Item 4. CONTROLS AND PROCEDURES
11K characters. Original on sec.gov · Markdown
Item 4. CONTROLS AND PROCEDURES
Evaluation of Disclosure Controls and Procedures
American Water maintains disclosure controls and procedures that are designed to ensure that information required to be disclosed in its reports filed or submitted under the Exchange Act is recorded, processed, summarized and reported within the time periods specified in the SEC’s rules and forms, and that such information is accumulated and communicated to management, including the Chief Executive Officer and the Chief Financial Officer, to allow timely decisions regarding required disclosure. In designing and evaluating the disclosure controls and procedures, management recognizes that any controls and procedures, no matter how well designed and operated, can provide only reasonable assurance of achieving the desired control objective.
The Company’s management, including the Chief Executive Officer and the Chief Financial Officer, conducted an evaluation of the effectiveness of its disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) of the Exchange Act) as of March 31, 2024.
Based on that evaluation, the Chief Executive Officer and the Chief Financial Officer have concluded that, as of March 31, 2024, the Company’s disclosure controls and procedures were effective at a reasonable level of assurance.
Changes in Internal Control over Financial Reporting
The Company concluded that there have been no changes in internal control over financial reporting that occurred during the three months ended March 31, 2024, that have materially affected, or are reasonably likely to materially affect, the Company’s internal control over financial reporting.
PART II. OTHER INFORMATION
ITEM 1. LEGAL PROCEEDINGS
The following information updates and amends the information provided in the Company’s Form 10-K in Item 3—Legal Proceedings. Capitalized terms used but not otherwise defined herein have the meanings set forth in the Company’s Form 10-K. In accordance with the SEC’s disclosure rules, the Company has elected to disclose environmental proceedings involving the Company and a governmental authority if the amount of potential monetary sanctions, exclusive of interest and costs, that the Company reasonably believes will result from such proceeding is $1 million or more.
Alternative Water Supply in Lieu of Carmel River Diversions
Monterey Peninsula Water Supply Project
Water Supply Project Land Acquisition and Slant Well Site Use
The July 15, 2024 trial date previously set by the Monterey County Superior Court for the City’s May 2020 lawsuit has been vacated pending receipt of the SWRCB’s expert advisory opinion. The court scheduled a status and trial setting conference for July 15, 2024.
Challenges Related to Compliance with California’s Sustainable Groundwater Management Act
In November 2021, the City appealed the court’s decision denying the City’s claims, and in December 2021, Monterey County appealed as to the court’s finding that the City’s action creating a GSA was not void. The related validation and reverse validation actions remain stayed during the pendency of the appeal. On November 13, 2023, the California Court of Appeal affirmed the trial court's decision. On December 22, 2023, the City filed a petition for review with the California Supreme Court, which was denied on February 14, 2024.
Cal Am’s Action for Damages Following Termination of Regional Desalination Project (“RDP”)
In 2010, the CPUC had approved the RDP, which was a precursor to the current Water Supply Project and called for the construction of a desalination facility in the City of Marina. The RDP was to be implemented through a Water Purchase Agreement and ancillary agreements (collectively, the “Agreements”) among MCWD, Cal Am and the Monterey County Water Resources Agency (“MCWRA”). In 2011, due to a conflict of interest concerning a former member of MCWRA’s Board of Directors, MCWRA stated that the Agreements were void, and, as a result, Cal Am terminated the Agreements. In ensuing litigation filed by Cal Am in 2012 to resolve the termination of the RDP, the court in 2015 entered a final judgment agreeing with Cal Am’s position that four of the five Agreements are void, and one, the credit line agreement, is not void. As a result of this litigation, Cal Am was permitted to institute further proceedings, discussed below, to determine the amount of damages that may be awarded to Cal Am as a result of the failure of the RDP.
In 2015, Cal Am and MCWRA filed a complaint in San Francisco County Superior Court against MCWD and RMC Water and Environment, a private engineering consulting firm (“RMC”), seeking to recover compensatory, consequential and incidental damages associated with the failure of the RDP, as well as punitive and treble damages, statutory penalties and attorneys’ fees. In 2019, MCWD was granted a motion for summary judgment related to the tort claims in the complaint. A settlement as to the non-tort claims was finalized and entered into in March 2020, in which MCWD and RMC paid Cal Am an aggregate of $5.2 million to resolve Cal Am’s contract claims against MCWD and all claims against RMC relating to the RDP. Under this agreement, Cal Am’s and MCWRA’s right to appeal the dismissal of their tort claims against MCWD were expressly reserved.
In July 2020, Cal Am appealed the grant of summary judgment on MCWD’s tort claims, and in December 2022, the trial court’s decision was reversed with instructions to vacate its prior orders granting MCWD’s motions for summary judgment and to enter new orders denying the motions. In February 2023, MCWD filed a petition for review of the appellate decision with the California Supreme Court, which was denied in March 2023. The trial court’s prior trial date of May 6, 2024, for Cal Am’s remaining tort claims against MCWD, has been vacated, and a new trial date will be set for later in the year.
Proposed Acquisition of Monterey System Assets — MPWMD Condemnation Action
Local Agency Formation Commission Litigation
On February 8, 2024, and February 9, 2024, respectively, Cal Am and LAFCO each filed a notice of appeal with the California Court of Appeals regarding the Monterey County Superior Court’s decision to issue the writ of mandate. The MPWMD filed a notice of cross-appeal on February 15, 2024.
MPWMD Condemnation Action
On February 26, 2024, Cal Am filed a motion requesting the Monterey County Superior Court dismiss the MPWMD’s eminent domain lawsuit seeking to condemn Cal Am’s Monterey system assets. Cal Am’s motion asserts that the MPWMD lacks legal authorization from both the California legislature and LAFCO to become a retail water provider and the lawsuit improperly seeks to effect a taking of property outside the boundaries of the MPWMD’s territory. The motion is scheduled for a hearing on May 3, 2024.
Chattanooga, Tennessee Class Action Litigation
On January 18, 2024, and April 19, 2024, the court heard oral argument on the motions related to the Tennessee Plaintiffs’ motion for an amended class definition. On April 19, 2024, the court provided an oral ruling denying the amended class and incorporating its denial of the original class. A written order will be drafted, and when entered, the Tennessee Plaintiffs will have a right under state law to appeal the denial of class certification.
Mountaineer Gas Company Main Break
On November 17, 2023, the Ruffin plaintiff filed a motion to consolidate the first three lawsuits before a single judge in Kanawha County Circuit Court. The motion was granted orally but no written order has yet been entered.
On March 6, 2024, the motion to transfer the complaint captioned Mountaineer Gas Company v. West Virginia-American Water Company to the West Virginia Business Court was granted and assigned trial and resolution judges. WVAWC’s partial motion to dismiss this lawsuit remains pending.
On February 19, 2024, Mountaineer Gas filed a motion opposing the referral of the four class action complaints and the Mountaineer Gas complaint to the West Virginia Mass Litigation Panel. On March 28, 2024, the Kanawha County Circuit Court trial judge filed a memorandum opposing the referral. The referral motion remains pending with the Chief Justice of the West Virginia Supreme Court.
On December 6, 2023, WVAWC initiated a process whereby Mountaineer Gas customers could file claims with WVAWC and seek payment from WVAWC of up to $2,000 per affected household for the inconvenience arising from a loss of use of their applicances and documented out-of-pocket expenses as a result of the natural gas outage. In light of the diminishing number of new claims being filed, the claims process was concluded on March 8, 2024. As of March 31, 2024, a total of 557 Mountaineer Gas customers completed the claims process, with another 87 claims pending completion, and the completed claimants were paid by WVAWC an average of approximately $1,500 each. In return, these customers were required to execute a partial release of liability in favor of WVAWC.
On March 1, 2024, the staff of the WVPSC issued an initial memorandum in each separate general investigation for Mountaineer Gas and WVAWC. On April 24, 2024, the staff issued a final joint memorandum in the Mountaineer Gas general investigation stating its view that Mountaineer Gas responded appropriately, reasonably and according to Mountaineer Gas’s written procedures. The staff is making no recommendations for improvements to Mountaineer Gas and is recommending that the Mountaineer Gas general investigation be closed. Both general investigations remain pending, and the due date for the staff memorandum in the WVAWC general investigation is July 24, 2024.
PFAS Multi-District Litigation
On February 8, 2024, after a hearing on December 14, 2023, the MDL court issued its final approval of the DuPont settlement. A fairness hearing on the 3M settlement was held on February 2, 2024, and that settlement was approved by the MDL court on March 29, 2024. The Company has begun the process of perfecting its claims under each settlement within the time periods provided by the MDL court. On April 26, 2024, a potential class action settlement involving defendant Tyco Fire Products LP was filed with the MDL court to resolve claims brought in the MDL against this defendant by public water systems. This potential settlement remains subject to preliminary and final approval of the MDL court. The MDL matter remains pending.