Item 1A. RISK FACTORS
15K characters. Original on sec.gov ·
Item 1A. RISK FACTORS
NiSource Inc.
In addition to these factors relating to our financing and credit ratings, our partnerships with our data center customers are expected to employ a significant amount of our existing excess transmission infrastructure, which will limit our ability to use these assets for other opportunities, including additional data center opportunities. Furthermore, effectively overseeing the construction and financing of the generation and transmission assets we develop to support our current and any future data center contracts has required and will continue to require significant time and attention of our management, which could detract from their oversight of our existing business and ability to pursue other strategic opportunities.
The return structure and risk profile of our Current Data Center Contracts and any future data center contracts will differ from those of NIPSCO’s traditionally regulated utility operations.
NIPSCO’s and GenCo’s operations under our Current Data Center Contracts will be, and under future data center contracts are expected to be, regulated by the IURC in a different way from the regulatory mechanisms applicable to NIPSCO’s historical operations, which affects the manner in which we recover our investment costs and earn a return on our investment. NIPSCO’s electric utility rates historically have been determined and approved in regulatory proceedings with the IURC based on an analysis of NIPSCO’s costs to provide utility service and a return on, and recovery of, NIPSCO’s investment in the utility business. Through the IURC rate-making process, retail rates may be adjusted over time, and NIPSCO may request additional revenue, in order to cover ongoing costs and investment and earn an adequate return.
In contrast, the terms of our Data Center Contracts were, and the terms of any future contracts with other data center customers are expected to be, determined through commercial negotiations. In the case of our Current Data Center Contracts, these terms include the charges that we receive from our data center customers, which are designed to allow us to recover the costs that we incur to construct and operate the generation and transmission assets we develop to support our current and any future data center contracts and otherwise to secure the capacity needed to serve these customers (including through capacity agreements such as PPAs, ESAs and tolling agreements) and earn a return, and provisions that may result in adjustments to those charges such as, among other factors, those relating to certain liquidated damages that we may owe certain of our data center customers in the event of construction delays or capacity shortfalls and the parties’ responsibility to share or pay for cost overruns, among other provisions. Although the terms of any future data center contracts we enter into may differ in certain respects from the terms of our Current Data Center Contracts, the terms of any future data center contracts (including the charges we receive from customers and any potential adjustments to such charges) will inform our ability to recover our investments and earn a return. These terms of our Current Data Center Contracts do not, and the terms of any future data center contract are not expected to, guarantee a specific overall rate of return, and the overall return we earn under our Current Data Center Contracts or any future data center contracts may ultimately be lower than that of NIPSCO’s traditional utility operations. The IURC has not and will not determine the commercial terms of our Current Data Center Contracts or any future data center contracts; however, the IURC is expected to maintain oversight under our Current Data Center Contracts and any future data center contracts to ensure NIPSCO provides reliable service to our data center customers and any future data center customers at just and reasonable rates. In order to recover our investment costs and earn our return under our Current Data Center Contracts and any future data center contracts, our subsidiaries must efficiently perform their own obligations and must look to our existing and any future data center customers (or, if applicable, any parent guarantor) to perform their obligations, rather than the IURC making use of its traditional rate-making process. In addition, under our Current Data Center Contracts, NIPSCO has direct contractual obligations to its data center customers to, among other things, construct certain generation and transmission assets to support our current data center customers and deliver committed electric capacity in fixed amounts by certain dates. We expect our subsidiaries to have comparable contractual obligations to customers in connection with any future data center contracts. If disputes arise with data center customers regarding provisions of a data center contract or payments to be made or actions to be taken thereunder, we may be significantly disadvantaged as a result of, among other factors, the significance of such contracts to us and the greater resources (financial and otherwise) available to the relevant customer. Any dispute or litigation with a data center customer could create significant demands on the attention of management and result in significant costs to us.
In addition, the IURC, through its review and approval of our Current Data Center Contracts and any future data center contracts, and the related PPAs between NIPSCO and GenCo, will have ultimate authority over the implementation of these agreements. In this context, we will need to continuously assess the applicability of ASC Topic 980 over the life of our Current Data Center Contracts and future data center contracts. It is possible that significant construction overruns, capacity shortfalls or other events that could result in NIPSCO or GenCo owing liquidated damages under our Current Data Center Contracts or any future data center contract could either preclude ongoing application of ASC Topic 980 or result in an immediate disallowance and impairment of the applicable generation and transmission assets we have developed to support the applicable data center contracts. In addition, early termination of a Data Center Contract or any future data center contract, as applicable, could result in such impairment and discontinuation of application of ASC Topic 980 with respect to the assets being constructed to serve the applicable data center contract, unless such assets can be used to support new or existing customers. If we incur significant costs that we are not able to recover from our current or any future data center customers (for example, greater than expected purchases of market capacity or operations and maintenance costs significantly exceeding those contemplated by an applicable
ITEM 1A. RISK FACTORS
NiSource Inc.
current or future data center contract), this also could discontinue the application of ASC Topic 980 to the applicable data center contract and related generation and transmission assets.
Our partnerships with our data center customers expose us to significant customer and industry concentration risk.
Our three existing data center customers will be significant customers of our electric utility operations. For example, at full ramp (expected in 2032), we expect to employ approximately 4,920MW of capacity (representing the generation resources we plan to construct, combined with contracted capacity) to serve our existing data center customers. By comparison, as of December 31, 2025, we owned generating resources representing approximately 3,967 MW of capacity and had PPAs providing for approximately 1,200 MW of capacity.
Although we anticipate expanding our base of data center customers, we expect the total number of data center customers we serve to remain relatively small by comparison to our current customer base. The concentration of business with a small number of customers in a single industry based on emerging technologies, including artificial intelligence and machine learning, presents several risks for us. Our data center customers’ technologies and their related business applications have developed rapidly in recent years and continue to develop. In addition, our customers’ data center and cloud computing businesses may themselves serve concentrated customers, such as “frontier” artificial intelligence companies, which may have developing and uncertain business models. We cannot predict the rate at which or the extent to which these emerging technologies will be broadly adopted or successful as business models. It is possible our customers will reduce their investment in these new technologies or abandon them entirely. Many factors, including those outside our and our customers’ control, could contribute to such a decision, including, for example: (i) any decrease or lessening of current cloud-computing or artificial intelligence demand trends, (ii) reports of significant financial or business difficulties at a “frontier” artificial intelligence company, (iii) adverse legal or regulatory developments (in Northern Indiana or elsewhere) with respect to data centers, cloud-computing or artificial intelligence, which could result, for example, from concerns with respect to the safety of artificial intelligence (which have led to recent statements and proposals from U.S. federal lawmakers calling for federal oversight and pauses in development of artificial intelligence models), environmental concerns (such as those relating to the sourcing of natural gas to power data centers or supplying water from local resources to cool data centers), or other factors, and which could negatively impact the demand for data centers, and (iv) any business downturns or weakening financial condition that our data center customers may experience (whether or not resulting from the foregoing factors). In addition, even if our data center customers do not decide to reduce or abandon their investments in data center technologies, it is possible they may seek to reduce or end their relationship with us. This could occur if, among other potential causes: (i) we experience construction delays, cost overruns or capacity shortfalls in connection with our construction of the generation and transmission assets we plan to construct to serve our data center customers, (ii) our data center customers encounter similar problems connection with constructing their data centers that we will serve, (iii) technological or other advances relating to the design and operation of data centers reduce the amount of electricity needed to power data centers (which reduction could be significant) or (iv) competing energy technologies that we are not able to offer become a preferred source of energy for powering data centers.
If, for any reason, one or more of our customers decide to reduce their investments in data centers generally or to reduce or end their relationship with us, it is possible such customer(s) could default under its contract with us. Our Current Data Center Contracts contain protections in the event of a customer default, including required termination payments designed to reimburse us for our costs related to the applicable data center contract and provide a return. However, it is possible disputes may arise in connection with termination payments. For example, a data center customer may dispute the existence of a customer default or the amount of a termination payment, or may assert that we are in default, among other tactics. If this were to occur, we may be significantly disadvantaged as a result of, among other factors, the significance of the applicable data center contract to us and the greater resources (financial and otherwise) available to the relevant customer.
In addition, ADS has the right to terminate the ADS Contract for convenience following certain notice periods and has a one-time option (exercisable no later than March 31, 2029) to reduce committed capacity under the ADS Contract by 1,200 MW commencing January 31, 2032. If ADS elects to terminate the ADS Contract during its initial term or reduce the committed capacity under the ADS Contract, we may not receive the full earnings we expect to receive over the life of the ADS Contract. Although the ADS Contract provides for reimbursement for our investment in the Contract Assets and related expenses in the event of a reduction in the committed capacity or early termination, the amount of any reimbursement is capped under the ADS Contract, with the amount of the caps being based on cost estimates determined as of signing. Furthermore, our ability to collect any reimbursable amounts will depend upon the willingness and ability of ADS or its parent guarantor to satisfy their payment obligations under the ADS Contract and related guarantee. Accordingly, we may not be able to recover our full investment, which may adversely affect our future results and financial condition.
Any future data center contracts our subsidiaries enter into may contain termination and/or capacity reduction provisions (which we expect would be accompanied by related reimbursement provisions), which would expose us to risks comparable to those described above.
ITEM 1A. RISK FACTORS
NiSource Inc.
If any of our data center customers defaults under, terminates or reduces capacity under its data center contract, we may not be able to replace such customer’s demand or otherwise fully utilize the assets constructed in connection with the such contract. We also may not receive the same level of return with respect to any alternative use of the assets we have constructed or contracted for to serve such customers. Any of such could adversely affect our future results, financial conditions and results of operations (the significance of which effect will be affected by the relative size of such contract and the costs we have incurred to develop resources supporting such contract).
In addition, as a result of our Current Data Center Contracts, and any further agreements we may sign with data center companies, our stock price may experience increased volatility as a result of factors outside our control. For example, our stock price may be negatively affected as a result of any actual or perceived slowdown in the adoption of artificial intelligence technology, the regulation or proposed regulation of such technology, or actual or perceived changes in the strategic or financial position of our data center customers, or “frontier” artificial intelligence companies more generally. The trading prices for shares of stock in a number of U.S. public companies operating or serving data centers have recently experienced significant volatility.
ITEM 2. UNREGISTERED SALES OF EQUITY SECURITIES AND USE OF PROCEEDS
None.
ITEM 3. DEFAULTS UPON SENIOR SECURITIES
None.
ITEM 4. MINE SAFETY DISCLOSURES
Not applicable.
Previous: Item 4. CONTROLS AND PROCEDURES · Next: Item 5. OTHER INFORMATION