Item 3. LEGAL PROCEEDINGS
Alternative Water Supply in Lieu of Carmel River Diversions
Compliance with SWRCB Orders to Reduce Carmel River Diversions
Under the 2009 Order, Cal Am is required, among other things, to decrease significantly its yearly diversions of water from the Carmel River according to a set reduction schedule. The 2009 Order responded to claims that Cal Am had not sufficiently implemented actions to terminate its unpermitted diversions of water from the Carmel River as required by a 1995 order of the SWRCB. In July 2016, at the request of Cal Am and several Monterey County government agencies, the SWRCB issued the 2016 Order approving the 2021 Deadline.
The 2009 Order includes a condition prohibiting Cal Am from diverting water from the Carmel River for new service connections or for any increased use of water at existing service addresses resulting from a change in zoning or use. In 2011, the California Public Utilities Commission (the “CPUC”) issued a decision directing modifications in Cal Am’s tariffs to recognize the moratorium mandated by the 2009 Order, and directing Cal Am to seek written guidance from the SWRCB with respect to any unresolved issues of interpretation or implementation of this condition. In 2012, the Deputy Director of the SWRCB sent a letter to Cal Am providing an interpretation as to the calculation of a baseline to determine increases in use of water at existing service addresses. In March 2018, the MPWMD adopted a resolution directing Cal Am to interpret the baseline in a manner that conflicts with the SWRCB’s written interpretation. In May 2018, Cal Am notified the MPWMD and the SWRCB that it intends to seek declaratory relief concerning the conflicting regulatory interpretations under the 2009 Order. In an attempt to resolve these conflicting interpretations prior to seeking judicial intervention, Cal Am has met with the MPWMD and the SWRCB several times. The SWRCB agreed to circulate revisions to its 2012 interpretive letter, which would be subject to a public comment period. Any failure to follow the MPWMD’s resolution or the SWRCB’s written interpretation, despite these conflicting interpretations, could potentially result in fines, penalties and other actions against Cal Am.
The 2016 Order provides that if the CPUC authorizes Cal Am to acquire more than 1,000 acre-feet per year of water from a source other than the Water Supply Project, proponents of the alternative water source could submit revised milestones to the SWRCB for consideration. In May 2018, certain parties to the Water Supply Project proceeding submitted a petition to the SWRCB to add parallel milestones to the 2009 Order for 2019, 2020, and 2021, based on the proposed expansion of the Pure Water Monterey project, another groundwater replenishment project under construction on the Monterey peninsula. Petitioners claim that compliance with the alternate milestones would still provide for cessation of Cal Am’s unauthorized diversions from the Carmel River by 2021. A preliminary report on feasibility concluded that the expanded Pure Water Monterey project could provide an additional 2,250 acre-feet of water per year. Cal Am believes that (i) the petition is premature, (ii) the expanded Pure Water Monterey project is not yet a sufficiently certain or reliable water supply and, even if construction is successfully completed, would provide an insufficient quantity of water to allow full compliance with the 2009 Order, and (iii) the imposition of parallel milestones would distract from completion of the Water Supply Project. On December 13, 2019, the SWRCB dismissed the petition without prejudice.
Cal Am continues to work constructively with all appropriate agencies to provide necessary information in connection with obtaining required approvals for the Water Supply Project. However, based on the matters discussed below in “Monterey Peninsula Water Supply Project,” there can be no assurance that the Water Supply Project in its current configuration will be completed on a timely basis, if ever. Due to the delay in the approval schedule, Cal Am currently does not believe that it will be able to fully comply with the diversion reduction requirements and other remaining requirements under the 2009 Order and the 2016 Order, including the 2021 Deadline. The CPUC’s final decision approving the Water Supply Project permits recovery of all of Cal Am’s prudently incurred costs associated therewith, subject to the frameworks set forth in the final decision related to cost caps, O&M costs, financing, ratemaking and contingency matters. Cal Am currently believes that its expenditures to date have been prudent and necessary to comply with the 2009 Order and the 2016 Order. Further attempts to comply with the 2009 Order and the 2016 Order, or the 2021 Deadline, may result in material additional costs or obligations to Cal Am, and failure to comply could lead to fines and penalties against Cal Am.
Regional Desalination Project Litigation
Review of CPUC-Approved Settlement Agreement
The Regional Desalination Project (the “RDP”) involved the construction of a desalination facility in the City of Marina, north of Monterey. The RDP was intended to, among other things, eliminate unauthorized diversions from the Carmel River as required under the 2009 Order. In December 2010, the CPUC approved the RDP, which was to be implemented through a Water Purchase Agreement and ancillary agreements (collectively, the “Agreements”) among the Marina Coast Water District (“MCWD”), the Monterey County Water Resources Agency (“MCWRA”) and Cal Am. In 2011, due to a conflict of interest concerning a former member of MCWRA’s Board of Directors, MCWRA stated that the Agreements were void, and, as a result, Cal Am terminated the Agreements. In April 2015, the CPUC approved a settlement agreement among Cal Am, MCWRA and the County of Monterey to resolve these matters among the parties signing the agreement. In March 2016, the Supreme Court of California granted MCWD’s petition for review of the CPUC approval, and following the court’s disposition of a related issue in another case, MCWD’s petition for review of the CPUC-approved settlement agreement was remanded to the CPUC. On September 19, 2019, the CPUC issued a decision affirming its prior decisions with respect to the settlement agreement that resolved matters among the parties thereto associated with the termination of the RDP agreements, after considering the issue remanded by the California Supreme Court.
Cal Am’s Action for Damages Following RDP Termination
In October 2012, Cal Am filed a Complaint for Declaratory Relief against MCWRA and MCWD, which was ultimately transferred to the San Francisco County Superior Court, seeking a determination as to whether the Agreements are void as a result of the alleged conflict of interest. In June 2015, the court entered a final judgment agreeing with Cal Am’s position that four of the five Agreements are void, and one, the credit line agreement, is not void. In November 2016, the Supreme Court of California denied MCWD’s final appeal of this judgment, which allows further proceedings, discussed below, to determine the amount of damages that may be awarded in the proceeding.
In July 2015, Cal Am and MCWRA filed a Complaint in San Francisco County Superior Court against MCWD and RMC Water and Environment (“RMC”), a private engineering consulting firm which has since been acquired by a national engineering, science and operations company, seeking to recover compensatory damages in excess of $10 million associated with the failure of the RDP, as well as punitive and treble damages, statutory penalties and attorneys’ fees. Shortly thereafter, complaints seeking similar damages were filed in the same court by MCWD and RMC against Cal Am and MCWRA in excess of $19 million in the aggregate. In December 2015, the court consolidated all of these complaints into a single action. On February 15, 2019, the court granted Cal Am’s motion for summary judgment, and as a result, no claims remain pending against Cal Am in this action. On February 25, 2019, the court granted RMC’s motion for judgment on the pleadings as to certain of Cal Am’s tort claims against it. On June 20, 2019, the court granted MCWD’s motion for summary judgment related to Cal Am’s tort claims against MCWD, which Cal Am appealed to the California Court of Appeal, and on January 14, 2020, this appeal was denied. On January 17, 2019, a motion filed by MCWD for summary judgment against Cal Am relating to the contract claims in Cal Am’s complaint was denied.
Trial in this lawsuit had been scheduled to take place in January 2020. On January 27, 2020, the parties to this lawsuit reached a tentative agreement, which was entered into the court record and would resolve the litigation in part without trial. Under the terms of this tentative agreement, MCWD and RMC would pay Cal Am an aggregate of $5.2 million in settlement of Cal Am’s contract claims against MCWD and all claims against RMC relating to the RDP. Under this agreement, Cal Am’s and MCWRA’s right to appeal the dismissal of their tort claims against MCWD would be expressly reserved. A draft settlement agreement is being reviewed and negotiated by the parties. Once executed, the settlement agreement would be subject to approval of the San Francisco County Superior Court.
Monterey Peninsula Water Supply Project
CPUC Final Approval of Water Supply Project
Cal Am’s ability to move forward on the Water Supply Project is and has been subject to extensive administrative review by the CPUC and other government agencies, obtaining necessary permits, and intervention from other parties. In September 2016, the CPUC unanimously approved a decision to authorize Cal Am to enter into a water purchase agreement for the GWR Project and to construct a pipeline and pump station facilities and recover up to $50 million in associated costs, subject to meeting certain criteria. If construction costs exceed $50 million, Cal Am would be allowed to seek additional cost recovery.
In September 2018, the CPUC unanimously adopted a final decision finding that (i) the Water Supply Project, based on Cal Am’s request for a 6.4 million gallons per day desalination plant, meets the CPUC’s requirements for a CPCN, (ii) the issuance of the final decision should not be delayed, and (iii) an additional procedural phase was not necessary to consider alternative projects. The CPUC’s decision directs Cal Am to enter into negotiations regarding expansion of the GWR Project between Monterey One Water and the MPWMD and to indicate whether Cal Am plans to file an application for approval of an agreement to purchase additional water from the GWR Project. The decision notes, however, that the CPUC will only consider such an application if the Water Supply Project is delayed such that Cal Am would not be able to meet the 2021 Deadline. The decision accepts Cal Am’s estimates of future water demand in Monterey and concludes that the Water Supply Project is the best project to address those needs, and adopts Cal Am’s most recent cost estimates. The decision also allows Cal Am to earn an allowance for funds used during construction, or AFUDC, at a rate representative of its actual financing costs. The final decision adopted frameworks as to cost caps, O&M costs, financing, ratemaking and contingency matters.
In addition, the CPUC final decision imposes numerous reporting and filing requirements to ensure the expenditures for the Water Supply Project are reasonable, including that the financing is the lowest cost and most beneficial for ratepayers, and that construction is progressing in a timely manner and within the authorized cost caps. The reasonableness of Water Supply Project costs will be reviewed in the first general rate case filed by Cal Am after the Water Supply Project becomes operational. Cal Am is also required to implement mitigation measures to avoid, minimize or offset significant environmental impacts from the construction and operation of the Water Supply Project and comply with a mitigation monitoring and reporting program, a reimbursement agreement for CPUC costs associated with that program, and reporting requirements on plant operations following placement of the Water Supply Project in service.
In February 2019, the City of Marina and MCWD filed petitions for writ of review before the Supreme Court of California challenging the sufficiency of the final Environmental Impact Report/Environmental Impact Statement adopted by the CPUC in September 2018, which the court declined to consider on August 28, 2019.
On July 2, 2019, Cal Am notified MPWMD and Monterey One Water (collectively, the “Agencies”) that an event of default occurred under the water purchase agreement for the GWR Project because the Agencies failed to deliver to Cal Am by July 1, 2019 advanced treated recycled water produced by the GWR Project. Under the water purchase agreement, upon the occurrence of this event of default, Cal Am had the right to terminate the water purchase agreement immediately. Cal Am has elected not to exercise its right to terminate the water purchase agreement at this time, but in its notification to the Agencies, Cal Am expressly reserved its right to terminate the water purchase agreement until such time as the Agencies commence their required delivery of water from the GWR Project. On July 16, 2019, MPWMD and Monterey One Water responded to Cal Am’s event of default notice and estimated that water delivery would begin by mid-October 2019. On December 12, 2019, Cal Am sent a letter to the Agencies requesting a status update with respect to the event of default. On January 2, 2020, Cal Am notified the Agencies that a second event of default occurred under the water purchase agreement because the Agencies failed to achieve the Performance Start Date (the date upon which MPWMD’s performance obligations under the water purchase agreement were to commence) by January 1, 2020. Under the water purchase agreement, upon the occurrence of this event of default, Cal Am had the right to terminate the water purchase agreement immediately. Cal Am has elected not to exercise its right to terminate the water purchase agreement at this time, but in its notification to the Agencies, Cal Am expressly reserved its right to terminate the water purchase agreement until such time as the Performance Start Date has occurred. On January 9, 2020, the Agencies responded to Cal Am’s December 12, 2019 and January 2, 2020 letters. In the response, the Agencies acknowledged they remain in default under the water purchase agreement but indicated that corrective action is being taken to attain the Performance Start Date in the near future.
On April 17, 2019, Water Ratepayers Association of the Monterey Peninsula (“WRAMP”), a citizens’ advocacy group, filed an amended complaint in Monterey County Superior Court asserting a “qui tam” claim under the California False Claims Act on behalf of itself and the State of California against Cal Am and certain environmental consultants who worked on the CPUC’s environmental analysis of the MPWSP. The State Attorney General declined to proceed with this action after it was originally filed in 2016. On July 10, 2019, defendants filed a joint demurrer challenging the legal sufficiency of the allegations of the amended complaint. At an August 27, 2019 hearing on the demurrer, the court dismissed the petition without leave to amend. On October 17, 2019, WRAMP filed motions seeking clarification and a reconsideration of the court’s ruling. A hearing on these motions was set for December 3, 2019, but on November 26, 2019, WRAMP abandoned its motions and instead filed an appeal of the court’s dismissal. This appeal remains pending.
Coastal Development Permit Application
In June 2018, Cal Am submitted a coastal development permit application to the City of Marina for those project components of the Water Supply Project located within the City of Marina’s coastal zone. Members of the City’s Planning Commission, as well as City councilpersons, have publicly expressed opposition to the Water Supply Project. On March 7, 2019, the City of Marina Planning Commission adopted a resolution denying Cal Am’s coastal development permit application. Cal Am appealed the Marina Planning Commission's decision to the City Council, which set a public hearing on the appeal for April 30, 2019. On April 25, 2019, Cal Am submitted a letter to the City challenging the impartiality of the City and three of its council members with respect to the Water Supply Project. On April 29, 2019, the City informed Cal Am that it intended to proceed with the hearing with the participation of the challenged City Council members. As a result, on April 29, 2019, Cal Am notified the City that it was withdrawing its appeal, as Cal Am believes it could not receive a fair and impartial hearing before the City Council.
On May 10, 2019, the City issued a notice of final local action based upon the Marina Planning Commission’s decision. On May 22, 2019, Cal Am appealed this decision to the California Coastal Commission (the “Coastal Commission”), as permitted under the City’s code and the California Coastal Act. On October 28, 2019, staff of the Coastal Commission issued a report recommending a denial of Cal Am’s application for a coastal development permit with respect to the Water Supply Project, largely based on a memorandum prepared by the general manager of the MPWMD that contradicted findings made by the CPUC in its final decision approving the Water Supply Project. Staffs of the CPUC and the Coastal Commission met to discuss the Coastal Commission’s staff recommendation, at which time the CPUC raised questions about the Coastal Commission staff’s findings on water supply and demand, groundwater impacts and other matters. On November 4, 2019, Coastal Commission staff released an addendum to the staff report, concluding that additional groundwater modeling was needed before staff could find that the Water Supply Project would not prevent depletion of groundwater supplies. At its November 14, 2019 hearing on both the appeal from the City of Marina’s denial and Cal Am’s application for a coastal development permit within the Coastal Commission’s original jurisdiction, Coastal Commission staff advised that no vote would be taken at the meeting and that further investigation was required in light of the CPUC staff’s questions. The hearing was continued to a later date. On January 28, 2020, Coastal Commission staff recommended to Cal Am that it withdraw its application for a coastal development permit within the Coastal Commission’s original jurisdiction and resubmit such application at a later date, as the staff believes that its additional investigation could not be completed in time for a vote on Cal Am’s existing application. The staff indicated that such a withdrawal would not affect Cal Am’s appeal of the City of Marin’s denial, which would remain pending. Cal Am has declined to withdraw its application, and instead, on February 12, 2020, Cal Am and the Coastal Commission entered into a stipulation extending by 90 days, to July 24, 2020, the deadline for the Coastal Commission to vote on Cal Am’s original jurisdiction application.
Desalination Plant Development Permit
The proposed desalination plant for the Water Supply Project is to be located in an unincorporated portion of Monterey County, California on a site owned by CEMEX, Inc. (“CEMEX”), and requires a combined development permit from the County of Monterey prior to commencement of construction. On April 24, 2019, the County’s Planning Commission voted to approve the permit. On July 15, 2019, the Board of Supervisors heard appeals filed by MCWD and a public advocacy group, at which time it denied the appeals and approved the permit. On August 21, 2019, MCWD filed a petition in Monterey County Superior Court challenging Monterey County’s approval of Cal Am’s combined development permit application and seeking injunctive relief to enjoin Monterey County and Cal Am from commencing construction of the desalination plant. On October 9, 2019, after a hearing, the court denied, without prejudice, MCWD’s motion for a preliminary injunction, but issued a stay of the County’s approval of the combined development permit, precluding commencement of physical construction of the desalination plant until November 19, 2019, at which time the parties were to advise the court of the Coastal Commission’s decision on Cal Am’s application for a coastal development permit for the slant wells needed to source water for the desalination plant. In the interim, Cal Am is allowed to continue to obtain permits needed for the desalination plant’s construction. On November 19, 2019, the parties informed the court that the Coastal Commission had continued its public hearing on the slant wells and had not yet made a determination about permitting the slant wells. In response, the court continued its stay until March 24, 2020.
Proposed Zoning Changes at CEMEX Site for Slant Wells
In August 2018, the City circulated a public review draft of proposed amendments to its local coastal program and zoning ordinance, and placed the matter for consideration on the Planning Commission’s agenda for its September 2018 meeting. The proposed amendments would change zoning at the CEMEX site to open space and restrict future uses, including with respect to Cal Am’s planned use of the site for the slant wells for the Water Supply Project. Any change to the City's local coastal program must ultimately be approved by the Coastal Commission. Cal Am, CEMEX and the Coastal Commission each submitted letters opposing the proposed amendments. At its November 2018 meeting, the Planning Commission adopted a resolution recommending that the Marina City Council consider approving the amendments.
In December 2018, the Marina City Council considered the proposed amendments. Cal Am, CEMEX and the Coastal Commission again submitted letters opposing the proposed changes, but the City Council unanimously adopted a resolution amending its local coastal plan and a draft amendment to its zoning ordinance. Changes to the ordinance require a second reading before becoming final, which occurred at the City’s December 2018 meeting. The changes to the local coastal plan must be submitted to the Coastal Commission for approval and are not effective until such approval is obtained.
Test Slant Well Permitting
A preliminary step to building the Water Supply Project desalination plant is the construction and operation of a test slant well to confirm the suitability of the property on which intake wells will be located to draw water from under Monterey Bay. In November 2014, the Coastal Commission approved coastal development permits for the test slant well, enabling Cal Am to construct and operate the test slant well. Because Cal Am may use the test slant well as one of the slant wells for the Water Supply Project, Cal Am sought and obtained from the Coastal Commission permit amendments to allow the test slant well to remain in place and be maintained until February 28, 2020. On November 27, 2019, Cal Am filed an application with the Coastal Commission for a permit amendment to allow the test slant well to remain in place and be maintained until February 28, 2021. A required lease obtained from the California State Lands Commission, as amended, will expire on December 16, 2022. Effective February 28, 2018, test slant well pumping ceased, except for minimal maintenance pumping activities, in accordance with Cal Am’s coastal development permits.
In November 2015, MCWD filed a Petition for Writ of Mandate and Complaint for Declaratory and Injunctive Relief in Santa Cruz County Superior Court against the Coastal Commission and Cal Am challenging the amendment of the coastal development permits and seeking an injunction against further test well pumping. In orders issued in September 2016 and October 2017, the court denied MCWD’s challenges. In January 2018, MCWD filed a notice of appeal of the court’s judgment. On June 28, 2019, the California Court of Appeal dismissed MCWD’s appeal. On July 15, 2019, MCWD filed a petition for rehearing with the Court of Appeal, which was denied on July 19, 2019. This decision is now final.
Water Supply Project Land Acquisition and Slant Well Site Use
In July 2017, the Coastal Commission adopted a consent agreement and cease and desist order requiring sand mining operations on the property owned by CEMEX on which intake wells for the Water Supply Project will be located, to cease by the end of 2020 and the property to be sold to either a non-profit or governmental entity. The consent agreement strictly limits future use of the property but preserves Cal Am’s existing property rights and allows uses consistent with existing easements and other rights of record. A permanent easement granted by CEMEX to Cal Am was recorded in June 2018 to allow Cal Am access to the property and to construct, operate and maintain the Water Supply Project intake wells. On November 26, 2019, the City of Marina notified CEMEX that, based on this easement and Cal Am’s proposed use of the site for the intake wells, CEMEX has breached or will soon breach a prior 1996 annexation agreement (to which Cal Am was not a party). The City states that it intends to seek declaratory relief from CEMEX and Cal Am ordering that Cal Am’s extraction is limited to 500 acre-feet per year of groundwater, that Cal Am cannot export extracted water out of the basin, and that the permanent easement granted by CEMEX to Cal Am is void. The City has requested a meeting with CEMEX as part of a mandatory dispute resolution process under the annexation agreement prior to filing a lawsuit. CEMEX has denied the City’s claims and requested indemnification from Cal Am under the terms of the permanent easement. Cal Am and CEMEX believe that there is no valid limitation under the annexation agreement on Cal Am’s right to pump brackish groundwater and seawater at the site for desalination and use by Cal Am’s customers.
Under California’s Sustainable Groundwater Management Act (“SGMA”) enacted in 2015, groundwater basins designated by the state as critically overdrafted must be managed by a groundwater sustainability agency (“GSA”) by 2020 in accordance with an approved groundwater sustainability plan (“GSP”) designed to achieve sustainability by 2040. Under the SGMA, GSAs have broad powers to achieve sustainability including, but not limited to, regulating groundwater extraction by imposing fees on groundwater extractions and controlling groundwater extractions by regulating, limiting or suspending extractions from wells. The 400-acre CEMEX site overlies a small portion of the 180/400 Subbasin of the Salinas Valley Groundwater Basin; the 84,000-acre 180/400 Subbasin has been designated by the state as critically overdrafted, mainly due to seawater intrusion into the subbasin.
In late 2016, the Salinas Valley Basin Groundwater Sustainability Agency (“SVBGSA”) was formed as a joint powers authority to become the GSA for the Salinas Valley Groundwater Basin and prepare a GSP. In April 2018, the City of Marina filed a notice to become the GSA for the CEMEX site, creating an overlap with the SVBGSA’s filing for the 180/400 Subbasin. In 2016, the SVBGSA commenced preparation of a GSP covering the entire 180/400 subbasin, including the CEMEX site, but in August 2019 the City filed a notice that it intends to prepare its own GSP for the CEMEX site with the intent to severely limit or prohibit groundwater pumping at that site. The State Department of Water Resources (“SDWR”) has taken the position that until the overlap is resolved, it will not accept the GSP from either agency, placing the subbasin at risk of being placed in a probationary status and subject to state management. In December 2019, the County of Monterey filed its own notice to become the exclusive GSA at the CEMEX site in order to resolve the overlap, which is permitted under SGMA. SDWR accepted the County’s filing on December 18, 2019, and now lists the County as the exclusive GSA for the site.
On December 30, 2019, the City of Marina filed a lawsuit in the Supreme Court of California challenging the County’s filing, and SDWR’s acceptance of the filing, as the exclusive GSA for the CEMEX site. The City has named the County and its Board of Supervisors, the County GSA, and SDWR and its director as defendants, and the SVBGSA and its Board of Directors as real parties. The City seeks to invalidate the County’s filing, as well as injunctive relief to preserve the City’s status as a GSA for the site. To protect its interest in the matter, Cal Am filed an application to intervene in this lawsuit, which is scheduled to be heard on February 18, 2020.
West Virginia Elk River Freedom Industries Chemical Spill
See Note 16—Commitments and Contingencies—Contingencies—West Virginia Elk River Freedom Industries Chemical Spill in the Notes to Consolidated Financial Statements for information regarding the final court approval of the global settlement with respect to the January 2014 Freedom Industries, Inc. chemical spill.
Dunbar, West Virginia Water Main Break Class Action Litigation
On the evening of June 23, 2015, a 36-inch pre-stressed concrete transmission water main, installed in the early 1970s, failed. The water main is part of WVAWC’s West Relay pumping station located in the City of Dunbar. The failure of the main caused water outages and low pressure to up to approximately 25,000 WVAWC customers. In the early morning hours of June 25, 2015, crews completed a repair, but that same day, the repair developed a leak. On June 26, 2015, a second repair was completed and service was restored that day to approximately 80% of the impacted customers, and to the remaining approximately 20% by the next morning. The second repair showed signs of leaking but the water main was usable until June 29, 2015 to allow tanks to refill. The system was reconfigured to maintain service to all but approximately 3,000 customers while a final repair was completed safely on June 30, 2015. Water service was fully restored on July 1, 2015 to all customers affected by this event.
On June 2, 2017, a complaint captioned Jeffries, et al. v. West Virginia-American Water Company was filed in West Virginia Circuit Court in Kanawha County on behalf of an alleged class of residents and business owners who lost water service or pressure as a result of the Dunbar main break. The complaint alleges breach of contract by WVAWC for failure to supply water, violation of West Virginia law regarding the sufficiency of WVAWC’s facilities and negligence by WVAWC in the design, maintenance and operation of the water system. The Jeffries plaintiffs seek unspecified alleged damages on behalf of the class for lost profits, annoyance and inconvenience, and loss of use, as well as punitive damages for willful, reckless and wanton behavior in not addressing the risk of pipe failure and a large outage.
In October 2017, WVAWC filed with the court a motion seeking to dismiss all of the Jeffries plaintiffs’ counts alleging statutory and common law tort claims. Furthermore, WVAWC asserted that the Public Service Commission of West Virginia, and not the court, has primary jurisdiction over allegations involving violations of the applicable tariff, the public utility code and related rules. In May 2018, the court, at a hearing, denied WVAWC’s motion to apply the primary jurisdiction doctrine, and in October 2018, the court issued a written order to that effect. On February 21, 2019, the court issued an order denying WVAWC’s motion to dismiss the Jeffries plaintiffs’ tort claims. On August 21, 2019, the court set a procedural schedule in this case, including a trial date of September 21, 2020. Discovery in this case is ongoing. On February 4, 2020, the Jeffries plaintiffs filed a motion seeking class certification on the issues of breach of contract and negligence, and to determine the applicability of punitive damages and a multiplier for those damages if imposed. A hearing on class certification is currently scheduled for March 11, 2020.
The Company and WVAWC believe that WVAWC has meritorious defenses to the claims raised in this class action complaint and WVAWC will continue to vigorously defend itself against these allegations.
Chattanooga, Tennessee Water Main Break Class Action Litigation
On September 12, 2019, Tennessee-American Water Company, a wholly owned subsidiary of the Company (“TAWC”), experienced a break of a 36-inch water transmission main, which caused service fluctuations or interruptions to TAWC customers and the issuance of a boil water notice. TAWC repaired the main break by early morning on September 14, 2019, and restored full water service by the afternoon on September 15, 2019, with the boil water notice lifted for all customers on September 16, 2019.
On September 17, 2019, a complaint captioned Bruce, et al. v. American Water Works Company, Inc., et al. was filed in the Circuit Court of Hamilton County, Tennessee against TAWC, the Company and the Service Company (collectively, the “Tennessee-American Water Defendants”), on behalf of an alleged class of individuals or entities who lost water service or suffered monetary losses as a result of the Chattanooga main break (the “Tennessee Plaintiffs”). The complaint alleges breach of contract and negligence against the Tennessee-American Water Defendants, as well as an equitable remedy of piercing the corporate veil. The Tennessee Plaintiffs seek an award of unspecified alleged damages for wage losses, business and economic losses, out-of-pocket expenses, loss of use and enjoyment of property and annoyance and inconvenience, as well as punitive damages, attorneys’ fees and pre- and post-judgment interest.
On November 22, 2019, the Tennessee-American Water Defendants filed a motion to dismiss the complaint for failure to state a claim upon which relief may be granted, and, with respect to the Company, for lack of personal jurisdiction. A hearing on this motion is scheduled for February 18, 2020.
The Tennessee-American Water Defendants believe that they have meritorious defenses to the claims raised in this class action complaint, and they are vigorously defending themselves against these allegations.
CSG — East Palo Alto Water System Voluntary Report
In April 2017, AWE, the parent entity of CSG, voluntarily reported to the Division of Drinking Water of the SWRCB potential violations of the California Safe Drinking Water Act (the “CSDWA”) in connection with AWE’s operation of the City of East Palo Alto’s water distribution system. Upon the resignation of the system’s general manager in March 2017, AWE discovered that it may have operated the system without a properly certified operator for two years, the triennial LCR sampling was not completed, and the 2015 Consumer Confidence Report improperly reported data for lead and copper samples from the system’s upstream water provider. Promptly after discovering these issues, AWE engaged an outside law firm to conduct an internal investigation and reported the results of that investigation to the SWRCB.
On June 15, 2017, the SWRCB issued to AWE a citation that required AWE to, among other things: comply with regulations related to water operator certifications, lead and copper tap sampling requirements and the publishing of a Consumer Confidence Report; provide public notification of the LCR violation; and prepare a corrective action plan to evaluate the causes leading to these incidents and measures to be taken to prevent recurrence of future incidents. The citation did not impose on AWE any monetary penalties, but the SWRCB reserved the right to take additional enforcement action.
In October 2017, the SWRCB advised AWE that it is in compliance with all of the directives and relevant statutory and administrative provisions specified in the SWRCB’s June 2017 citation. In February 2018, the SWRCB referred this matter to the San Mateo County, California District Attorney’s office for further investigation. AWE continues to cooperate with the SWRCB, the City of East Palo Alto and the San Mateo County District Attorney regarding this matter. Proven violations of the CSDWA may result in civil and criminal penalties.
General
Periodically, the Company is involved in other proceedings or litigation arising in the ordinary course of business. Other than those proceedings described in this Item 3—Legal Proceedings, the Company does not believe that the ultimate resolution of these matters will materially affect its financial position or results of operations. However, litigation and other proceedings are subject to many uncertainties, and the outcome of individual matters is not predictable with assurance. It is possible that some litigation and other proceedings could be decided unfavorably to the Company, and that any such unfavorable decisions could have a material adverse effect on its business, financial condition, results of operations and cash flows.