Alliant Energy - As a holding company, Alliant Energy doesn’t directly own any significant properties other than the stock of its subsidiaries. The principal properties of those subsidiaries are as follows:

IPL and WPL

Electric - At December 31, 2016, IPL’s and WPL’s EGUs by primary fuel type were as follows:

IPLExpectedPrimaryNameplateGenerating
Retirement orIn-serviceDispatchCapacityCapacity
Name of EGU and LocationFuel Switch (a)DatesType (b)in MWin MW (c)
Emery Generating Station (Units 1-3); Mason City, IAN/A2004IN603527
M.L. Kapp Generating Station (Unit 2); Clinton, IAN/A1967IN21892
Sutherland Generating Station (Units 1,3); Marshalltown, IARetire by 6/30/17 (d)1955-1961IN11999
Fox Lake Generating Station (Units 1,3); Sherburn, MNRetire by 12/31/171950-1962IN9383
Burlington Combustion Turbines (Units 1-4); Burlington, IARetire by 12/31/171994-1996PK7951
Dubuque Generating Station (Units 3-4); Dubuque, IARetire by 6/30/17 (d)1952-1959IN6659
Grinnell Combustion Turbines (Units 1-2); Grinnell, IARetire by 12/31/171990-1991PK4836
Red Cedar Combustion Turbine (Unit 1); Cedar Rapids, IARetire by 12/31/181996PK2311
Total Gas1,249958
Ottumwa Generating Station (Unit 1); Ottumwa, IA (e)N/A1981BL348326
Lansing Generating Station (Unit 4); Lansing, IAN/A1977BL275235
Prairie Creek Generating Station (Units 1,3,4); Cedar Rapids, IAUnits 1 and 3 - fuel switch or retire by 12/31/25; Unit 4 - fuel switch by 12/31/17 (d)1958-1997BL213147
Burlington Generating Station (Unit 1); Burlington, IAFuel switch by 12/31/21 (d)1968BL212203
George Neal Generating Station (Unit 4); Sioux City, IA (f)N/A1979BL179160
George Neal Generating Station (Unit 3); Sioux City, IA (g)N/A1975BL164131
Louisa Generating Station (Unit 1); Louisa, IA (h)N/A1983BL3229
Total Coal1,4231,231
Marshalltown Combustion Turbines (Units 1-3); Marshalltown, IAFuel switch by 12/31/171978PK189139
Lime Creek Combustion Turbines (Units 1-2); Mason City, IAN/A1991PK9069
Centerville Combustion Turbines (Units 1-2); Centerville, IARetire by 12/31/171990PK5447
Diesel Stations (5 Units); Iowa (i)Retire by 12/31/171963-1966PK10—
Total Oil343255
Whispering Willow - East (121 Units); Franklin Co., IAN/A2009IN20033
Total Wind20033
Total capacity3,2152,477
WPLPrimaryNameplateGenerating
In-serviceDispatchCapacityCapacity
Name of EGU and LocationExpected Retirement (a)DatesType (b)in MWin MW (c)
Riverside Energy Center (Units 1-3); Beloit, WIN/A2004IN675539
Neenah Energy Facility (Units 1-2); Neenah, WIN/A2000PK371283
South Fond du Lac Combustion Turbines (2 Units); Fond du Lac, WI (j)N/A1994PK191146
Rock River Combustion Turbines (Units 3-6); Beloit, WIRetire by 12/31/201967-1972PK169122
Sheepskin Combustion Turbine (Unit 1); Edgerton, WIRetire by 12/31/201971PK4235
Total Gas1,4481,125
Columbia Energy Center (Units 1-2); Portage, WI (k)N/A1975-1978BL514495
Edgewater Generating Station (Unit 5); Sheboygan, WIN/A1985BL414399
Edgewater Generating Station (Unit 4); Sheboygan, WI (l)Retire by 12/31/18 (d)1969BL239191
Total Coal1,1671,085
Bent Tree (122 Units); Freeborn Co., MNN/A2010-2011IN20132
Cedar Ridge (41 Units); Fond du Lac Co., WIN/A2008IN689
Total Wind26941
Prairie du Sac Hydro Plant (8 Units); Prairie due Sac, WIN/A1914-1940IN3212
Kilbourn Hydro Plant (4 Units); Wisconsin Dells, WIN/A1926-1939IN106
Total Hydro4218
Total capacity2,9262,269
(a)Expected dates for the retirement and fuel switching of these EGUs are subject to change depending on operational, regulatory, market and other factors. The potential retirement of other EGUs within the generation fleet continues to be evaluated. IPL and WPL are working with MISO, state regulatory commissions and other regulatory agencies, as required, to determine the final timing of certain of these actions. Final MISO studies could indicate that the retirement of an individual EGU may result in reliability issues and that transmission network upgrades for system reliability are necessary to enable such retirement. Under the current MISO tariff, the specific timing for the retirement of these EGUs could depend on the timing of the required transmission network upgrades as well as various operational, market and other factors.
(b)Base load EGUs (BL) are designed for nearly continuous operation at or near full capacity to provide the system base load. Intermediate EGUs (IN) follow system load changes with frequent starts and curtailments of output during low demand. Peak load EGUs (PK) are generally low efficiency, quick response units that run primarily when there is high demand.
(c)Based on the accredited generating capacity of the EGUs included in MISO’s resource adequacy process for the planning period from June 2016 through May 2017.
(d)Actions and plans for retirement or fuel switch meet requirements specified in IPL’s and WPL’s respective Consent Decree, which are discussed in Note 16(e).
(e)Represents IPL’s 48% ownership interest in this 726 MW (nameplate capacity) / 680 MW (generating capacity) EGU, which is operated by IPL.
(f)Represents IPL’s 25.695% ownership interest in this 696 MW (nameplate capacity) / 622 MW (generating capacity) EGU, which is operated by MidAmerican Energy Company.
(g)Represents IPL’s 28% ownership interest in this 584 MW (nameplate capacity) / 466 MW (generating capacity) EGU, which is operated by MidAmerican Energy Company.
(h)Represents IPL’s 4% ownership interest in this 812 MW (nameplate capacity) / 725 MW (generating capacity) EGU, which is operated by MidAmerican Energy Company.
(i)These EGUs did not receive any accredited generating capacity for the planning period from June 2016 through May 2017.
(j)Represents Units 2 and 3, which WPL owns. WPL also operates, but does not own, South Fond du Lac Combustion Turbines Units 1 and 4.
(k)Represents WPL’s 46.2% ownership interest in this 1,112 MW (nameplate capacity) / 1,072 MW (generating capacity) EGU, which is operated by WPL.
(l)Represents WPL’s 68.2% ownership interest in this 351 MW (nameplate capacity) / 280 MW (generating capacity) EGU, which is operated by WPL.

At December 31, 2016, IPL owned approximately 17,485 miles of overhead electric distribution line and 2,977 miles of underground electric distribution cable, as well as 564 substation distribution transformers, substantially all of which are located in Iowa. At December 31, 2016, WPL owned approximately 16,222 miles of overhead electric distribution line and 5,481 miles of underground electric distribution cable, as well as 302 substation distribution transformers, substantially all of which are located in Wisconsin.

Gas - IPL’s and WPL’s gas properties consist primarily of mains and services, meters, regulating and gate stations and other related transmission and distribution equipment. At December 31, 2016, IPL’s gas distribution facilities included approximately 5,116 miles of gas mains located in Iowa and WPL’s included approximately 4,430 miles of gas mains located in Wisconsin.

Other - IPL’s and WPL’s other property consists primarily of operating and storeroom facilities, vehicles, computer hardware and software, communication equipment and other miscellaneous tools and equipment. IPL’s other property also includes steam service assets. Refer to Note 10(b) for information regarding WPL’s lease of Sheboygan Falls from AEF’s Non-regulated Generation business.

AEF - AEF’s principal properties included in “Property, plant and equipment, net” on Alliant Energy’s balance sheet at December 31, 2016 were as follows:

Non-regulated Generation - Includes Sheboygan Falls, a 347 MW, simple-cycle, natural gas-fired facility near Sheboygan Falls, Wisconsin that was placed in service in 2005 and is leased to WPL, and the 99 MW (60 Units) Franklin County wind farm in Franklin County, Iowa that was placed in service in 2012. Sheboygan Falls and Franklin County wind farm were accredited with 281 MW and 17 MW, respectively, of generating capacity for MISO’s resource adequacy process for the planning period from June 2016 through May 2017.

Transportation - Includes a short-line railway in Iowa with 114 miles of railroad track, 10 active locomotives and 12 rail-cars; and a barge terminal on the Mississippi River.

Corporate Services - Corporate Services’ property included in “Property, plant and equipment, net” on Alliant Energy’s balance sheet at December 31, 2016 consisted primarily of a customer billing and information system for IPL and WPL and other computer software, and the corporate headquarters building located in Madison, Wisconsin.