The Utility Registrants

The Utility Registrants' electric substations and a portion of their transmission rights are located on property that they own. A significant portion of their electric transmission and distribution facilities are located above or underneath highways, streets, other public places, or property that others own. The Utility Registrants believe that they have satisfactory rights to use those places or property in the form of permits, grants, easements, licenses, and franchise rights; however, they have not necessarily undertaken to examine the underlying title to the land upon which the rights rest.

Transmission and Distribution

The Utility Registrants’ high voltage electric transmission lines owned and in service at December 31, 2022 were as follows:

VoltageCircuit Miles
(Volts)ComEdPECOBGEPepcoDPLACE
765,00090—————
500,000(a)—18821610915—
345,0002,678—————
230,000—550352770472272
138,0002,2571355561586214
115,000——70025——
69,000—177——567662

(a) In addition, PECO, DPL, and ACE have an ownership interest located in Delaware and New Jersey. See Note 8 — Jointly Owned Electric Utility Plant of the Combined Notes to the Consolidated Financial Statements for additional information.

The Utility Registrants' electric distribution system includes the following number of circuit miles of overhead and underground lines:

Circuit MilesComEdPECOBGEPepcoDPLACE
Overhead35,38712,9659,1554,1306,0077,345
Underground32,6849,59017,9277,2076,5133,007

Gas

The following table presents PECO’s, BGE’s, and DPL’s natural gas pipeline miles at December 31, 2022:

PECOBGEDPL
Transmission(a)91528
Distribution6,9907,5272,198
Service piping6,4796,7611,486
Total13,47814,4403,692

(a) DPL has a 10% undivided interest in approximately 8 miles of natural gas transmission mains located in Delaware, which are used by DPL for its natural gas operations and by 90% owner for distribution of natural gas to its electric generating facilities.

The following table presents PECO’s, BGE’s, and DPL’s natural gas facilities:

RegistrantFacilityLocationStorage Capacity (mmcf)Send-out or Peaking Capacity (mmcf/day)
PECOLNG FacilityWest Conshohocken, PA1,200160
PECOPropane Air PlantChester, PA10525
BGELNG FacilityBaltimore, MD1,056332
BGEPropane Air PlantBaltimore, MD55085
DPLLNG FacilityWilmington, DE25025

PECO, BGE, and DPL also own 30, 30, and 10 natural gas city gate stations and direct pipeline customer delivery points at various locations throughout their gas service territory, respectively.

First Mortgage and Insurance

The principal properties of ComEd, PECO, PEPCO, DPL, and ACE are subject to the lien of their respective Mortgages under which their respective First Mortgage Bonds are issued. See Note 16 — Debt and Credit Agreements of the Combined Notes to Consolidated Financial Statements for additional information.

The Utility Registrants maintain property insurance against loss or damage to their properties by fire or other perils, subject to certain exceptions. For their insured losses, the Utility Registrants are self-insured to the extent that any losses are within the policy deductible or exceed the amount of insurance maintained. Any such losses could have a material adverse effect in the consolidated financial condition or results of operations of the Utility Registrants.

Exelon

Security Measures

The Registrants have initiated and work to maintain security measures. On a continuing basis, the Registrants evaluate enhanced security measures at certain critical locations, enhanced response and recovery plans, long-term design changes, and redundancy measures. Additionally, the energy industry has strategic relationships with governmental authorities to ensure that emergency plans are in place and critical infrastructure vulnerabilities are addressed in order to maintain the reliability of the country’s energy systems.