)NAOKWind912021
Total MWs3,931

(a)SWEPCo owns a 54.5% interest and PSO owns the remaining 45.5% interest in Sundance and Maverick.

NA Not applicable.

SWEPCo
Plant NameUnitsStateFuel TypeNet Maximum Capacity (MWs)Year Plant or First Unit Commissioned
Mattison4ARNatural Gas3142007
Stall3LANatural Gas5342010
Flint Creek (a)1ARSteam - Coal2581978
Turk (a)1ARSteam - Coal4772012
Welsh (b)2TXSteam - Coal1,0531977
Pirkey (a)(c)1TXSteam - Lignite5801985
Arsenal Hill1LASteam - Natural Gas1101960
Knox Lee1TXSteam - Natural Gas3441950
Lieberman3LASteam - Natural Gas2171947
Wilkes3TXSteam - Natural Gas8891964
Maverick (d)NAOKWind1562021
Sundance (d)NAOKWind1082021
Total MWs5,040

(a)Jointly-owned with nonaffiliated entities. Figures presented reflect only the portion owned by SWEPCo. The Arkansas jurisdictional portion of SWEPCo’s interest in Turk Plant is not in rate base.

(b)In November 2020, management announced it will cease using coal at the Welsh Plant in 2028.

(c)In November 2020, management announced plans to retire the plant in 2023.

(d)SWEPCo owns a 54.5% interest and PSO owns the remaining 45.5% interest in Sundance and Maverick.

NA Not applicable.

WPCo
Plant NameUnitsStateFuel TypeNet Maximum Capacity (MWs)Year Plant or First Unit Commissioned
Mitchell (a)(b)2WVSteam - Coal7801971

(a)WPCo owns 50% in the Mitchell Plant units. KPCo owns the remaining 50%. Figures presented reflect only the portion owned by WPCo.

(b)In November 2021, KPCo made filings with KPSC, WVPSC and FERC to approve a new proposed Mitchell Plant Operations and Maintenance Agreement and Mitchell Plant Ownership Agreement between KPCo and WPCo pursuant to which WPCo will replace KPCo as the operator of Mitchell Plant. See “Dispositions of KPCo and KTCo” section of Note 7 included in the 2021 Annual Report for additional information.

Generation & Marketing Segment

AGR
Plant NameUnitsStateFuel TypeNet Maximum Capacity (MWs)Year Plant or First Unit Commissioned
Cardinal1OHSteam - Coal5951967
Renewable Power
Size of Energy ResourceAEP Energy Supply, LLC DivisionRenewable Energy ResourceLocationIn-Service or Under Construction
1,435 MWAEP RenewablesWindEight states (a)In-service
20 MWAEP RenewablesSolarCaliforniaIn-service
20 MWAEP RenewablesSolarUtahIn-service
125 MWAEP RenewablesSolarNevadaIn-service
161 MWAEP OnSite PartnersSolarSeventeen states (b)In-service
27 MWAEP OnSite PartnersSolarTwo states (c)Under Construction

(a) Colorado, Hawaii, Indiana, Kansas, Michigan, Minnesota, Pennsylvania and Texas.

(b) California, Colorado, Florida, Hawaii, Illinois, Iowa, Minnesota, Nebraska, New Hampshire, New Jersey, New Mexico, New York, Ohio, Rhode Island, Texas, Vermont and Wisconsin.

(c) Ohio and New Mexico.

TRANSMISSION AND DISTRIBUTION FACILITIES

The following tables set forth the total overhead circuit miles of transmission and distribution lines of the AEP System and its operating companies.

Vertically Integrated Utilities Segment

Total Overhead Circuit Miles of Transmission and Distribution Lines
APCo51,714
I&M20,943
KGPCo1,408
KPCo11,166
PSO18,145
SWEPCo26,162
WPCo1,730
Total Circuit Miles131,268

Transmission and Distribution Utilities Segment

Total Overhead Circuit Miles of Transmission and Distribution Lines
OPCo44,703
AEP Texas46,353
Total Circuit Miles91,056

AEP Transmission Holdco Segment

The following table sets forth the total overhead circuit miles of transmission lines of certain wholly-owned and joint venture-owned entities:

Total Overhead Circuit Miles of Transmission Lines
ETT1,883
IMTCo990
OHTCo1,026
OKTCo1,015
WVTCo261
Pioneer43
Prairie Wind Transmission216
Transource Missouri167
Transource West Virginia27
Total Circuit Miles5,628

TITLE TO PROPERTY

The AEP System’s generating facilities are generally located on lands owned in fee simple. The greater portion of the transmission and distribution lines of the AEP System has been constructed over lands of private owners pursuant to easements or along public highways and streets pursuant to appropriate statutory authority. The rights of AEP’s public utility subsidiaries in the realty on which their facilities are located are considered adequate for use in the conduct of their business. Minor defects and irregularities customarily found in title to properties of like size and character may exist, but such defects and irregularities do not materially impair the use of the properties. AEP’s public utility subsidiaries generally have the right of eminent domain which permits them, if necessary, to acquire, perfect or secure titles to or easements on privately held lands used or to be used in their utility operations.

SYSTEM TRANSMISSION LINES AND FACILITY SITING

Laws in the states of Arkansas, Indiana, Kentucky, Louisiana, Michigan, Ohio, Tennessee, Texas, Virginia and West Virginia require prior approval of sites of generating facilities and/or routes of high-voltage transmission lines. AEP has experienced delays and additional costs in constructing facilities as a result of proceedings conducted pursuant to such statutes and in proceedings in which AEP’s operating companies have sought to acquire rights-of-way through condemnation. These proceedings may result in additional delays and costs in future years.

CONSTRUCTION PROGRAM

With input from its state utility commissions, the AEP System continuously assesses the adequacy of its transmission, distribution, generation and other facilities to plan and provide for the reliable supply of electric power and energy to its customers. In this assessment process, assumptions are continually being reviewed as new information becomes available and assessments and plans are modified, as appropriate. AEP forecasts approximately $7.6 billion of construction expenditures for 2022. Estimated construction expenditures are subject to periodic review and modification and may vary based on the ongoing effects of regulatory constraints, environmental regulations, business opportunities, market volatility, economic trends, supply chain issues, weather, legal reviews and the ability to access capital. See the “Budgeted Capital Expenditures” section of Management’s Discussion and Analysis of Financial Condition and Results of Operations included in the 2021 Annual Report for additional information.

POTENTIAL UNINSURED LOSSES

Some potential losses or liabilities may not be insurable or the amount of insurance carried may not be sufficient to meet potential losses and liabilities, including liabilities relating to damage to AEP’s generation plants and costs of replacement power. Unless allowed to be recovered through rates, future losses or liabilities which are not completely insured could reduce net income and impact the financial conditions of AEP and other AEP System companies. For risks related to owning a nuclear generating unit, see the “Nuclear Contingencies” section of Note 6 - Commitments, Guarantees and Contingencies included in the 2021 Annual Report for additional information.