Item 3. LEGAL PROCEEDINGS

3K characters. Original on sec.gov · Markdown

Item 3. LEGAL PROCEEDINGS

The following should be read in conjunction with Note 24, Commitments and Contingencies, and Note 26, Regulatory Environment, in this report for additional information on material legal proceedings and matters related to us and our subsidiaries.

In addition to those legal proceedings discussed in Note 24, Commitments and Contingencies, Note 26, Regulatory Environment, and below, we are currently, and from time to time, subject to claims and suits arising in the ordinary course of business. Although the

2020 Form 10-K36WEC Energy Group, Inc.

Table of Contents

results of these additional legal proceedings cannot be predicted with certainty, management believes, after consultation with legal counsel, that the ultimate resolution of these proceedings will not have a material effect on our financial statements.

Environmental Matters

Manlove Field Matter

In September 2017, the IDNR, Office of Oil and Gas Resource Management, issued a VN to PGL related to a leak of natural gas from a well located at the PGL Manlove Gas Storage Field in December 2016. PGL quickly shut down and permanently plugged the well to contain the leak after it was discovered. The leak resulted in the migration of natural gas from the well to the Mahomet Aquifer located in central Illinois and impacted residential freshwater wells. PGL has been working with residents potentially impacted by the natural gas leak, and the Illinois state agencies to investigate and remediate the impacts of the natural gas leak to the Mahomet Aquifer. In October 2017, the Illinois AG filed a complaint against PGL alleging certain violations of the Illinois Environmental Protection Act and the Oil and Gas Act. PGL entered into an Agreed Interim Order with the State of Illinois in October 2017 and a First Amended Agreed Interim Order in September 2019 whereby PGL agreed, among other things, to continue actions it was already undertaking proactively, including the submittal of a GMZ application to the IEPA in August 2019. A supplemental filing was sent to the IEPA in December 2019. Proposed modifications to the GMZ application were submitted to the Illinois AG and the IEPA in May 2020. In September 2020, the IEPA sent PGL a letter conditionally approving the GMZ application.

In addition, in December 2017, the IEPA issued a VN to PGL alleging the same violations as the AG. Lastly, in January 2018, the IEPA issued a VN alleging certain violations of Illinois air emission rules arising from the construction and operation of flaring equipment at the leak site. Both of the IEPA VN matters have been referred to the AG for enforcement.

In the complaint, as is customary in these types of actions, the AG cited to the statutory penalties allowed by law. Ultimately, the pursuit of any civil penalties is at the AG’s discretion. In the event the AG pursues penalties in connection with a final order, we believe that PGL's high level of cooperation and quick action to remedy the situation and to work with the potentially impacted homeowners would be taken into account. At this time, we believe that civil penalties, if any, will not have a material impact on our financial statements.

Previous: Item 2. PROPERTIES · Next: Item 4. MINE SAFETY DISCLOSURES