Alliant Energy (LNT) 10-K risk factor changes: FY2014 vs FY2013
The 2014-12-31 10-K against the 2013-12-31 one, compared heading by heading and sentence by sentence. One of these filings carries no fiscal year tag, so its year is the calendar year of the period end.
Item 1A48 rewritten24 added11 removed132 unchanged
All filing items2,813 rewritten1,029 added1,237 removed2,185 unchanged
Summary
counted, not written
- Item 1A headings could not be compared: only 0 carried over between the two years, which usually means one filing was read wrongly, so none is reported as new or removed.
- Sentence by sentence, 1,029 added, 1,237 removed, 2,813 rewritten and 2,185 unchanged across 17 items that differ.
Sentences by item
21 items, with every count and a link to each item that changed
Underlined words on a shaded ground are new in FY2014; struck-through words were in FY2013. Sentences that are wholly new or wholly gone are labelled rather than marked.
Item 1A. RISK FACTORS
48 rewritten, 24 added, 11 removed, 132 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Our business is significantly impacted by government regulation and legislation [removed: -] [added: \-] We are subject to extensive regulation by federal and state regulatory authorities, which significantly influences our operations and our ability to timely recover costs from customers and earn appropriate rates of return.
Our operations are also governed by organizations such as the North American Electric Reliability Corporation, the Pipeline and Hazardous Materials Safety Administration, and the Midcontinent Independent System Operator, Inc. Operations impacted by these regulatory groups include: the rates charged to our customers; [added: rates of return of IPL, WPL and ATC;] our ability to site and construct new generating facilities, such as the natural [removed: gas] [added: gas-fired] generating [removed: facility] [added: facilities] in Marshalltown, [removed: Iowa, any potential new generation investment in] [added: Iowa and Beloit,] Wisconsin, and future wind projects to utilize our remaining available wind sites, and the amount of costs associated therewith that may be recovered from customers; the installation of environmental emission controls equipment and the amount of costs for the construction and maintenance of such equipment that may be recovered from customers; our ability to decommission generating facilities and recover the costs incurred to decommission the facilities and the remaining carrying value of such facilities; [added: our ability to site and construct new natural gas pipelines; our ability to recover costs to upgrade our natural gas distribution system to comply with] the [added: anticipated Pipeline and Hazardous Materials Safety Administration requirements that have not yet been finalized; the] amount of certain sources of energy we must use, such as renewable sources and reductions in energy usage by customers; our ability to purchase generating facilities and the amount of costs associated therewith that may be recovered from customers; [added: our ability to sell utility assets and any conditions placed upon] the [added: sale of such assets, such as the sale of our Minnesota gas and electric distribution assets; the] rates paid to transmission operators and the amount of those costs, and how those costs are recovered from customers; our ability to enter into purchased power agreements, [removed: such as] the [removed: purchased power agreement entered into with NextEra Energy, Inc., the] amount of costs associated therewith, and how those costs are recovered from customers; [added: resource adequacy requirements,] energy capacity [removed: standards and] [added: standards,] what forms of energy are considered when determining whether we meet those [removed: standards;] [added: standards, and when new facilities such as IPL’s Marshalltown Generating Station and WPL’s proposed Riverside Energy Center expansion may be fully credited with energy capacity;] the allocation of expenditures by transmission companies on transmission network upgrades and our ability to recover costs associated therewith from customers; reliability; safety; the issuance of securities; accounting matters; and transactions between affiliates.
While we believe we comply in all material respects with applicable laws and regulations governing us, state or federal agencies may not agree and may find that we violated a law or [added: regulation.]
In future rate cases, IPL and WPL may not receive an adequate amount of rate [removed: relief,] [added: relief to recover all costs and earn their authorized] rates [added: of return, rates] may be reduced, rate refunds may be required, rate adjustments may not be approved on a timely basis, costs may not be otherwise recovered through rates, future rates may be temporarily frozen (as is the case for [added: IPL’s and] WPL’s retail electric [removed: and gas] base rates through [removed: 2014)] [added: the end of 2016)] and authorized rates of return on capital may be reduced.
Large construction projects are subject to delays and cost increases that may not be recovered from customers - Our strategic plan includes [added: constructing natural gas-fired generating facilities,] installing environmental control equipment at our newer and more efficient coal-fired generating facilities, [added: and] making other large-scale improvements to such generating [removed: facilities,] [added: facilities] and [removed: the construction of] [added: large-scale additions and upgrades to our] natural [removed: gas-fired generating facilities.][added: gas distribution system.]
[removed: If] [added: We may not be able to recover all costs for the projects in rates and face increased risk of potential impairment of our project investment if] a construction project is not completed or is delayed, or final costs exceed the costs approved by our regulators, for example, if the Marshalltown Generating Station exceeds the cost cap approved by the [removed: IUB, we may not be able to recover all costs for the project in rates and face increased risk of potential impairment of our investment in the project.][added: IUB.]
We are also subject to a Consent Decree between WPL, the EPA and the Sierra Club, which resolved environmental claims related to [removed: WPL’s] [added: air emissions at certain WPL coal-fired] generating facilities.
The [removed: regulations] [added: environmental laws] and [removed: the Consent Decree] [added: regulations] govern air emissions, [added: ambient air quality standards,] water quality, cooling water intake structures, wastewater discharges, the generation, transport and disposal of coal combustion [removed: products] [added: residuals] and other solid wastes and hazardous substances, [removed: and the] clean-up of contaminated [removed: sites.][added: sites and protection of natural resources.]
Environmental [removed: laws, regulations] [added: laws] and [removed: the Consent Decree] [added: regulations] can also require us to restrict or limit the output of certain facilities or the use of certain fuels, to install emission controls equipment at our facilities, clean up spills and correct environmental hazards and other contamination.
Compliance with these regulations can significantly increase capital spending, operating [removed: costs,] [added: costs] and plant [removed: down-times] [added: down-times,] and can negatively affect the affordability of rates we charge our customers.
We cannot predict with certainty the amount and timing of all future expenditures (including the potential or magnitude of any fines or penalties, including the severity of any restriction on our operations) necessary to comply with, or as a result of liabilities under, these environmental [removed: laws, regulations,] [added: laws] and [removed: the Consent Decree,] [added: regulations,] although we expect the expenditures to be material.
Although we believe we comply in all material respects with currently applicable environmental laws, regulations, and the Consent Decree, we may [removed: receive notices of violation from] [added: be subject to regulatory enforcement action by] state or federal [removed: agencies.][added: agencies should we operate out of compliance.]
[removed: Citizen] [added: In addition, citizen] groups [removed: or] [added: and] private individuals [removed: that feel environmental regulations are not being sufficiently enforced by regulatory agencies] may bring legal action against [removed: those] regulatory agencies or bring citizen enforcement actions against [removed: us.][added: us claiming that the environmental requirements are not being sufficiently enforced by regulatory agencies.]
If we are unsuccessful defending or settling [added: such] litigation [removed: from] [added: by] governmental [removed: agencies or] [added: agencies,] citizen groups, [added: or individuals,] we could be subject to restrictions or prohibitions on operating our generation facilities, costly upgrades to our generating facilities, payment of damages or fines, requirements to complete other beneficial environmental projects, and litigation costs, all of which could be material.
We are subject to existing and potential future governmental mandates to provide customers with [removed: clean energy,] renewable energy and energy conservation offerings.
Existing environmental laws or regulations may be revised and new laws or regulations seeking to protect the environment [added: and natural resources] may be adopted or become applicable to us.
These revised and new laws or regulations [added: and any areas in our service territories designated as non-attainment] may [removed: include] [added: require] regulation of mercury, nitrogen oxide, sulfur dioxide, carbon dioxide (CO2) and other greenhouse gases (GHG) emissions, particulates, coal ash and other coal combustion products, [removed: and] [added: wastewater discharges,] cooling water intake [removed: structures.][added: structures, and threatened, endangered or invasive species.]
Our strategic plan was developed in part to comply with [removed: certain] expected environmental laws and regulations as we anticipate they will be finally adopted.
Revision of existing environmental laws or regulations may cause: (1) state utility commissions to not approve our plans to install environmental emission controls equipment at our existing generating facilities or not allow us to recover costs of such projects; (2) state utility commissions to not approve costs of emission allowances purchased to comply with environmental regulations that are no longer applicable to our operations; (3) co-owners in our jointly-owned facilities to not agree with our decision to move forward with these projects; or (4) our current plans [removed: do] [added: and/or past actions to] not meet new requirements.
[removed: The] [added: In January 2014, the] EPA [removed: has issued] [added: published] proposed regulations governing GHG emissions from new generating facilities, which would impact [removed: the] [added: IPL’s] Marshalltown Generating Station [added: in Iowa] and [removed: any new generation investment] [added: WPL’s proposed Riverside Energy Center expansion] in Wisconsin.
Due to the uncertainty of [removed: what] [added: the final] form [removed: CO2] [added: of the GHG] emissions regulations [removed: regarding our existing generating facilities could take] and [removed: control technologies] [added: solutions, including] available [added: control technologies,] to [added: comply with regulations to] reduce GHG emissions, including CO2, we cannot provide any assurance regarding the potential impacts [removed: any] [added: such] future regulations would have on our operations.
[removed: Technology] [added: Continuing technology] improvements and regulatory developments are making [removed: distributed] [added: customer- and third party-owned] generation [added: technologies such as rooftop solar systems, wind turbines, microturbines and battery storage systems more cost effective and] feasible for more of our customers.
As more customers utilize [removed: distributed] [added: their own] generation, demand for energy from us may decline.
Adverse economic conditions in our service territories [removed: reduce] [added: can adversely affect] the [added: financial condition of our customers and reduce their] demand for electricity and natural gas.
Physical attacks on transmission and distribution [removed: facilities, including a substation in San Jose, California and substation and transmission] facilities [removed: in Arkansas,] [added: that] appeared to be terrorist-style [removed: attacks.][added: attacks have occurred in the recent past.]
In addition, in the ordinary course of business, we collect and retain sensitive information including personal information about our [removed: customers] [added: customers, shareowners] and employees.
Any theft, loss [removed: and or/fraudulent] [added: and/or fraudulent] use of customer, shareowner, employee or proprietary data as a result of a cyber attack could subject us to significant litigation, liability and costs, as well as adversely impact our reputation with customers and regulators, among others.
We have instituted [added: certain] safeguards to protect our operational systems and information technology assets.
[removed: If the technology systems were to fail or be breached] by a cyber attack or a computer virus, and not be recovered in a timely fashion, we may be unable to fulfill critical business functions and confidential data could be compromised, adversely impacting our financial condition and results of operation.
Further, we currently rely on coal primarily from the Powder River Basin in Wyoming and any disruption of coal production in, or transportation from, that region may cause us to incur additional [added: costs which may not be fully recovered through rates.]
[removed: Further, any disruption of production or transportation of natural gas, such as the recent pipeline explosion in Manitoba, Canada,] [added: Price increases] may cause us to incur additional costs to purchase natural gas, which may not be fully recovered through rates and may adversely impact our financial condition and results of operations.
Changes are occurring in the transmission [removed: network] [added: network,] which are required to, among other things, accommodate renewable energy and the decommissioning of older coal-fired generating facilities.
We may [added: not] be [removed: unable] [added: able] to fully pass on the increases in such transmission costs to our [removed: customers, especially at WPL where we do not have a retail automatic transmission rider.][added: customers.]
We have forecasted capital expenditures of approximately [removed: $3.6] [added: $4.2] billion over the next four years.
Disruptions could be caused by Federal Reserve policies and [removed: actions including tapering of its quantitative easing program,] [added: actions,] U.S. debt management concerns, U.S. debt limit and budget debates including government shutdowns, European sovereign debt concerns, [added: currency concerns,] economic downturn or uncertainty, monetary policies, a negative view of the utility industry or our company, failures of financial institutions or other factors.
We are also subject to collective bargaining agreements with approximately [removed: 2,300] [added: 2,400] employees.
Any work stoppage experienced in connections with negotiations of collective bargaining agreements could adversely affect our financial condition and [added: results of operations as well as] our ability to implement our strategic plan.
We face risks associated with operating electric and natural gas infrastructure - The operation of electric generating facilities involves many risks, including start-up risks, breakdown or failure of equipment, [added: failure of generating facilities including wind turbines,] the dependence on a specific fuel source, including the supply and transportation of fuel, the risk of performance below expected or contracted levels of output [added: or efficiency, operator error and compliance with mandatory reliability standards.]
The operation of our energy delivery infrastructure involves many risks including breakdown or failure of equipment and [removed: forest or prairie] fires developing from [removed: vegetation around] our power lines.
We also have obligations to provide [removed: electrical] [added: electric] service under regulatory requirements and contractual commitments.
State and federal election results may serve as a catalyst for regulatory changes.
We may lose wholesale customers such as Jo-Carroll Energy, Inc., WPPI Energy and Great Lakes Utilities who have provided us notice of their intent to terminate their wholesale power supply agreements.
The Consent Decree requires construction of specific emission controls equipment, establishes emission rate limits, requires retirement or fuel switching of certain facilities, and requires WPL to complete certain environmental mitigation projects.
In some instances, complying with certain environmental regulations may not be sufficient to satisfy the obligations of the Consent Decree or other operating regulations discussed earlier.
In addition, we may also be subject to third party environmental claims relating to property damage or personal injury that arise from our operations.
Areas in our service territories that are currently attainment areas under National Ambient Air Quality Standards could be designated as non-attainment areas due to new air monitoring results.
Federal and state election results may serve as a catalyst for regulatory changes.
In 2013, a series of actions were announced to reduce carbon emissions, prepare the U.S. for the impacts of climate change, and lead international efforts to address global climate change.
In November 2014, future targets for GHG emission reductions for the U.S. were announced in anticipation of achieving a global climate agreement.
The following are some proposed regulations that are expected to impact our operations.
In June 2014, the EPA issued its Clean Air Act Section 111(d) proposal to reduce CO2 emissions from existing fossil-fueled generating facilities.
The EPA’s proposal is based on broad measures to lower CO2 emissions, which could impact the dispatch of existing fossil-fueled generating facilities and the fuel mix used to generate electricity, and require other actions in order to achieve CO2 emission reduction goals.
If the technology systems were to fail or be breached
In some cases, we outsource administration of certain functions to vendors that could be targets of cyber attacks.
For example, we outsource administration of our employee health insurance to Anthem.
Anthem was recently the target of a cyber attack.
Our strategic plan includes increasing our reliance on natural-gas fired electric generating facilities, particularly the new facilities planned in Marshalltown, Iowa and the Riverside Energy Center expansion in Beloit, Wisconsin, and coal-fired facilities expected to switch from coal to natural gas as the primary fuel type, such as IPL’s M.L. Kapp facility.
Natural gas prices may increase due to disruption of production or transportation of natural gas, such as the pipeline explosion in Manitoba, Canada in January 2014, or regulatory developments that increase the cost of natural gas extraction methods, including fracking.
Increased utilization of customer- and third party-owned generation technologies could disrupt the reliability and balance of the electricity grid.
We face risks associated with deployment and integration of a new customer billing and information system - We are implementing a new customer billing and information system for IPL and WPL, which is currently expected to be deployed in 2015.
This new customer billing and information system will house all customer records and process metering, billing, payment, and on-line transactions.
Implementing a new customer system is complex, costly and time consuming.
If we do not successfully implement the system and new related processes, or if it does not operate as intended, it could result in substantial disruptions to our business, including customer billings and collections, which could have a material adverse effect on our financial condition and results of operations.
Changes in technology could also alter the channels through which electric customers buy or utilize power, which could reduce the revenues or increase the expenses of our utility companies.
regulation.
We may be subject to litigation over environmental issues, including claims for property damage or personal injury, or suits by citizen groups alleging violations of environmental requirements.
In particular, President Obama and his administration have affirmed that the regulation of GHG emissions continues to be a top priority.
The EPA is also expected to propose regulations in 2014 governing GHG emissions from existing generating facilities, which potentially could impact all of our generating facilities.
We may also lose wholesale customers to competitors.
We lost certain customers after plants closed due to the 2009 recession.
costs which may not be fully recovered through rates.
Our contract with one collective bargaining unit representing over 1,000 of our employees is due to expire in May 2014.
or efficiency, operator error and compliance with mandatory reliability standards.
Pursuant to the terms of that sale, we may face unfavorable post-closing adjustments that could be material.
If we do not receive adequate dividends and distributions from
An excerpt. Shown here: 40 of 48 rewritten, all 24 added and all 11 removed. The counts are complete. For every sentence, read Item 1A. RISK FACTORS in the FY2014 filing and the FY2013 filing.
Item 7. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
673 rewritten, 388 added, 484 removed, 363 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
The following discussion and analysis should be read in conjunction with the [removed: Consolidated] Financial Statements and [removed: Combined] Notes [removed: to Consolidated Financial Statements] included in this report.
| • | [Executive [removed: Summary](#sDE1CF235278FB89AD754F8B9D2563DE3)] [added: Summary](#sD7EB98B62CCBC7F32A2D6ABA516E50DB)] |
| • | [Strategic [removed: Overview](#s2C54611047F2696E7B5FF8B9C951ACE9)] [added: Overview](#s06C4F7DE4D3FFCA8A1BD6ABA7ACD6C39)] |
| • | [Rate [removed: Matters](#sAC09DDB84E9D4F9EC770F8B9CFB3A73E)] [added: Matters](#sD5006DB81447ADFCF1446ABA4FA8C350)] |
| • | [Environmental [removed: Matters](#s1F3659F1320C40F5693BF8B9DFF825D9)] [added: Matters](#sB59F5FC8BEF9DB683F956ABA7B22EDF5)] |
| • | [Legislative [removed: Matters](#s86CEDAF82D88F5857127F8B9E0193EF7)] [added: Matters](#s27D9D5872E31E6911B326ABA7B43B0C2)] |
| • | [Alliant Energy’s Results of [removed: Operations](#s6E72AFA4BFBD6ABD126DF8B9CA2B5522)] [added: Operations](#s6E35C038326B990186856ABA5033D4B3)] |
| • | [IPL’s Results of [removed: Operations](#s5FF8C440E4B4753BC29CF8B9C9B0B466)] [added: Operations](#s718964D057811BAEF8E46ABA4EFF2CDB)] |
| • | [WPL’s Results of [removed: Operations](#s17F48D4E56963EC5DF93F8B9C9E51FC7)] [added: Operations](#s109645F7393F827B840A6ABA4F826955)] |
| • | [Liquidity and Capital [removed: Resources](#s347182CA2CD1EEDAF167F8B9CA32EBB3)] [added: Resources](#sC406469B25A3650B9C066ABA501F1587)] |
| • | [Other [removed: Matters](#sE78B28F776F52BC6B5D4F8B9E12D5B00)] [added: Matters](#s04D0812DC404F3254EE16ABA7C44723C)] |
| • | [Market Risk Sensitive Instruments and [removed: Positions](#sA02ED73A59C9955B68F3F8B9E134FE5D)] [added: Positions](#sD74E79C523565D5D95EA6ABA7C4B5BCF)] |
| • | [Critical Accounting Policies and [removed: Estimates](#s17BD8D4E550B5F20ACC6F8B9D1FC1116)] [added: Estimates](#s73A57CEFC8C2F23E47206ABA6D9EE507)] |
| • | [Other Future [removed: Considerations](#s7F8D069BA2FDF5911C76F8B9C9E026A7)] [added: Considerations](#s2DB6159B9E91221797116ABA7C8E9DD7)] |
IPL is a public utility engaged principally in the generation and distribution of electricity and the distribution and transportation of natural gas in [removed: selective] [added: select] markets in Iowa and southern Minnesota.
WPL is a public utility engaged principally in the generation and distribution of electricity and the distribution and transportation of natural gas in [removed: selective] [added: select] markets in southern and central Wisconsin.
At December 31, [removed: 2013, WPL,] [added: 2014, WPL and Resources,] through [removed: its] [added: their] ownership [removed: interest] [added: interests] in WPL Transco, [added: in aggregate] held an approximate 16% [added: ownership] interest in ATC, a transmission-only utility operating [added: primarily] in the Midwest.
An illustration of Alliant Energy’s primary businesses [removed: as of December 31, 2013] is shown below.
| [removed: Utility] [added: Utilities] and Corporate Services | | | | Non-regulated and Parent | |
| \- 16% interest in ATC [removed: (WPL)] [added: (primarily WPL)] | | | | \- Parent Company | |
| (a) | In September 2013, IPL signed definitive agreements to sell its Minnesota electric and natural gas distribution assets. Refer to [Note [removed: 3(a)](#s7699adb581a54c8e952936c5043d527a) of the “Combined Notes to Consolidated Financial Statements”] [added: 3](#sAA2499D9F431FDD1F46A6ABA34CF93A1)] for further discussion of these [removed: proposed] [added: anticipated] sales. |
[removed: Utility] [added: Utilities] and Corporate Services \- IPL and WPL own a portfolio of EGUs located in Iowa, Wisconsin and Minnesota with a diversified fuel mix including coal, natural gas and renewable resources.
The utility business also procures natural gas from various suppliers to provide service to approximately [removed: 418,000] [added: 420,000] retail gas customers in the upper Midwest.
The earnings and cash flows from the [removed: utility] [added: utilities] and Corporate Services business are sensitive to various external factors including, but not limited to, the amount and timing of rates approved by regulatory authorities, the impact of weather and economic conditions on electric and gas sales volumes and other factors listed in “[Risk [removed: Factors](#s1B47635654DED2B3FB1EF8B9DD2AAEC9)”] [added: Factors](#s11D4876801DEF982224C6ABA785572C6)”] in Item 1A and “[Forward-looking [removed: Statements](#sF07B5BA59A40359BC34CF8B9D9C84E97).”][added: Statements](#sCE18FD98D940A0986B086ABA74F3A70F).”]
Financial Results - Details regarding Alliant Energy’s net income and EPS attributable to Alliant Energy common shareowners [removed: for 2013 and 2012] were as follows (dollars in millions, except per share amount):
| | 2013 | | [added: 2012] | | [added: 2011] | | [added: 2013] | | 2012 | | [added: 2011] | | [added: 2013] | | [added: 2012] | [added: | 2011 |]
| Utilities and Corporate Services | | [removed: $356.5] [added: $373.3] | | | | [removed: $3.22] [added: $3.37] | | | | [removed: $304.8] [added: $356.5] | | | | [removed: $2.75] [added: $3.22] | |
| Non-regulated and [removed: parent] [added: Parent] | [removed: 7.7] [added: 12.2] | | | | [removed: 0.07] [added: 0.11] | | | | [removed: 20.1] [added: 7.7] | | | | [removed: 0.18] [added: 0.07] | | |
| Income from continuing operations | [removed: 364.2] [added: 385.5] | | | | [removed: 3.29] [added: 3.48] | | | | [removed: 324.9] [added: 364.2] | | | | [removed: 2.93] [added: 3.29] | | |
| Loss from discontinued operations | [removed: (5.9] [added: (2.4] | | ) | | [removed: (0.06] [added: (0.02] | | ) | | [removed: (5.1] [added: (5.9] | | ) | | [removed: (0.04] [added: (0.06] | | ) |
| Net income | | [removed: $358.3] [added: $383.1] | | | | [removed: $3.23] [added: $3.46] | | | | [removed: $319.8] [added: $358.3] | | | | [removed: $2.89] [added: $3.23] | |
Alliant Energy believes utilities and Corporate Services, and non-regulated and parent EPS from continuing operations are useful to investors because they facilitate an understanding of segment performance and trends and provide additional information about Alliant Energy’s operations on a basis consistent with the [added: measures that management uses to manage its operations and evaluate its performance.]
Utilities and Corporate Services - Higher EPS from continuing operations in [removed: 2013] [added: 2014] compared to [removed: 2012] [added: 2013] was primarily due to:
| • | [removed: $0.32] [added: $0.70] per share of [added: lower] purchased electric capacity expense related to the [removed: Riverside] [added: previous DAEC] PPA recorded in [removed: 2012;] [added: 2014 compared to 2013;] |
| • | [removed: $0.13] [added: $0.05] per share from [added: changes in] the revenue requirement adjustment related to certain IPL tax benefits in [added: 2014 compared to] 2013; |
| • | an estimated [removed: $0.13] [added: $0.08] per share of [removed: higher weather-normalized retail] [added: net decreases in revenues from lower] electric and gas sales in [removed: 2013] [added: 2014] compared to [removed: 2012;] [added: 2013 due to weather conditions;] |
| • | $0.11 per share of [removed: lower] [added: higher] energy [removed: conservation] [added: efficiency] cost recovery amortizations at WPL in [removed: 2013] [added: 2014] compared to [removed: 2012;] [added: 2013;] |
| • | $0.06 per share of lower income tax expense at IPL in [removed: 2013] [added: 2014] compared to [removed: 2012] [added: 2013] due to Iowa rate-making practices; and |
| • | [removed: $0.17] [added: $0.08] per share of higher depreciation expense in [removed: 2013] [added: 2014] compared to [removed: 2012, primarily due to WPL’s acquisition of Riverside in December 2012;] [added: 2013;] |
| • | [removed: $0.09] [added: $0.08] per share of higher [removed: generation] [added: generation, distribution and customer service] operation and maintenances expenses in [removed: 2013] [added: 2014] compared to [removed: 2012;] [added: 2013;] |
| • | [New Accounting Pronouncements](#saef3af7a7a3a402d967cb506cb3de33b) |
| | 2014 | | | | | | | | 2013 | | | | | | |
| • | $0.33 per share of purchased electric capacity expense related to the Kewaunee PPA that expired in 2013; |
| • | $0.39 per share of retail electric customer billing credits at IPL in 2014 related to an approved settlement agreement for its Iowa retail electric base rates; |
| • | $0.05 per share of lower electric margins related to changes in the recovery of fuel-related expense at WPL. |
| • | April 2014 - The scrubber and baghouse at WPL’s Columbia Unit 2 were placed in service. In addition, the scrubber and baghouse at WPL’s Columbia Unit 1 were placed in service in July 2014. |
| • | May 2014 - The scrubber and baghouse at IPL’s George Neal Unit 3 were placed in service. |
| • | June 2014 - After receiving the final necessary regulatory approvals and permits in the second quarter of 2014, IPL began constructing Marshalltown, an approximate 650 MW natural gas-fired combined-cycle EGU. IPL currently expects to place Marshalltown in service in the second quarter of 2017. |
| • | November 2014 - WPL announced plans to file a CPCN application with the PSCW in early 2015 for approval to construct an approximate 650 MW natural gas-fired combined-cycle EGU in Beloit, Wisconsin, referred to as the Riverside expansion. A decision from the PSCW on WPL’s request is currently expected by mid-2016. Construction of the Riverside expansion is also subject to the receipt of various approvals and permits necessary to construct and operate the EGU. Subject to such approvals, construction is currently expected to begin in 2016 and be completed by early 2019. Capital expenditures are currently estimated to be approximately $725 million to $775 million to construct the EGU and a pipeline to supply natural gas to the EGU. The estimated capital expenditures exclude transmission network upgrades and AFUDC. |
| • | December 2014 - The MPUC issued an order approving the proposed sale of IPL’s Minnesota natural gas distribution assets. IPL currently expects to complete the sale in 2015 pending completion of various other contingencies. Proceeds from the sale of the natural gas distribution assets, which approximate the carrying value of such assets, are expected to be approximately $10 million, subject to customary closing adjustments. |
| • | December 2014 - The scrubber and baghouse at IPL’s Ottumwa Unit 1 were placed in service. |
| • | January 2015 - WPL received an order from the PSCW approving WPL’s CA application to install an SCR system at Columbia Unit 2 to reduce NOx emissions at the EGU. WPL’s portion of the capital expenditures for the SCR system, excluding AFUDC, is currently estimated to be between $60 million and $80 million. WPL currently expects to place the project in service in 2018. |
Federal regulation of wholesale electric rates is administered by FERC and state regulation of retail utility rates is administered by the IUB, PSCW and MPUC.
| • | July 2014 - WPL received an order from the PSCW authorizing WPL to maintain retail electric base rates at their current levels through the end of 2016. The retail electric base rate case included a return of and a return on costs for emission controls projects at Columbia Units 1 and 2 and Edgewater Unit 5, generation performance and reliability improvements at Columbia Units 1 and 2, other ongoing capital expenditures, and an increase in electric transmission service expense. The additional revenue requirement for these cost increases was offset by the impact of changes in the amortization of regulatory liabilities associated with energy efficiency cost recoveries and increased sales volumes. The order also authorized WPL to implement a $5 million decrease in annual retail gas base rates effective January 1, 2015 followed by a freeze of such gas base rates through the end of 2016. |
| • | September 2014 - The IUB approved a settlement agreement, which extends IPL’s Iowa retail electric base rates authorized in its 2009 test year case through 2016 and provides retail electric customer billing credits of $105 million in aggregate, including targeting $70 million in 2014 (beginning May 2014), $25 million in 2015 and $10 million in 2016. In 2014, IPL recorded $72 million of such retail electric customer billing credits. IPL will make adjustments to future billing credits to provide retail electric customer billing credits of $105 million in aggregate. The settlement agreement included the continuation of the energy adjustment clause, transmission cost rider and electric tax benefit rider credits; the ability for IPL to seek rate relief if a significant event occurs; and the ability for parties to the DAEC PPA proceeding to request show cause action if IPL’s Iowa retail electric return on common equity exceeds 11% for 2014, 2015 or 2016. |
| • | June 2014 - The EPA issued proposed standards to reduce CO2 emissions from existing fossil-fueled EGUs. The EPA is proposing a two-part goal structure: an “interim goal” that each state meets an average threshold over the period from 2020 through 2029, and a “final goal” based on a three-year rolling average that each state meets beginning in 2030. State plans that provide details of how these guidelines are to be met would be required by June 30, 2016. The EPA’s proposal allows for a one-year extension to submit state-only plans and a two-year extension if a state elects to join a regional multi-state program. In August 2014, the EPA’s legal authority to issue the proposed standards was challenged. The EPA is currently expected to issue final standards in 2015. |
| • | August 2014 - The EPA published a final rule related to Section 316(b) of the Federal Clean Water Act rule to regulate cooling water intake structures and minimize adverse environmental impacts to fish and other aquatic life. Compliance with this final rule will be incorporated during periodic facility permit renewal cycles, with final compliance anticipated by 2022. |
| • | December 2014 - The EPA issued the final CCR rule, which regulates CCR as a non-hazardous waste. The final rule establishes minimum criteria for disposing of CCR in landfills and surface impoundments (ash ponds), and allows for continued operation of ash ponds if they meet certain location and performance criteria. The rule is currently anticipated to become effective in 2015. |
| • | January 2015 - CSAPR replaced CAIR. Compliance with CSAPR emissions limits began in 2015, with additional emissions limits reductions beginning in 2017. |
| • | October 2014 - WPL issued $250 million of 4.1% debentures due 2044. The proceeds from the issuance were used by WPL to reduce commercial paper and for general corporate purposes. |
| • | October 2014 - Alliant Energy entered into a $250 million variable-rate term loan credit agreement and used the proceeds from borrowings under this agreement to retire its $250 million, 4% senior notes. The term loan credit agreement expires in October 2016. |
| • | November 2014 - WPL received authorization from the PSCW to issue up to $500 million of long-term debt securities during 2015 and 2016, with no more than $300 million to be issued in either year. |
| • | November 2014 - Alliant Energy, IPL and WPL announced their future financing plans. IPL currently expects to issue up to $300 million of additional long-term debt in 2015. IPL’s $150 million, 3.3% senior debentures mature in 2015. Alliant Energy currently expects to issue approximately $150 million of common stock in 2015 through one or more offerings and its Shareowner Direct Plan. |
| • | December 2014 - Franklin County Holdings LLC, Resources’ wholly-owned subsidiary, entered into a $60 million variable-rate term loan credit agreement and used the proceeds to retire its borrowings under a term loan credit agreement that matured in December 2014. The latest term loan credit agreement expires December 2016. |
| • | October 2014 - FERC issued an order on a complaint against the MISO transmission owners. The order established hearing and settlement procedures on the return on equity component of the complaint, and established a refund period back to November 12, 2013. FERC also denied a request to limit the regulatory capital structure to 50% of common equity, among other items. Settlement discussions between the parties were held and no agreement was reached. The complaint is now subject to hearing procedures and an initial decision from FERC on the complaint is currently expected in late 2015. Alliant Energy, IPL and WPL are currently unable to determine what, if any, impact the October 2014 FERC order, subsequent hearing procedures and a new methodology FERC established for determining the return on equity may have on the returns authorized by FERC for MISO transmission owners, including ITC and ATC. |
| • | January 2015 - FERC issued an order accepting a request from a group of MISO transmission owners, including ITC and ATC, to implement a 50 basis point incentive adder to their return on equity based on participation in MISO. The implementation of the adder is effective January 2015, subject to certain conditions. Alliant Energy, IPL and WPL are currently unable to determine any resulting changes to future electric transmission service charges. |
For example, IPL and WPL have retail electric base rate freezes in Iowa and Wisconsin, respectively, during 2015 and 2016.
customers’ bills to help offset impacts of rate increases.
Responsible Resources \- Another key element of the strategic plan is finding innovative ways to meet environmental objectives, improve energy efficiency and provide resource flexibility.
A diversified fuel mix for EGUs is important to meet the energy needs of customers and also recognizes the importance of using resources in environmentally responsible ways for the benefit of future generations.
| • | Natural gas - purchasing, constructing and/or converting to natural gas-fired EGUs. IPL is currently constructing Marshalltown, an approximate 650 MW natural gas-fired combined cycle EGU, and M.L. Kapp Unit 2 is expected to switch from coal to natural gas as its only fuel type in 2015. WPL currently plans to file a CPCN application with the PSCW in early 2015 for approval to construct an approximate 650 MW natural gas-fired combined cycle EGU referred to as the Riverside expansion. |
| • | Renewables - operating hydroelectric generators and current wind projects, as well as evaluating the development of future wind sites and solar projects. IPL and WPL currently have up to 400 MW and 200 MW of undeveloped wind sites, respectively, available for future wind projects. Alliant Energy, IPL and WPL are also exploring opportunities to integrate solar projects into the portfolio of energy resources as the cost to produce solar energy continues to decline. |
As a result of these efforts, SO2 and NOx emissions are currently expected to be reduced by approximately 90% and 80%, respectively, from 2005 levels by 2025.
Mercury emissions are currently expected to be reduced by approximately 90% from 2009 levels by 2025.
CO2 emissions have been reduced by approximately 15% from 2005 levels.
In addition, WPL contributes 1.2% of its annual utility revenues to Wisconsin’s Focus on Energy program.
Generation Plans - Generation plans are reviewed and updated as deemed necessary and in accordance with regulatory requirements.
After receiving the final necessary regulatory approvals and permits in the second quarter of 2014, IPL began constructing Marshalltown.
IPL currently expects to place Marshalltown in service in the second quarter of 2017.
Refer to [Note 3](#sAA2499D9F431FDD1F46A6ABA34CF93A1) for further discussion of Marshalltown.
measures that management uses to manage its operations and evaluate its performance.
| • | $0.14 per share related to the impact of state income tax charges in 2012 due to changes in state apportionment projections caused by Alliant Energy’s announced sale of the RMT business; |
| • | an estimated $0.05 per share of net increases in revenues from higher electric and gas sales in 2013 compared to 2012 due to weather conditions. |
| • | $0.05 per share of higher distribution system operation and maintenance expenses in 2013 compared to 2012. |
Non-regulated and parent - Lower EPS from continuing operations in 2013 compared to 2012 was primarily due to $0.04 per share of losses incurred at the Franklin County wind project in 2013.
| • | April 2013 - WPL announced that its current environmental compliance plans include installing an SCR at Columbia Unit 2 to reduce NOx emissions. The SCR is expected to support compliance obligations for current and anticipated air quality regulatory requirements, including CAIR or some alternative to this rule that may be implemented. WPL currently expects to file a CA application with the PSCW in the second quarter of 2014 for the SCR at Columbia Unit 2. |
| • | July 2013 - FERC issued an order requiring MISO, on behalf of ITC, to revise ITC’s Attachment “FF” tariff, which determines how much of the transmission network upgrade costs incurred to interconnect an EGU to ITC’s transmission system will be incurred by the owner of such EGU. The revisions to ITC’s Attachment “FF” tariff required by the FERC order result in the owners of the EGUs being responsible for a substantially higher portion of the transmission network upgrade costs required to meet MISO interconnection requirements. IPL and WPL currently anticipate that ITC will pursue an option separate from ITC’s revised Attachment “FF” tariff to self-fund the transmission network upgrades associated with Marshalltown and Bent Tree, respectively. As a result, ITC would incur the capital expenditures to construct the transmission network upgrades and include a direct charge for such transmission network upgrade costs as part of its electric transmission service costs billed to IPL and WPL as the owners of Marshalltown and Bent Tree, respectively. |
| • | September 2013 - IPL signed separate definitive agreements to sell its Minnesota electric and natural gas distribution assets. Proceeds from the sales are expected to be approximately $128 million in aggregate, subject to customary closing adjustments. The proceeds are expected to reduce Alliant Energy’s and IPL’s future financing requirements. Pending all |
necessary federal and state regulatory approvals, including the MPUC, FERC and the IUB, the transactions are expected to be concluded in the second half of 2014.
The electric distribution asset sales agreement includes a wholesale power supply agreement, which is subject to FERC approval.
The agreement contains a five-year termination notice, which may not be given until the fifth anniversary of the effective date of the agreement, resulting in a minimum term of 10 years.
This wholesale power supply agreement includes standardized pricing mechanisms that are detailed in IPL’s current tariffs accepted by FERC through wholesale rate case proceedings.
| • | November 2013 - Alliant Energy announced WPL currently expects to begin incurring capital expenditures in 2016 for a potential generation investment to address its future customer energy and capacity needs. Options under consideration include conversion of an existing natural gas-fired facility from simple-cycle to combined-cycle, or the construction of a new resource. WPL plans to complete a feasibility study of resource options and file the necessary regulatory applications for approval of the selected resource option with the PSCW by the end of 2014. |
Alliant Energy’s utility subsidiaries, IPL and WPL, are subject to federal regulation by FERC, which has jurisdiction over wholesale electric rates, and state regulation in Iowa, Wisconsin and Minnesota for retail utility rates.
| • | January 2013 - The IUB authorized IPL to recover the Iowa retail portion of the costs of its DAEC PPA from Iowa retail electric customers through the energy adjustment clause beginning February 22, 2014. The IUB encouraged IPL to continue discussions with parties to the DAEC PPA proceeding to resolve concerns expressed by such parties during the proceeding regarding rate impacts beginning in 2014. IPL is preparing to file an Iowa retail electric base rate case without interim rates in late March 2014 in case such discussions do not result in a resolution of the issues. Based on the terms of the January 2013 order, if the IUB would order a rate decrease from such a rate case, IPL has agreed to subject its Iowa retail electric base rates to potential refund beginning February 22, 2014. IPL currently anticipates a decision from the IUB on this matter by the end of 2014, either through an approved rate case or an approved settlement. |
| • | February 2013 - IPL received an order from the IUB approving the 2013 electric tax benefit rider tariff and a $24 million revenue requirement adjustment recognized during 2013. |
| • | November 2013 - Alliant Energy announced WPL currently expects to make a retail rate filing in late March 2014 based on a forward-looking test period that may include calendar years 2015 and 2016. The form and magnitude of such filing is currently being analyzed and could range from a future test year 2015 electric fuel plan to a full rate case for the 2015 and 2016 test period. Any rate changes granted are expected to be effective in early 2015. |
| • | December 2013 - IPL received an order from the IUB approving the 2014 electric tax benefit rider tariff and a $15 million revenue requirement adjustment to be recognized during 2014. |
| • | December 2013 - IPL received an order from the MPUC approving full cost recovery of the Minnesota retail portion of IPL’s Whispering Willow - East wind project construction costs of approximately $30 million, effective January 1, 2013. |
| • | December 2013 - WPL received an order from the PSCW authorizing an annual retail electric rate increase of $19 million, or approximately 2%, effective January 1, 2014, to reflect anticipated increases in retail electric fuel-related costs in 2014 compared to the fuel-related cost estimates used to determine rates for 2013. WPL’s 2014 fuel-related costs will be subject to deferral if they fall outside an annual bandwidth of plus or minus 2% of the approved annual forecasted fuel-related costs. |
| • | January 2014 - IPL received an order from the IUB approving IPL’s transmission cost rider rates effective February 1, 2014. |
| • | April 2013 - WPL, along with the other owners of Edgewater and Columbia, entered into a Consent Decree with the EPA and the Sierra Club to resolve certain alleged air permitting violations, while admitting no liability. The Consent Decree was approved by the Court in June 2013 thereby resolving the related claims and requiring the installation of certain emission controls systems. |
| • | June 2013 - President Obama announced plans to address climate change and issued a memorandum directing the EPA to proceed with rules to reduce CO2 emissions from new and existing fossil-fueled EGUs. In January 2014, the EPA published revised proposed NSPS for GHG emissions for new fossil-fueled EGUs. A date for finalizing these standards has not yet been established. The EPA is expected to issue proposed and final NSPS for GHG emissions for existing EGUs by June 1, 2014 and June 1, 2015, respectively, which would provide guidelines that states must follow to achieve required GHG emissions reductions. SIPs that provide details of how these guidelines are to be met would be required from state agencies by June 30, 2016. |
| • | June 2013 - The U.S. Supreme Court issued an order granting an EPA petition for review of a D.C. Circuit Court decision to vacate and remand CSAPR for further EPA review. The U.S. Supreme Court ruling on the CSAPR vacatur is expected in 2014, and during the interim, CAIR remains effective. |
| • | March 2013 - IPL issued 8,000,000 shares of 5.1% cumulative preferred stock and received proceeds of $200 million. The proceeds were used by IPL to redeem all 6,000,000 outstanding shares of its 8.375% cumulative preferred stock for $150 million, reduce commercial paper classified as long-term debt by $40 million and for other general corporate purposes. |
| • | March 2013 - WPL redeemed all 1,049,225 outstanding shares of its 4.40% through 6.50% cumulative preferred stock for $61 million. |
| • | August 2013 - WPL received approval from the PSCW to issue up to $400 million of long-term debt securities through 2014. |
| • | November 2013 - IPL received authority from FERC to issue through December 31, 2015 up to $750 million of long-term debt securities in aggregate, up to $750 million of short-term debt securities at any time and up to $300 million of preferred stock in aggregate. |
| • | November 2013 - Alliant Energy, IPL and WPL announced their future financing plans, which include issuing up to $600 million, $300 million and $300 million, respectively, of additional long-term debt in 2014. Alliant Energy currently |
expects to issue approximately $150 million of common stock through 2016.
Alliant Energy currently does not plan to issue any material amount of common stock in 2014.
| • | January 2014 - Moody’s Investors Service raised Alliant Energy’s and WPL’s credit ratings. |
| • | April 2013 - IPL and MidAmerican filed a joint Notice of Appeal, and the IUB and the Iowa Association of Electric Cooperatives filed Notices of Appeal, with the Iowa Supreme Court related to a ruling by the Polk County, Iowa District Court in March 2013. This ruling found Eagle Point is not a public utility and could sell directly to the City of Dubuque the power generated by a 175 kilowatt solar unit installed on the City’s property. The District Court decision is currently stayed. Alliant Energy and IPL are unable to determine how this District Court ruling may impact the level of third-party solar development in IPL’s service territory and resulting impact on future demand of electricity by IPL’s customers. |
| • | July 2013 - FERC issued an order requiring MISO, on behalf of ITC, to revise ITC’s Attachment “FF” tariff to conform to the MISO Attachment “FF” tariff. In August 2013, MISO submitted a filing with the proposed tariff revisions, which became effective as of the date of the July 2013 order. Also in August 2013, ITC filed a request for rehearing and/or clarification, and IPL filed a request for clarification. In February 2014, FERC issued an order that denied ITC’s request for rehearing, responded to the requests for clarification, accepted MISO’s tariff revisions and substantially affirmed its July 2013 order. The tariff revisions ordered by FERC are expected to reduce the amount of transmission network upgrade costs billed by ITC to IPL compared to what would have been billed under ITC’s prior Attachment “FF” tariff. Alliant Energy and IPL currently expect to pass on the Iowa retail portion of any changes in electric transmission service costs billed by ITC to IPL from the revision in ITC’s Attachment “FF” tariff to IPL’s retail electric customers in Iowa through the transmission cost recovery rider. |
| • | September 2013 - ITC finalized its Attachment “O” rate it proposes to charge its customers in 2014 for electric transmission services. The increase in ITC’s Attachment “O” rate, as well as MISO transmission charges for shared transmission projects, are expected to contribute to increases in future electric transmission service charges for IPL and WPL. Alliant Energy, IPL and WPL currently estimate their electric transmission service expenses in 2014 will be higher than the comparable expenses charged in 2013 by approximately $30 million, $20 million and $10 million, respectively. A significant portion of the increase in IPL’s electric transmission service expenses is expected to be offset with increases in electric revenues resulting from the transmission cost recovery rider. A significant portion of the increase in WPL’s electric transmission service expenses was utilized to set electric revenues approved by the PSCW in WPL’s latest retail electric base rate case. |
| • | November 2013 - A group of MISO industrial customer organizations filed a complaint with FERC requesting to: (1) reduce the base return on equity used by MISO transmission owners, including ITC and ATC, to 9.15%; (2) institute a regulatory capital structure not to exceed 50% of common equity; and (3) eliminate certain return on equity adders. ITC’s and ATC’s current authorized return on equity is 12.38% and 12.2%, respectively. ITC’s and ATC’s current authorized regulatory capital structure for common equity is 60% and 50%, respectively. Any change to ITC’s and ATC’s return on equity and regulatory capital structure for common equity would impact the calculation of their respective Attachment “O” rates, resulting in changes to electric transmission service costs billed by ITC and ATC to their customers. Any changes in IPL’s electric transmission service costs billed by ITC to IPL are expected to be passed on to IPL’s Iowa retail electric customers through the transmission cost recovery rider. Any changes in WPL’s electric transmission service costs will be incorporated into WPL’s retail electric rates in a future retail electric base rate proceeding with the PSCW. In addition, any change to ATC’s return on equity and regulatory capital structure for common equity could result in Alliant Energy and WPL realizing lower equity income and dividends from ATC in the future. |
The strategic plan is built upon three key elements: competitive costs, safe and reliable service, and balanced generation.
Alliant Energy’s, IPL’s and WPL’s approach to energy efficiency is based on regulations in Iowa and Wisconsin.
The objective in each of these states is to meet prescribed goals in the most cost-effective manner.
Alliant Energy, IPL and WPL believe a diversified fuel mix for their EGUs is important to meeting the needs of their customers, shareowners and the environment while preparing for a potentially carbon-constrained environment in the future.
An excerpt. Shown here: 40 of 673 rewritten, 40 of 388 added and 40 of 484 removed. The counts are complete. For every sentence, read Item 7. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS in the FY2014 filing and the FY2013 filing.
Item 7A. QUANTITATIVE AND QUALITATIVE DISCLOSURES ABOUT MARKET RISK
1 rewritten, 0 added, 0 removed, 0 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Quantitative and Qualitative Disclosures About Market Risk are reported in “[Other Matters - Market Risk Sensitive Instruments and [removed: Positions](#sA02ED73A59C9955B68F3F8B9E134FE5D)”] [added: Positions](#sD74E79C523565D5D95EA6ABA7C4B5BCF)”] in MDA.
Item 1. BUSINESS
319 rewritten, 79 added, 68 removed, 268 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Alliant Energy’s primary focus is to provide regulated [removed: electricity] [added: electric] and natural gas service to approximately 1 million electric and approximately [removed: 418,000] [added: 420,000] natural gas customers in the Midwest through its two public utility subsidiaries, IPL and WPL.
IPL is a public utility engaged principally in the generation and distribution of electricity and the distribution and transportation of natural gas in [removed: selective] [added: select] markets in Iowa and southern Minnesota.
At December 31, [removed: 2013,] [added: 2014,] IPL supplied electric and natural gas service to [removed: 528,355] [added: approximately 529,000] and [removed: 234,563] [added: 235,000] retail customers, respectively.
In [removed: 2013, 2012] [added: 2014, 2013] and [removed: 2011,] [added: 2012,] IPL had no single customer for which electric, gas, steam and/or other sales accounted for 10% or more of IPL’s consolidated revenues.
Refer to [Note [removed: 3(a)](#s7699adb581a54c8e952936c5043d527a) of the “Combined Notes to Consolidated Financial Statements”] [added: 3](#sAA2499D9F431FDD1F46A6ABA34CF93A1)] for discussion of IPL’s [removed: proposed] [added: anticipated] sales of its Minnesota electric and natural gas distribution assets.
WPL is a public utility engaged principally in the generation and distribution of electricity and the distribution and transportation of natural gas in [removed: selective] [added: select] markets in southern and central Wisconsin.
In [removed: 2013, 2012] [added: 2014, 2013] and [removed: 2011,] [added: 2012,] WPL had no single customer for which electric, gas and/or other sales accounted for 10% or more of WPL’s consolidated revenues.
Refer to “[Information Relating to Non-regulated [removed: Operations](#sC181B87C2B5E0A965EEDF8B9DD0940B7)”] [added: Operations](#sAEA261FE173C3DBEB53E6ABA7834C525)”] for additional details.
Refer to [Note [removed: 17](#sD43E0B10205982CF225CF8B9B71254DA) of the “Combined Notes to Consolidated Financial Statements”] [added: 17](#sADB3FE9ADAED31AE6EB66ABA34D83703)] for further discussion of business segments, which information is incorporated herein by reference.
1) EMPLOYEES - At December 31, [removed: 2013,] [added: 2014,] Alliant Energy’s consolidated subsidiaries had the following full- and part-time employees:
At December 31, [removed: 2013,] [added: 2014,] Alliant Energy employees covered by collective bargaining agreements were as follows:
| IBEW Local 204 (Cedar Rapids) | [removed: 757] [added: 770] | | | 8/31/17 |
| IBEW - Various | [removed: 362] [added: 373] | | | Various |
| WPL - IBEW Local 965 | [removed: 1,026] [added: 1,128] | | | [removed: 5/31/14] [added: 5/31/19] |
| Resources - Various | [removed: 85] [added: 88] | | | Various |
| Corporate Services - IBEW Local 204 | [removed: 25] [added: 24] | | | [removed: 10/31/14] [added: 10/31/16] |
2) CAPITAL EXPENDITURE AND INVESTMENT PLANS - Refer to “[Liquidity and Capital [removed: Resources](#s347182CA2CD1EEDAF167F8B9CA32EBB3) - Cash Flows - Investing Activities - Construction and Acquisition Expenditures”] [added: Resources](#sC406469B25A3650B9C066ABA501F1587)”] in MDA for discussion of anticipated construction and acquisition expenditures for [removed: 2014] [added: 2015] through [removed: 2017.][added: 2018.]
Public Utility Holding Company Act of 2005 - Alliant Energy is registered with FERC as a public utility holding company, pursuant to [removed: PUHCA,] [added: the Public Utility Holding Company Act of 2005,] and is required to maintain certain records and to report certain transactions involving its public utilities, service company and other entities regulated by FERC.
Corporate Services, IPL and WPL are subject to regulation by FERC under [removed: PUHCA] [added: the Public Utility Holding Company Act of 2005] for various matters including, but not limited to, affiliate transactions, public utility mergers, acquisitions and dispositions, and books, records and accounting requirements.
Energy Policy Act - The Energy Policy Act requires creation of an [removed: ERO] [added: Electric Reliability Organization] to provide oversight by FERC.
[removed: MRO,] [added: Midwest Reliability Organization,] which is a regional member of [removed: NERC,] [added: North American Electric Reliability Corporation,] has direct responsibility for mandatory electric reliability standards for IPL and WPL.
Federal Power Act - FERC also has jurisdiction, under the Federal Power Act, over certain electric utility facilities and operations, electric wholesale and transmission rates, dividend payments, issuance of [removed: securities (only IPL, and Corporate Services through March 31, 2014)] [added: IPL’s securities,] and accounting practices of Corporate Services, IPL and WPL.
Market-based rate authorization allows for wholesale sales of electricity within the MISO and PJM markets and in [removed: bilateral markets,] [added: transactions directly with third parties,] based on the market value of the transactions.
Due to the formula rates used by ITC and ATC to charge their customers and possible future changes to these rates, there is uncertainty regarding IPL’s and WPL’s future electric transmission service [removed: expenses.][added: expense.]
Refer to “[Other Future [removed: Considerations](#s7F8D069BA2FDF5911C76F8B9C9E026A7)”] [added: Considerations](#s2DB6159B9E91221797116ABA7C8E9DD7)”] in MDA for further discussion of electric transmission service [removed: charges.][added: expense.]
IUB - IPL is subject to regulation by the IUB related to its operations in Iowa for various matters including, but not limited to, retail utility rates and standards of service, accounting [removed: requirements] [added: requirements, sales of assets with values that exceed 3% of IPL’s revenues for its Iowa jurisdiction,] and approval of the location and construction of EGUs.
Retail Electric Transmission Cost Recovery Mechanism - Electric transmission service [removed: expenses are] [added: expense is] billed to IPL’s Iowa retail electric customers through a transmission cost rider.
This cost recovery mechanism provides for subsequent adjustments to electric rates charged to Iowa retail electric customers for changes in electric transmission service [removed: expenses.][added: expense.]
The EECR factors are revised annually and include a reconciliation to eliminate any over- or under-recovery of energy efficiency [removed: expenses] [added: expense] from prior periods.
Electric Generating Units - IPL must obtain a [removed: GCU Certificate] [added: certificate of public convenience, use and necessity (GCU Certificate)] from the IUB in order to construct a [removed: new] [added: new,] or significantly alter an [removed: existing] [added: existing,] EGU located in Iowa with 25 MW or more of capacity.
As a result, IPL [removed: must] [added: may] file for, and the IUB must render a decision on, rate-making principles for EGUs located in Iowa, including new base-load (nuclear or coal-fired generation) EGUs with a nameplate generating capacity of 300 MW or more, combined-cycle natural gas-fired EGUs [removed: of any size] and renewable generating resources, such [added: as wind facilities.]
Electric Generating Unit Emission Controls Projects \- IPL is required to submit an EPB biennially to the IUB setting out a multi-year plan and budget for managing regulated emissions from its [added: coal-fired] EGUs in a cost-effective manner.
The reasonable costs associated with implementing the [added: approved] plan are expected to be included in IPL’s future retail electric rates.
Energy Efficiency Cost Recovery [removed: Mechanism] - WPL contributes a certain percentage of its annual utility revenues to help fund Focus on Energy, Wisconsin’s state-wide energy efficiency and renewable energy resource program.
Estimated contributions to Focus on Energy, along with WPL-run energy efficiency program costs, are recovered from WPL’s retail customers through changes in base rates determined during periodic rate proceedings and include a reconciliation of such estimated amounts to actual costs incurred with any difference deferred for inclusion in [added: a] future base rate [removed: changes.][added: proceeding.]
New Electric Generating Units - A CA application is required to be filed with the PSCW for construction approval of any new EGU with a capacity of less than 100 [removed: MW.][added: MW and a project cost of $10 million or more.]
WPL must obtain a [removed: Certificate of Public Convenience and Necessity] [added: CPCN] from the PSCW in order to construct a new EGU in Wisconsin with a capacity of 100 MW or more.
Electric Generating Unit Upgrades - A CA application is required to be filed with the PSCW for construction approval of any additions to EGUs, including emission controls [removed: projects that exceed a certain threshold amount.][added: projects.]
The current PSCW rules require a CA [added: application] for [added: such] projects with an estimated project cost of $10 million or more.
Retail Utility Rates - Requests for retail rate change can be based on either historical or projected data and interim retail rates [removed: are permitted.][added: can be implemented 60 days after the filing date, with regulatory review.]
At December 31, 2014, WPL supplied electric and natural gas service to approximately 463,000 and 185,000 retail customers, respectively.
WPL’s consolidated subsidiary, WPL Transco, holds Alliant Energy’s investment in ATC.
Refer to [Note 6(a)](#s371FE11E1259F07CF8DF6ABA370E3B3B) for further discussion of ATC.
| IPL | 1,143 | | | 623 | | | 1,766 | | | 65 | % |
| WPL | 1,128 | | | 263 | | | 1,391 | | | 81 | % |
| Corporate Services | 24 | | | 915 | | | 939 | | | 3 | % |
| Resources | 88 | | | 28 | | | 116 | | | 76 | % |
| | 2,383 | | | 1,829 | | | 4,212 | | | 57 | % |
| | 1,143 | | | |
| | 2,383 | | | |
FERC designated North American Electric Reliability Corporation as the overarching Electric Reliability Organization.
IPL’s ownership and operation of EGUs (including those located outside the state of Iowa) to serve Iowa customers is subject to retail utility rate regulation by the IUB.
Gas Distribution Projects - IPL must obtain a pipeline permit from the IUB related to the citing of certain utility gas pipelines in Iowa.
Currently, WPL is required to defer a portion of its earnings if its annual regulatory return on common equity exceeds certain levels and is allowed to request a change in retail base rates if its annual return on common equity falls below a certain level.
Retail Electric Transmission Cost Recovery - WPL’s retail electric base rates include estimates of electric transmission service expense anticipated during the forward-looking test period.
A majority of WPL’s electric transmission service expense in 2015 and 2016 will be subject to a reconciliation of such estimated amounts to actual costs incurred with any difference deferred for inclusion in future base rate changes.
Gas Distribution Projects - A CA application is required to be filed with the PSCW for construction approval of gas projects with an estimated project cost of $2.5 million or more and at any time that WPL requests to extend gas service to a new portion of its service territory.
Refer to [Note 3](#sAA2499D9F431FDD1F46A6ABA34CF93A1) for discussion of this anticipated sale.
| | Iowa | | | Minnesota | | | Wisconsin | | | Total | | | Customers | | | Customers | | | Customers | | | Served | |
| IPL | 486,854 | | | 42,338 | | | — | | | 529,192 | | | 7 | | | 1,378 | | | 530,577 | | | 752 | |
| WPL | — | | | — | | | 463,139 | | | 463,139 | | | 21 | | | 2,256 | | | 465,416 | | | 607 | |
| | 486,854 | | | 42,338 | | | 463,139 | | | 992,331 | | | 28 | | | 3,634 | | | 995,993 | | | 1,359 | |
Deferrals of under-collections are reduced to the extent actual return on common equity earned by WPL during the fuel cost plan year exceeds the applicable authorized return on common equity.
Refer to “[Other Future Considerations](#s2DB6159B9E91221797116ABA7C8E9DD7)” in MDA for discussion of notifications provided to each of IPL and WPL to terminate certain of their wholesale power supply agreements.
| | Summer Peak | | | | Winter Peak | | |
| Alliant Energy | 5,426 | | July 22 | | 4,803 | | January 6 |
| IPL | 2,840 | | September 4 | | 2,601 | | January 6 |
| WPL | 2,594 | | July 22 | | 2,202 | | January 6 |
purchases from wholesale energy markets.
| | MWs | | | % | | | MWs | | | % | | | MWs | | | % | |
| Coal | 1,641 | | | 51 | % | | 1,463 | | | 46 | % | | 3,104 | | | 48 | % |
| Oil | 347 | | | 11 | % | | — | | | — | % | | 347 | | | 5 | % |
| Total | 3,219 | | | 100 | % | | 3,221 | | | 100 | % | | 6,440 | | | 100 | % |
Alliant Energy, through its subsidiaries Corporate
During 2014, coal deliveries to one of WPL’s EGUs were delayed due to additional rail-car traffic for non-coal commodities.
As a result, WPL shifted some of its rail-car coal traffic to a less congested route to help avoid such delays.
Legacy transportation contracts at each of IPL and WPL expired at the end of 2014, which will result in higher coal transportation costs for IPL and WPL beginning in 2015.
Refer to “[Strategic Overview](#s06C4F7DE4D3FFCA8A1BD6ABA7ACD6C39)” for discussion of IPL’s construction of Marshalltown, an approximate 650 MW natural gas-fired combined-cycle EGU and WPL’s proposed construction of the Riverside expansion, an approximate 650 MW natural gas-fired combined-cycle EGU.
WPL’s
Refer to “[Properties](#s4C687D89ADD7C1A852386ABA4FA7ADC9)” in Item 2 for the generating capacity of these wind projects.
At December 31, 2013, WPL supplied electric
and natural gas service to 460,396 and 182,647 retail customers, respectively.
At December 31, 2013, WPL Transco was a wholly-owned subsidiary of WPL and held WPL’s investment in ATC.
| IPL | 1,119 | | | 557 | | | 1,676 | | | 67 | % |
| WPL | 1,026 | | | 251 | | | 1,277 | | | 80 | % |
| Corporate Services | 25 | | | 853 | | | 878 | | | 3 | % |
| Resources | 85 | | | 29 | | | 114 | | | 75 | % |
| | 2,255 | | | 1,690 | | | 3,945 | | | 57 | % |
| | 1,119 | | | |
| | 2,255 | | | |
FERC designated NERC as the overarching ERO.
as wind facilities, of any size.
Refer to [Note 3(a)](#s7699adb581a54c8e952936c5043d527a) of the “Combined Notes to Consolidated Financial Statements” for discussion of this proposed sale.
| IPL | 528,355 | | | 8 | | | 1,366 | | | 529,729 | | | 752 | |
| WPL | 460,396 | | | 21 | | | 2,262 | | | 462,679 | | | 607 | |
| | 988,751 | | | 29 | | | 3,628 | | | 992,408 | | | 1,359 | |
WPL’s recovery of deferred fuel-related costs is restricted if it earns in excess of its authorized return on common equity.
| MW | 5,820 | | 3,107 | | 2,752 |
Refer to “[Other Future Considerations](#s7F8D069BA2FDF5911C76F8B9C9E026A7)” in MDA for discussion of litigation related to a renewable power developer seeking to distribute energy in IPL’s service territory, which may impact IPL’s future electric sales.
In 2010, the PSCW approved an economic development program, which is intended to attract and retain industrial customers in WPL’s service territory.
The program permits WPL to enter into a contract with eligible industrial customers for a discounted energy rate based upon specifically-defined conditions through December 2014.
To be eligible for the program, each customer needs to demonstrate that it is also eligible for direct governmental assistance through a local, state or federal economic development program, in addition to other criteria.
The discount amounts are limited to ensure recovery of marginal costs and will be decreased over time until a customer is paying the full tariff rate.
Currently, there are three WPL customers utilizing the economic development program.
Beginning with the June 1, 2013 through May 31, 2014 MISO planning year, MISO implemented an LRZ concept.
The purpose of the LRZ concept is to encourage adequate generating resources adjacent to the load served by such generating resources.
IPL is located in LRZ No. 3, which covers the entire state of Iowa and a portion of southern Minnesota.
WPL is located in LRZ No. 2, which covers the southern and eastern portions of Wisconsin and upper peninsula of Michigan.
Subject to certain zonal transfer capacity limits, load-serving utilities (including IPL and WPL) are permitted to have generating capacity located outside of their respective LRZs if they procure firm point-to-point transmission service to import the capacity from another LRZ.
If a utility chooses to import capacity from another LRZ without firm point-to-point transmission service, it will incur a zonal delivery charge.
Neither IPL nor WPL have current generating capacity located outside of their respective LRZs; therefore they do not expect to be subject to zonal delivery charges during the June 1, 2013 through May 31, 2014 and June 1, 2014 through May 31, 2015 MISO planning years.
| | IPL | | | WPL | | | Total | |
| Coal | 1,617 | | | 1,338 | | | 2,955 | |
| Oil | 349 | | | — | | | 349 | |
| Total | 3,197 | | | 3,096 | | | 6,293 | |
published by the Association of American Railroads.
Electric Transmission \-
IPL - IPL currently receives substantially all its electric transmission services from ITC.
Refer to “[Rate Matters](#sAC09DDB84E9D4F9EC770F8B9CFB3A73E)” in MDA for discussion of a transmission cost rider approved by the IUB in January 2011 for recovery of IPL’s electric transmission service expenses.
WPL - WPL currently receives substantially all its transmission services from ATC.
An excerpt. Shown here: 40 of 319 rewritten, 40 of 79 added and 40 of 68 removed. The counts are complete. For every sentence, read Item 1. BUSINESS in the FY2014 filing and the FY2013 filing.
Cover and table of contents
104 rewritten, 29 added, 44 removed, 199 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
For the fiscal year ended December 31, [removed: 2013][added: 2014]
The aggregate market value of the voting and non-voting common equity held by nonaffiliates as of June 30, [removed: 2013:][added: 2014:]
| Alliant Energy Corporation | [removed: $5.6] [added: $6.7] billion |
Number of shares outstanding of each class of common stock as of January [removed: 31, 2014:][added: 30, 2015:]
| Alliant Energy Corporation | Common stock, $0.01 par value, [removed: 110,943,669] [added: 110,935,680] shares outstanding |
Portions of the Proxy Statement relating to Alliant Energy Corporation’s [removed: 2014] [added: 2015] Annual Meeting of Shareowners are, or will be upon filing with the Securities and Exchange Commission, incorporated by reference into Part III hereof.
| [Forward-looking [removed: Statements](#sF07B5BA59A40359BC34CF8B9D9C84E97)] [added: Statements](#sCE18FD98D940A0986B086ABA74F3A70F)] | | | | | | [removed: [4](#sF07B5BA59A40359BC34CF8B9D9C84E97)] [added: [3](#sCE18FD98D940A0986B086ABA74F3A70F)] |
| [Website Access to [removed: Reports](#sD13AC4255BFDB4FBBF72F8B9D9E91AE1)] [added: Reports](#s9664EB943D6FAEB3312E6ABA75152244)] | | | | | | [removed: [5](#sD13AC4255BFDB4FBBF72F8B9D9E91AE1)] [added: [4](#s9664EB943D6FAEB3312E6ABA75152244)] |
| [Part [removed: I.](#sE89C41D42DEDF544CF8EF8B9DA1BD7E5)] [added: I.](#s968F74BF6345451DF6066ABA754664F8)] | [Item 1. [removed: Business](#s59264F187085D80F4F68F8B9DA3DA36A)] [added: Business](#sB4C2792B356268D668C36ABA75680FA1)] | | | | | [removed: [5](#s59264F187085D80F4F68F8B9DA3DA36A)] [added: [5](#sB4C2792B356268D668C36ABA75680FA1)] |
| | | [Electric Utility [removed: Operations](#s684CD8826B9E0716E43BF8B9CA2EE56F)] [added: Operations](#s0A9B95D04A0DDDEE56106ABA509F1776)] | | | | [removed: [10](#s684CD8826B9E0716E43BF8B9CA2EE56F)] [added: [9](#s0A9B95D04A0DDDEE56106ABA509F1776)] |
| | | [Gas Utility [removed: Operations](#s1164EDB4697973918A88F8B9CC27703B)] [added: Operations](#sE5D17FE7E8672AD71C936ABA5EF8DA68)] | | | | [removed: [20](#s1164EDB4697973918A88F8B9CC27703B)] [added: [19](#sE5D17FE7E8672AD71C936ABA5EF8DA68)] |
| | | [Other Utility Operations - [removed: Steam](#s28C28FD02904BC80E681F8B9DCD84ED6)] [added: Steam](#s2E315BD670E0A34F82026ABA780208B5)] | | | | [removed: [23](#s28C28FD02904BC80E681F8B9DCD84ED6)] [added: [22](#s2E315BD670E0A34F82026ABA780208B5)] |
| | | [Non-regulated [removed: Operations](#sC181B87C2B5E0A965EEDF8B9DD0940B7)] [added: Operations](#sAEA261FE173C3DBEB53E6ABA7834C525)] | | | | [removed: [23](#sC181B87C2B5E0A965EEDF8B9DD0940B7)] [added: [22](#sAEA261FE173C3DBEB53E6ABA7834C525)] |
| | [Item 1A. Risk [removed: Factors](#s1B47635654DED2B3FB1EF8B9DD2AAEC9)] [added: Factors](#s11D4876801DEF982224C6ABA785572C6)] | | | | | [removed: [23](#s1B47635654DED2B3FB1EF8B9DD2AAEC9)] [added: [22](#s11D4876801DEF982224C6ABA785572C6)] |
| | [Item 1B. Unresolved Staff [removed: Comments](#s21C66E2ABD8653746B84F8B9DD5C2BB5)] [added: Comments](#s698048B74F68F1154AA56ABA7885C95F)] | | | | | [removed: [29](#s21C66E2ABD8653746B84F8B9DD5C2BB5)] [added: [29](#s698048B74F68F1154AA56ABA7885C95F)] |
| | [Item 2. [removed: Properties](#sE40BF006937917CA3615F8B9CADB9FDD)] [added: Properties](#s4C687D89ADD7C1A852386ABA4FA7ADC9)] | | | | | [removed: [30](#sE40BF006937917CA3615F8B9CADB9FDD)] [added: [30](#s4C687D89ADD7C1A852386ABA4FA7ADC9)] |
| | [Item 3. Legal [removed: Proceedings](#s97EF9AF02CE4AFB85728F8B9DDB08B07)] [added: Proceedings](#sA1372EEBA09FB867F8756ABA78D829F5)] | | | | | [removed: [32](#s97EF9AF02CE4AFB85728F8B9DDB08B07)] [added: [32](#sA1372EEBA09FB867F8756ABA78D829F5)] |
| | [Item 4. Mine Safety [removed: Disclosures](#s9AB26A36385E304CCE0AF8B9DDD1E9F7)] [added: Disclosures](#s0B4E7088EAEDCA8B34F46ABA78FAB2D7)] | | | | | [removed: [33](#s9AB26A36385E304CCE0AF8B9DDD1E9F7)] [added: [32](#s0B4E7088EAEDCA8B34F46ABA78FAB2D7)] |
| | [Executive Officers of the [removed: Registrants](#s245FC04BD0E9D5704487F8B9DE037E68)] [added: Registrants](#s4B2D5A37A900B1025FB96ABA792EDD79)] | | | | | [removed: [33](#s245FC04BD0E9D5704487F8B9DE037E68)] [added: [33](#s4B2D5A37A900B1025FB96ABA792EDD79)] |
| [Part [removed: II.](#s2B3D6E274D42D87C1046F8B9DE2466B5)] [added: II.](#sD18086D30523FA8E96836ABA794D7031)] | [Item 5. Market for Registrants’ Common Equity, Related Stockholder Matters and Issuer Purchases of Equity [removed: Securities](#sF5E7E9827C6985550934F8B9D0D13A03)] [added: Securities](#sBF9F2129210919D5F4DE6ABA5F805E1C)] | | | | | [removed: [34](#sF5E7E9827C6985550934F8B9D0D13A03)] [added: [34](#sBF9F2129210919D5F4DE6ABA5F805E1C)] |
| | [Item 6. Selected Financial [removed: Data](#s2D03C083DD48DFABC9E8F8B9DE78278F)] [added: Data](#s630C069628682FD1030A6ABA79A27433)] | | | | | [removed: [35](#s2D03C083DD48DFABC9E8F8B9DE78278F)] [added: [35](#s630C069628682FD1030A6ABA79A27433)] |
| | [Item 7. Management’s Discussion and Analysis of Financial Condition and Results of [removed: Operations](#sF1D9994EBFFBD70CBF15F8B9DF1EA4D5)] [added: Operations](#s87CFCE52FC0812A4A7F86ABA7A492ED6)] | | | | | [removed: [36](#sF1D9994EBFFBD70CBF15F8B9DF1EA4D5)] [added: [36](#s87CFCE52FC0812A4A7F86ABA7A492ED6)] |
| | | [Executive [removed: Summary](#sDE1CF235278FB89AD754F8B9D2563DE3)] [added: Summary](#sD7EB98B62CCBC7F32A2D6ABA516E50DB)] | | | | [removed: [37](#sDE1CF235278FB89AD754F8B9D2563DE3)] [added: [37](#sD7EB98B62CCBC7F32A2D6ABA516E50DB)] |
| | | [Strategic [removed: Overview](#s2C54611047F2696E7B5FF8B9C951ACE9)] [added: Overview](#s06C4F7DE4D3FFCA8A1BD6ABA7ACD6C39)] | | | | [removed: [41](#s2C54611047F2696E7B5FF8B9C951ACE9)] [added: [40](#s06C4F7DE4D3FFCA8A1BD6ABA7ACD6C39)] |
| | | [Rate [removed: Matters](#sAC09DDB84E9D4F9EC770F8B9CFB3A73E)] [added: Matters](#sD5006DB81447ADFCF1446ABA4FA8C350)] | | | | [removed: [47](#sAC09DDB84E9D4F9EC770F8B9CFB3A73E)] [added: [46](#sD5006DB81447ADFCF1446ABA4FA8C350)] |
| | | [Environmental [removed: Matters](#s1F3659F1320C40F5693BF8B9DFF825D9)] [added: Matters](#sB59F5FC8BEF9DB683F956ABA7B22EDF5)] | | | | [removed: [52](#s1F3659F1320C40F5693BF8B9DFF825D9)] [added: [49](#sB59F5FC8BEF9DB683F956ABA7B22EDF5)] |
| | | [Legislative [removed: Matters](#s86CEDAF82D88F5857127F8B9E0193EF7)] [added: Matters](#s27D9D5872E31E6911B326ABA7B43B0C2)] | | | | [removed: [57](#s86CEDAF82D88F5857127F8B9E0193EF7)] [added: [54](#s27D9D5872E31E6911B326ABA7B43B0C2)] |
| | | [Alliant Energy’s Results of [removed: Operations](#s6E72AFA4BFBD6ABD126DF8B9CA2B5522)] [added: Operations](#s6E35C038326B990186856ABA5033D4B3)] | | | | [removed: [58](#s6E72AFA4BFBD6ABD126DF8B9CA2B5522)] [added: [54](#s6E35C038326B990186856ABA5033D4B3)] |
| | | [IPL’s Results of [removed: Operations](#s5FF8C440E4B4753BC29CF8B9C9B0B466)] [added: Operations](#s718964D057811BAEF8E46ABA4EFF2CDB)] | | | | [removed: [65](#s5FF8C440E4B4753BC29CF8B9C9B0B466)] [added: [62](#s718964D057811BAEF8E46ABA4EFF2CDB)] |
| | | [WPL’s Results of [removed: Operations](#s17F48D4E56963EC5DF93F8B9C9E51FC7)] [added: Operations](#s109645F7393F827B840A6ABA4F826955)] | | | | [removed: [68](#s17F48D4E56963EC5DF93F8B9C9E51FC7)] [added: [64](#s109645F7393F827B840A6ABA4F826955)] |
| | | [Liquidity and Capital [removed: Resources](#s347182CA2CD1EEDAF167F8B9CA32EBB3)] [added: Resources](#sC406469B25A3650B9C066ABA501F1587)] | | | | [removed: [71](#s347182CA2CD1EEDAF167F8B9CA32EBB3)] [added: [66](#sC406469B25A3650B9C066ABA501F1587)] |
| | | [Other [removed: Matters](#sE78B28F776F52BC6B5D4F8B9E12D5B00)] [added: Matters](#s04D0812DC404F3254EE16ABA7C44723C)] | | | | [removed: [81](#sE78B28F776F52BC6B5D4F8B9E12D5B00)] [added: [76](#s04D0812DC404F3254EE16ABA7C44723C)] |
| | | | [Market Risk Sensitive Instruments and [removed: Positions](#sA02ED73A59C9955B68F3F8B9E134FE5D)] [added: Positions](#sD74E79C523565D5D95EA6ABA7C4B5BCF)] | | | [removed: [81](#sA02ED73A59C9955B68F3F8B9E134FE5D)] [added: [76](#sD74E79C523565D5D95EA6ABA7C4B5BCF)] |
| | | | [Critical Accounting Policies and [removed: Estimates](#s17BD8D4E550B5F20ACC6F8B9D1FC1116)] [added: Estimates](#s73A57CEFC8C2F23E47206ABA6D9EE507)] | | | [removed: [82](#s17BD8D4E550B5F20ACC6F8B9D1FC1116)] [added: [77](#s73A57CEFC8C2F23E47206ABA6D9EE507)] |
| | | | [Other Future [removed: Considerations](#s7F8D069BA2FDF5911C76F8B9C9E026A7)] [added: Considerations](#s2DB6159B9E91221797116ABA7C8E9DD7)] | | | [removed: [85](#s7F8D069BA2FDF5911C76F8B9C9E026A7)] [added: [80](#s2DB6159B9E91221797116ABA7C8E9DD7)] |
| | [Item 7A. Quantitative and Qualitative Disclosures About Market [removed: Risk](#sFECB0A9A77CBBDE81298F8B9E19976A9)] [added: Risk](#s53B2DD704F9DDE6101FD6ABA7CC18A43)] | | | | | [removed: [88](#sFECB0A9A77CBBDE81298F8B9E19976A9)] [added: [82](#s53B2DD704F9DDE6101FD6ABA7CC18A43)] |
| | [Item 8. Financial Statements and Supplementary [removed: Data](#s9817C8F3C608E919A2AEF8B9E1BB8ABF)] [added: Data](#sB47AC4C8A418965286766ABA7CE32D72)] | | | | | [removed: [89](#s9817C8F3C608E919A2AEF8B9E1BB8ABF)] [added: [83](#sB47AC4C8A418965286766ABA7CE32D72)] |
| | | [Alliant Energy [removed: Corporation:](#s53DDED65E095B35148C4F8B9E1EC6CD4)] [added: Corporation:](#sAC4E4F6CA70A77E3B6E56ABA7D1433FD)] | | | | |
| | | | [Management’s Annual Report on Internal Control over Financial [removed: Reporting](#sEDF7819C419DB634547CF8B9E20DBA9A)] [added: Reporting](#s36ACBECA1941413417D26ABA7D37CC5C)] | | | [removed: [89](#sEDF7819C419DB634547CF8B9E20DBA9A)] [added: [83](#s36ACBECA1941413417D26ABA7D37CC5C)] |
| | | | [Reports of Independent Registered Public Accounting [removed: Firm](#s235BA7E9FF823A340CC9F8B9E23FAC1E)] [added: Firm](#sF28D61AFCAF277700F9D6ABA7D69334D)] | | | [removed: [90](#s235BA7E9FF823A340CC9F8B9E23FAC1E)] [added: [84](#sF28D61AFCAF277700F9D6ABA7D69334D)] |
10-K 1 lnt1231201410-k.htm 10-K
| [Definitions](#s332BAE161B4FD778645A6ABA74BEAD2A) | | | | | | [1](#s332BAE161B4FD778645A6ABA74BEAD2A) |
| | | [General](#sF5E3FA7514A37FD3F9AC6ABA7598E72F) | | | | [5](#sF5E3FA7514A37FD3F9AC6ABA7598E72F) |
| | | [Employees](#sD5A956414B928589EBA86ABA6D7F9CD3) | | | | [5](#sD5A956414B928589EBA86ABA6D7F9CD3) |
| | | [Regulation](#sCC326C77F41C9C2005636ABA763E8EAC) | | | | [6](#sCC326C77F41C9C2005636ABA763E8EAC) |
| | | | [New Accounting Pronouncements](#saef3af7a7a3a402d967cb506cb3de33b) | | | [76](#saef3af7a7a3a402d967cb506cb3de33b) |
| | | | [Consolidated Statements of Equity](#sA1E0E1A640206E6B4A866ABA359F890C) | | | [104](#sA1E0E1A640206E6B4A866ABA359F890C) |
| | | | [2. Regulatory Matters](#sF838B7F50B08CD3FF0096ABA34EDDF7E) | | | [112](#sF838B7F50B08CD3FF0096ABA34EDDF7E) |
| | | | [5. Receivables](#sE0A7670FAAD6235B17F86ABA3B924155) | | | [121](#sE0A7670FAAD6235B17F86ABA3B924155) |
| | | | [6. Investments](#sAB6E0566AA3A4C91759B6ABA36939A81) | | | [123](#sAB6E0566AA3A4C91759B6ABA36939A81) |
| | | | [7. Common Equity](#s91D9D0E077361FB7D53D6ABA3545800B) | | | [124](#s91D9D0E077361FB7D53D6ABA3545800B) |
| | | | [9. Debt](#s4BF590FC5D21D12C73996ABA3CBCBF63) | | | [126](#s4BF590FC5D21D12C73996ABA3CBCBF63) |
| | | | [10. Leases](#sAC5F85DA3EFCBB4492436ABA3DFA048D) | | | [128](#sAC5F85DA3EFCBB4492436ABA3DFA048D) |
| [Signatures](#s6DCB4DA0E3870C6A2B056ABA91447636) | | | | | | [171](#s6DCB4DA0E3870C6A2B056ABA91447636) |
| Bent Tree | Bent Tree - Phase I wind project |
| FASB | Financial Accounting Standards Board |
| Financial Statements | Consolidated Financial Statements |
| FTIP Act | Federal Tax Increase Prevention Act |
| Jo-Carroll | Jo-Carroll Energy, Inc. |
| N.A. | National Association |
| Note(s) | Combined Notes to Consolidated Financial Statements |
| OPEB | Other postretirement benefits |
| • | the impact of IPL’s retail electric base rate freeze in Iowa during 2015 and 2016; |
| • | issues related to the availability and operations of EGUs, including start-up risks, breakdown or failure of equipment, performance below expected or contracted levels of output or efficiency, operator error, transmission constraints, compliance with mandatory reliability standards and risks related to recovery of resulting incremental costs through rates; |
| • | disruptions in the supply and delivery of coal, natural gas and purchased electricity; |
| • | the direct or indirect effects resulting from breakdown or failure of equipment in the operation of natural gas distribution systems, such as leaks, explosions and mechanical problems, and compliance with natural gas distribution safety regulations, such as those that may be issued by the Pipeline and Hazardous Materials Safety Administration; |
| • | risks associated with deployment and integration of a new customer billing and information system expected in 2015; |
| • | changes made by FERC to ATC’s authorized return on equity; |
| • | changes in technology that alter the channels through which electric customers buy or utilize power; |
10-K 1 lnt1231201310-k.htm 10-K
| [Definitions](#s6faef7f5fb8249868df5a1f300b3aced) | | | | | | [1](#s6faef7f5fb8249868df5a1f300b3aced) |
| | | [General](#s72BD6659F75B08EBF7C9F8B9DA6EE462) | | | | [5](#s72BD6659F75B08EBF7C9F8B9DA6EE462) |
| | | [Employees](#s1A65C0DCC0A5126BAB2FF8B9CDC073CC) | | | | [6](#s1A65C0DCC0A5126BAB2FF8B9CDC073CC) |
| | | [Regulation](#sE860E139C3D4C28B7923F8B9DB15077F) | | | | [6](#sE860E139C3D4C28B7923F8B9DB15077F) |
| | | | [Consolidated Statements of Common Equity](#sCF9EEF4825019B1166D2F8B9A63D7D80) | | | [110](#sCF9EEF4825019B1166D2F8B9A63D7D80) |
| | | | [2. Regulatory Matters](#s6616DE41780DA3A1E8C1F8B9A7AAC6D8) | | | [118](#s6616DE41780DA3A1E8C1F8B9A7AAC6D8) |
| | | | [5. Receivables](#s4A3E30698E74B0C6A313F8B9A802663D) | | | [127](#s4A3E30698E74B0C6A313F8B9A802663D) |
| | | | [6. Investments](#s3E5931D9325ABC1E8ACCF8B9B50B1C06) | | | [129](#s3E5931D9325ABC1E8ACCF8B9B50B1C06) |
| | | | [7. Common Equity](#s44A583C9241813863649F8B9B3F01A3E) | | | [130](#s44A583C9241813863649F8B9B3F01A3E) |
| | | | [9. Debt](#sD4479A7E4CEEAF94ABA7F8B9B4604260) | | | [132](#sD4479A7E4CEEAF94ABA7F8B9B4604260) |
| | | | [10. Leases](#s65D70D1BAF3F24BB4D48F8B9A7CCBD13) | | | [134](#s65D70D1BAF3F24BB4D48F8B9A7CCBD13) |
| [Signatures](#sE42912CE209FF702BFAFF8B9F65F2952) | | | | | | [179](#sE42912CE209FF702BFAFF8B9F65F2952) |
| Abbreviation or Acronym | Definition |
| Act 32 | 2011 Wisconsin Act 32 |
| ATR Act | American Taxpayer Relief Act of 2012 |
| BL | Base load units |
| DATC | Duke-American Transmission Co. |
| Eagle Point | Eagle Point Solar |
| ERISA | Employee Retirement Income Security Act of 1974 |
| ERO | Electric Reliability Organization |
| IEA | Industrial Energy Applications, Inc. |
| IN | Intermediate units |
| IPO | Initial public offering |
| LRZ | Local resource zone |
| MidAmerican | MidAmerican Energy Company |
| MRO | Midwest Reliability Organization |
| NER | NextEra Energy Resources, LLC |
| NERC | North American Electric Reliability Corporation |
| NOV | Notice of violation |
| NRB | Natural Resources Board |
| NSPS | New Source Performance Standards |
| NYSE | New York Stock Exchange |
| OCA | Iowa Office of Consumer Advocate |
| PK | Peaking units |
| PM2.5 | Fine particulate matter |
| PRM | Planning reserve margin |
| PUHCA | Public Utility Holding Company Act of 2005 |
| RTO | Regional Transmission Organization |
| Sheboygan Power | Sheboygan Power, LLC |
An excerpt. Shown here: 40 of 104 rewritten, all 29 added and 40 of 44 removed. The counts are complete. For every sentence, read Cover and table of contents in the FY2014 filing and the FY2013 filing.
Item 2. PROPERTIES
65 rewritten, 6 added, 6 removed, 16 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Electric - At December 31, [removed: 2013,] [added: 2014,] IPL’s EGUs by primary fuel type were as follows:
| Ottumwa Generating Station (Unit 1) (c) | | Ottumwa, IA | | 1981 | | BL | | 348 | | | [removed: 309] [added: 316] | |
| Lansing Generating Station (Unit 4) | | Lansing, IA | | 1977 | | BL | | 275 | | | [removed: 230] [added: 247] | |
| M.L. Kapp Generating Station (Unit 2) (d) | | Clinton, IA | | 1967 | | BL | | 218 | | | [removed: 177] [added: 195] | |
| Burlington Generating Station (Unit 1) | | Burlington, IA | | 1968 | | BL | | 212 | | | [removed: 177] [added: 194] | |
| George Neal Generating Station (Unit 4) (e) | | Sioux City, IA | | 1979 | | BL | | [removed: 165] [added: 179] | | | [removed: 160] [added: 159] | |
| George Neal Generating Station (Unit 3) (f) | | Sioux City, IA | | 1975 | | BL | | [removed: 154] [added: 164] | | | [removed: 136] [added: 134] | |
| Prairie Creek Generating Station (Units 1,3,4) | | Cedar Rapids, IA | | 1958-1997 | | BL | | 213 | | | [removed: 126] [added: 142] | |
| Emery Generating Station (Units 1-3) | | Mason City, IA | | 2004 | | IN | | 603 | | | [removed: 494] [added: 499] | |
| Fox Lake Generating Station (Units 1,3) (d) | | Sherburn, MN | | 1950-1962 | | IN | | 93 | | | [removed: 82] [added: 83] | |
| Sutherland Generating Station (Units 1,3) (d) | | Marshalltown, IA | | 1955-1961 | | IN | | 119 | | | [removed: 79] [added: 84] | |
| Dubuque Generating Station (Units 3-4) (d) | | Dubuque, IA | | 1952-1959 | | IN | | 66 | | | [removed: 58] [added: 59] | |
| Burlington Combustion Turbines (Units 1-4) (d) | | Burlington, IA | | 1994-1996 | | PK | | 79 | | | [removed: 58] [added: 60] | |
| Grinnell Combustion Turbines (Units 1-2) (d) | | Grinnell, IA | | 1990-1991 | | PK | | 48 | | | [removed: 44] [added: 38] | |
| Red Cedar Combustion Turbine (Unit 1) | | Cedar Rapids, IA | | 1996 | | PK | | 23 | | | [removed: 11] [added: 6] | |
| Total Gas | | | | | | | | 1,031 | | | [removed: 826] [added: 829] | |
| Marshalltown Combustion Turbines (Units 1-3) | | Marshalltown, IA | | 1978 | | PK | | 189 | | | [removed: 143] [added: 140] | |
| Lime Creek Combustion Turbines (Units 1-2) | | Mason City, IA | | 1991 | | PK | | 90 | | | [removed: 56] [added: 60] | |
| Centerville Combustion Turbines (Units 1-2) (d) | | Centerville, IA | | 1990 | | PK | | 54 | | | [removed: 29] [added: 45] | |
| Diesel Stations [removed: (9] [added: (7] Units) (d) | | Iowa and Minnesota | | 1963-1996 | | PK | | [removed: 16] [added: 14] | | | [removed: 11] [added: 8] | |
| (a) | [removed: BL] [added: Base load EGUs (BL)] are designed for nearly continuous operation at or near full capacity to provide the system base load. [removed: IN] [added: Intermediate EGUs (IN)] follow system load changes with frequent starts and curtailments of output during low demand. [removed: PK] [added: Peak load EGUs (PK)] are generally low efficiency, quick response units that run primarily when there is high demand. |
| (b) | Based on the [added: accredited] generating capacity of the EGUs included in MISO’s resource adequacy process for the planning period from June [removed: 2013] [added: 2014] through May [removed: 2014.] [added: 2015.] |
| (c) | Represents IPL’s 48% ownership interest in this 726 MW (nameplate capacity) / [removed: 644] [added: 659] MW (generating capacity) EGU, which is operated by IPL. |
| (d) | Refer to “[Strategic [removed: Overview](#s2C54611047F2696E7B5FF8B9C951ACE9)”] [added: Overview](#s06C4F7DE4D3FFCA8A1BD6ABA7ACD6C39)”] in MDA for discussion of EGUs that may be retired or changed from coal-fired to an alternative fuel source in the next few years. |
| (e) | Represents IPL’s 25.695% ownership interest in this [removed: 641] [added: 696] MW (nameplate capacity) / [removed: 623] [added: 620] MW (generating capacity) EGU, which is operated by [removed: MidAmerican.] [added: MidAmerican Energy Company.] |
| (f) | Represents IPL’s 28% ownership interest in this [removed: 550] [added: 584] MW (nameplate capacity) / [removed: 486] [added: 479] MW (generating capacity) EGU, which is operated by [removed: MidAmerican.] [added: MidAmerican Energy Company.] |
| (g) | Represents IPL’s 4% ownership interest in this [removed: 810] [added: 812] MW (nameplate capacity) / [removed: 725] [added: 728] MW (generating capacity) EGU, which is operated by [removed: MidAmerican.] [added: MidAmerican Energy Company.] |
| (h) | Generating capacity represents 0% of the capacity of this wind project based upon the MISO resource adequacy process, which is determined separately for each wind site, during the planning period from June [removed: 2013] [added: 2014] through May [removed: 2014.] [added: 2015.] The 0% allocation resulted from the lack of firm transmission at this wind site during the planning period from June [removed: 2013] [added: 2014] through May [removed: 2014.] [added: 2015.] |
At December 31, [removed: 2013,] [added: 2014,] IPL owned approximately [removed: 19,696] [added: 19,642] miles of overhead electric distribution line and [removed: 2,843] [added: 2,961] miles of underground electric distribution cable, as well as [removed: 714] [added: 696] substation distribution transformers, substantially all of which are located in Iowa and Minnesota.
Gas - IPL’s gas properties consist primarily of mains and services, meters, regulating and gate stations and other related [added: transmission and] distribution equipment.
At December 31, [removed: 2013,] [added: 2014,] IPL’s gas distribution facilities included approximately [removed: 5,051] [added: 5,088] miles and [removed: 238] [added: 237] miles of gas mains located in Iowa and Minnesota, respectively.
Other - IPL’s other property [removed: included in “Property, plant and equipment - Other” on its Consolidated Balance Sheets] consists primarily of steam service assets, operating and storeroom facilities, vehicles, computer hardware and software, communication equipment and other miscellaneous tools and equipment.
Electric - At December 31, [removed: 2013,] [added: 2014,] WPL’s EGUs by primary fuel type were as follows:
| Columbia Energy Center (Units 1-2) (c) | | Portage, WI | | 1975-1978 | | BL | | [removed: 473] [added: 514] | | | [removed: 504] [added: 494] | |
| Edgewater Generating Station (Unit 5) | | Sheboygan, WI | | 1985 | | BL | | [removed: 380] [added: 414] | | | [removed: 402] [added: 406] | |
| Edgewater Generating Station (Unit 4) (d) (e) | | Sheboygan, WI | | 1969 | | BL | | [removed: 225] [added: 239] | | | [removed: 211] [added: 199] | |
| Nelson Dewey Generating Station (Units 1-2) (e) | | Cassville, WI | | 1959-1962 | | BL | | [removed: 200] [added: 227] | | | [removed: 207] [added: 202] | |
| Edgewater Generating Station (Unit 3) (e) | | Sheboygan, WI | | 1951 | | IN | | [removed: 60] [added: 69] | | | [removed: 54] [added: 69] | |
| Riverside Energy Center (Units 1-3) [removed: (f)] | | Beloit, WI | | 2004 | | IN | | 675 | | | [removed: 568] [added: 545] | |
| Neenah Energy Facility (Units 1-2) | | Neenah, WI | | 2000 | | PK | | 371 | | | [removed: 279] [added: 281] | |
| Total Coal | | | | | | | | 1,641 | | | 1,416 | |
| Total Oil | | | | | | | | 347 | | | 253 | |
| Total capacity | | | | | | | | 3,219 | | | 2,498 | |
| Total Coal | | | | | | | | 1,463 | | | 1,370 | |
| Total capacity | | | | | | | | 3,221 | | | 2,488 | |
Corporate Services is also implementing a new customer billing and information system for IPL and WPL, which is currently expected to be deployed in 2015.
| Total Coal | | | | | | | | 1,617 | | | 1,344 | |
| Total Oil | | | | | | | | 349 | | | 239 | |
| Total generating capacity | | | | | | | | 3,197 | | | 2,409 | |
| Total Coal | | | | | | | | 1,338 | | | 1,378 | |
| Total generating capacity | | | | | | | | 3,096 | | | 2,514 | |
| (f) | WPL was credited 568 MW of generating capacity for this EGU for the planning period from June 2013 through May 2014. WPL is utilizing 468 MW of the accredited generating capacity from Riverside to satisfy its PRM requirements and has sold 100 MW of the accredited capacity to a third party with a PPA through May 2014. |
An excerpt. Shown here: 40 of 65 rewritten, all 6 added and all 6 removed. The counts are complete. For every sentence, read Item 2. PROPERTIES in the FY2014 filing and the FY2013 filing.
Item 4. MINE SAFETY DISCLOSURES
23 rewritten, 0 added, 10 removed, 28 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Kampling, [removed: 54,] [added: 55,] has served as a director since January 2012, and as Chairman of the Board, President and CEO since April 2012.
She previously served as President and Chief Operating Officer since February 2011, as EVP and CFO from September 2010 to February 2011, [added: and] as EVP-CFO and Treasurer from January 2010 to September [removed: 2010, and as VP-CFO and Treasurer from January 2009 to January] 2010.
[removed: Aller, 64,] [added: Larsen, 51,] was elected Senior VP effective February 2014.
Gallegos, [removed: 53,] [added: 54,] was elected Senior [removed: VP and] [added: VP,] General Counsel [added: and Corporate Secretary] effective February [removed: 2014.][added: 2015.]
He previously served as [added: Senior] VP and General Counsel since [added: February 2014, as VP and General Counsel from] November [removed: 2010,] [added: 2010 to February 2014,] and as VP and Corporate General Counsel of BNSF Railway Company, a subsidiary of Burlington Northern and Santa Fe Corporation, from April 2003 to April 2010.
Hanson, [removed: 60,] [added: 61,] was elected Senior VP and CFO effective January 2013.
Kopp, [removed: 60,] [added: 61,] was elected Senior VP effective March 2014.
He previously served as VP-Environmental Affairs since January 2013, as Director-Environmental Affairs from January 2011 to January 2013, as Plant Manager of the Prairie Creek Generating Station from September 2010 to January 2011, [added: and] as Plant Manager of the Sutherland Generating Station from May 2009 to September [removed: 2010 and as Plant Manager of the Sixth Street Generating Station from July 2006 to May 2009.][added: 2010.]
Larsen, [removed: 50,] [added: 51,] was elected Senior VP effective February 2014.
He previously served as Senior VP-Generation since January [removed: 2010 and as VP-Generation from August 2008 to January] 2010.
Durian, [removed: 43,] [added: 44,] was elected Controller and CAO effective February 2011.
He previously served as Controller since September 2010, [added: and] as Assistant Controller from March 2009 to September [removed: 2010 and as Director of Financial Reporting from February 2006 to March 2009.][added: 2010.]
Kampling, [removed: 54,] [added: 55,] has served as a director since January 2012, and as Chairman of the Board and CEO since April 2012.
[removed: Aller, 64,] [added: Larsen, 51,] was elected President effective [removed: January 2004.][added: December 2010.]
Kopp, [removed: 60,] [added: 61,] was elected Senior VP effective March 2014 and President effective April 2014.
Gallegos, [removed: 53,] [added: 54,] was elected Senior [removed: VP and] [added: VP,] General Counsel [added: and Corporate Secretary] effective February [removed: 2014.][added: 2015.]
Hanson, [removed: 60,] [added: 61,] was elected Senior VP and CFO effective January 2013.
[removed: Larsen, 50,] [added: Kopp, 61,] was elected Senior VP effective [removed: February] [added: March] 2014.
Durian, [removed: 43,] [added: 44,] was elected Controller and CAO effective February 2011.
Kampling, [removed: 54,] [added: 55,] has served as a director since January 2012, and as Chairman of the Board and CEO since April 2012.
Gallegos, [removed: 53,] [added: 54,] was elected Senior [removed: VP and] [added: VP,] General Counsel [added: and Corporate Secretary] effective February [removed: 2014.][added: 2015.]
Hanson, [removed: 60,] [added: 61,] was elected Senior VP and CFO effective January 2013.
Durian, [removed: 43,] [added: 44,] was elected Controller and CAO effective February 2011.
Thomas L.
He previously served as Senior VP-Operations Support since January 2013 and as Senior VP-Energy Resource Development from January 2009 to January 2013.
Mr. Aller announced his intent to retire effective March 31, 2014.
Thomas L.
Thomas L.
Mr. Aller announced his intent to retire effective March 31, 2014.
Larsen, 50, was elected President effective December 2010.
Aller, 64, was elected Senior VP effective February 2014.
Mr. Aller announced his intent to retire effective March 31, 2014.
Kopp, 60, was elected Senior VP effective March 2014.
Item 5. MARKET FOR REGISTRANTS’ COMMON EQUITY, RELATED STOCKHOLDER MATTERS AND ISSUER PURCHASES OF EQUITY SECURITIES
12 rewritten, 5 added, 5 removed, 9 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Stock Price - Alliant Energy’s common stock trades on the [removed: NYSE] [added: New York Stock Exchange] under the symbol “LNT.” Quarterly sales price ranges and dividends with respect to Alliant Energy’s common stock were as follows:
| First | | | [removed: $50.23] [added: $56.99] | | | | [removed: $43.73] [added: $50.00] | | | | [removed: $0.47] [added: $0.51] | | | | [removed: $44.57] [added: $50.23] | | | | [removed: $41.86] [added: $43.73] | | | | [removed: $0.45] [added: $0.47] | |
| Second | | [removed: 53.52] [added: 60.88] | | | | [removed: 46.79] [added: 55.47] | | | | [removed: 0.47] [added: 0.51] | | | | [removed: 46.00] [added: 53.52] | | | | [removed: 42.00] [added: 46.79] | | | | [removed: 0.45] [added: 0.47] | | |
| Third | | [removed: 54.18] [added: 60.89] | | | | [removed: 48.17] [added: 54.69] | | | | [removed: 0.47] [added: 0.51] | | | | [removed: 47.65] [added: 54.18] | | | | [removed: 42.95] [added: 48.17] | | | | [removed: 0.45] [added: 0.47] | | |
| Fourth | | [removed: 53.69] [added: 69.78] | | | | [removed: 48.83] [added: 55.38] | | | | [removed: 0.47] [added: 0.51] | | | | [removed: 45.66] [added: 53.69] | | | | [removed: 42.21] [added: 48.83] | | | | [removed: 0.45] [added: 0.47] | | |
| Year | | [removed: 54.18] [added: 69.78] | | | | [removed: 43.73] [added: 50.00] | | | | [removed: 1.88] [added: 2.04] | | | | [removed: 47.65] [added: 54.18] | | | | [removed: 41.86] [added: 43.73] | | | | [removed: 1.80] [added: 1.88] | | |
Stock closing price at December 31, [removed: 2013: $51.60][added: 2014: $66.42]
Shareowners - At December 31, [removed: 2013,] [added: 2014,] there were [removed: 30,873] [added: 29,493] holders of record of Alliant Energy’s common stock, including holders through Alliant Energy’s Shareowner Direct Plan.
Dividends - In November [removed: 2013,] [added: 2014,] Alliant Energy announced an increase in its targeted [removed: 2014] [added: 2015] annual common stock dividend to [removed: $2.04] [added: $2.20] per share, which is equivalent to a quarterly rate of [removed: $0.51] [added: $0.55] per share, beginning with the February [removed: 2014] [added: 2015] dividend payment.
Refer to [Note [removed: 7](#s44A583C9241813863649F8B9B3F01A3E) of the “Combined Notes to Consolidated Financial Statements”] [added: 7](#s91D9D0E077361FB7D53D6ABA3545800B)] for information about IPL’s and WPL’s dividend restrictions and limitations on distributions to their parent company.
Common Stock Repurchases - A summary of Alliant Energy common stock repurchases for the quarter ended December 31, [removed: 2013] [added: 2014] was as follows:
Other - Refer to “[Security Ownership of Certain Beneficial Owners and Management and Related Stockholder [removed: Matters](#s3537F59E3AF604F08EB7F8B9F521C224)”] [added: Matters](#s594453E5DAA7B862E7C16ABA8FF8BACD)”] in Item 12 for details of securities authorized for issuance under equity compensation plans.
| | | 2014 | | | | | | | | | | | | 2013 | | | | | | | | | | |
| October 1 to October 31 | | 3,211 | | | | $56.36 | | | — | | N/A |
| November 1 to November 30 | | 2,036 | | | 61.80 | | | | — | | N/A |
| December 1 to December 31 | | 78 | | | 64.60 | | | | — | | N/A |
| | | 5,325 | | | 58.56 | | | | — | | |
| | | 2013 | | | | | | | | | | | | 2012 | | | | | | | | | | |
| October 1 to October 31 | | 2,966 | | | | $50.67 | | | — | | N/A |
| November 1 to November 30 | | 2,032 | | | 53.57 | | | | — | | N/A |
| December 1 to December 31 | | 56 | | | 52.16 | | | | — | | N/A |
| | | 5,054 | | | 51.85 | | | | — | | |
Item 6. SELECTED FINANCIAL DATA
44 rewritten, 0 added, 1 removed, 15 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
| Alliant Energy | [removed: 2013] [added: 2014] (a) | | | | [removed: 2012] [added: 2013] (a) | | | | [removed: 2011] [added: 2012] (a) | | | | [removed: 2010] [added: 2011] | | | | [removed: 2009 (b)] [added: 2010] | | |
| Operating revenues | | [removed: $3,276.8] [added: $3,350.3] | | | | [removed: $3,094.5] [added: $3,276.8] | | | | [removed: $3,221.4] [added: $3,094.5] | | | | [removed: $3,262.1] [added: $3,221.4] | | | | [removed: $3,133.2] [added: $3,262.1] | |
| Income from continuing operations, net of tax | [removed: 382.1] [added: 395.7] | | | | [removed: 340.8] [added: 382.1] | | | | [removed: 341.4] [added: 340.8] | | | | [removed: 310.2] [added: 341.4] | | | | [removed: 130.3] [added: 310.2] | | |
| Loss from discontinued operations, net of tax | [removed: (5.9] [added: (2.4] | | ) | | [removed: (5.1] [added: (5.9] | | ) | | [removed: (19.5] [added: (5.1] | | ) | | [removed: (3.9] [added: (19.5] | | ) | | [removed: (0.6] [added: (3.9] | | ) |
| Net income | [removed: 376.2] [added: 393.3] | | | | [removed: 335.7] [added: 376.2] | | | | [removed: 321.9] [added: 335.7] | | | | [removed: 306.3] [added: 321.9] | | | | [removed: 129.7] [added: 306.3] | | |
| Income from continuing operations, net of tax | [removed: 364.2] [added: 385.5] | | | | [removed: 324.9] [added: 364.2] | | | | [removed: 323.1] [added: 324.9] | | | | [removed: 291.5] [added: 323.1] | | | | [removed: 111.6] [added: 291.5] | | |
| Loss from discontinued operations, net of tax | [removed: (5.9] [added: (2.4] | | ) | | [removed: (5.1] [added: (5.9] | | ) | | [removed: (19.5] [added: (5.1] | | ) | | [removed: (3.9] [added: (19.5] | | ) | | [removed: (0.6] [added: (3.9] | | ) |
| Net income | [removed: 358.3] [added: 383.1] | | | | [removed: 319.8] [added: 358.3] | | | | [removed: 303.6] [added: 319.8] | | | | [removed: 287.6] [added: 303.6] | | | | [removed: 111.0] [added: 287.6] | | |
| Income from continuing operations, net of tax | | [removed: $3.29] [added: $3.48] | | | | [removed: $2.93] [added: $3.29] | | | | [removed: $2.92] [added: $2.93] | | | | [removed: $2.64] [added: $2.92] | | | | [removed: $1.01] [added: $2.64] | |
| Loss from discontinued operations, net of tax | | [removed: ($0.06] [added: ($0.02] | ) | | | [removed: ($0.04] [added: ($0.06] | ) | | | [removed: ($0.18] [added: ($0.04] | ) | | | [removed: ($0.04] [added: ($0.18] | ) | | | [removed: $—] [added: ($0.04] | [added: )] |
| Net income | | [removed: $3.23] [added: $3.46] | | | | [removed: $2.89] [added: $3.23] | | | | [removed: $2.74] [added: $2.89] | | | | [removed: $2.60] [added: $2.74] | | | | [removed: $1.01] [added: $2.60] | |
| Common shares outstanding at year-end (000s) | [removed: 110,944] [added: 110,936] | | | | [removed: 110,987] [added: 110,944] | | | | [removed: 111,019] [added: 110,987] | | | | [removed: 110,894] [added: 111,019] | | | | [removed: 110,656] [added: 110,894] | | |
| Dividends declared per common share | | [removed: $1.88] [added: $2.04] | | | | [removed: $1.80] [added: $1.88] | | | | [removed: $1.70] [added: $1.80] | | | | [removed: $1.58] [added: $1.70] | | | | [removed: $1.50] [added: $1.58] | |
| Market value per share at year-end | | [removed: $51.60] [added: $66.42] | | | | [removed: $43.91] [added: $51.60] | | | | [removed: $44.11] [added: $43.91] | | | | [removed: $36.77] [added: $44.11] | | | | [removed: $30.26] [added: $36.77] | |
| Book value per share at year-end | | [removed: $29.58] [added: $31.00] | | | | [removed: $28.25] [added: $29.58] | | | | [removed: $27.14] [added: $28.25] | | | | [removed: $26.09] [added: $27.14] | | | | [removed: $25.06] [added: $26.09] | |
| Market capitalization at year-end | | [removed: $5,724.7] [added: $7,368.4] | | | | [removed: $4,873.4] [added: $5,724.7] | | | | [removed: $4,897.0] [added: $4,873.4] | | | | [removed: $4,077.6] [added: $4,897.0] | | | | [removed: $3,348.5] [added: $4,077.6] | |
| Cash flows from operating activities | | [removed: $731.0] [added: $891.6] | | | | [removed: $841.1] [added: $731.0] | | | | [removed: $702.7] [added: $841.1] | | | | [removed: $984.9] [added: $702.7] | | | | [removed: $657.1] [added: $984.9] | |
| Construction and acquisition expenditures | | [removed: $798.3] [added: $902.8] | | | | [removed: $1,158.1] [added: $798.3] | | | | [removed: $673.4] [added: $1,158.1] | | | | [removed: $866.9] [added: $673.4] | | | | [removed: $1,202.6] [added: $866.9] | |
| Total assets at year-end | | [removed: $11,112.4] [added: $12,085.9] | | | | [removed: $10,785.5] [added: $11,112.4] | | | | [removed: $9,687.9] [added: $10,785.5] | | | | [removed: $9,282.9] [added: $9,687.9] | | | | [removed: $9,036.0] [added: $9,282.9] | |
| Long-term obligations, net | | [removed: $3,338.1] [added: $3,791.1] | | | | [removed: $3,141.5] [added: $3,338.1] | | | | [removed: $2,708.0] [added: $3,141.5] | | | | [removed: $2,710.3] [added: $2,708.0] | | | | [removed: $2,512.2] [added: $2,710.3] | |
| Times interest earned before income taxes [removed: (c)] [added: (b)] | [removed: 3.52X] [added: 3.44X] | | | | [removed: 3.75X] [added: 3.52X] | | | | [removed: 3.59X] [added: 3.75X] | | | | [removed: 3.81X] [added: 3.59X] | | | | [removed: 1.80X] [added: 3.81X] | | |
| Common equity | [removed: 46] [added: 45] | | % | | [removed: 47] [added: 46] | | % | | [removed: 50] [added: 47] | | % | | [removed: 49] [added: 50] | | % | | 49 | | % |
| Preferred stock of subsidiaries | 3 | | % | | 3 | | % | | 3 | | % | | [removed: 4] [added: 3] | | % | | 4 | | % |
| Long- and short-term debt | [removed: 51] [added: 52] | | % | | [removed: 50] [added: 51] | | % | | [removed: 47] [added: 50] | | % | | 47 | | % | | 47 | | % |
| (a) | Refer to “[Alliant Energy’s Results of [removed: Operations](#s6E72AFA4BFBD6ABD126DF8B9CA2B5522)”] [added: Operations](#s6E35C038326B990186856ABA5033D4B3)”] in MDA for discussion of the [removed: 2013, 2012] [added: 2014, 2013] and [removed: 2011] [added: 2012] results of operations. |
| [removed: (c)] [added: (b)] | Represents the sum of income from continuing operations before income taxes plus interest expense, divided by interest expense. [removed: The calculation does not consider the “Loss on early extinguishment of debt” that Alliant Energy has incurred as part of interest expense.] |
| IPL | [removed: 2013] [added: 2014] (a) | | | | [removed: 2012] [added: 2013] (a) | | | | [removed: 2011] [added: 2012] (a) | | | | [removed: 2010] [added: 2011] | | | | [removed: 2009] [added: 2010] | | |
| Operating revenues | | [removed: $1,818.8] [added: $1,848.1] | | | | [removed: $1,650.3] [added: $1,818.8] | | | | [removed: $1,740.1] [added: $1,650.3] | | | | [removed: $1,795.8] [added: $1,740.1] | | | | [removed: $1,708.0] [added: $1,795.8] | |
| Net income | [removed: 189.9] [added: 194.6] | | | | [removed: 150.2] [added: 189.9] | | | | [removed: 139.3] [added: 150.2] | | | | [removed: 143.4] [added: 139.3] | | | | [removed: 153.0] [added: 143.4] | | |
| Earnings available for common stock | [removed: 173.6] [added: 184.4] | | | | [removed: 137.6] [added: 173.6] | | | | [removed: 124.3] [added: 137.6] | | | | [removed: 128.0] [added: 124.3] | | | | [removed: 137.6] [added: 128.0] | | |
| Cash dividends declared on common stock | [removed: 128.1] [added: 140.0] | | | | [removed: 122.9] [added: 128.1] | | | | [removed: 73.4] [added: 122.9] | | | | [removed: —] [added: 73.4] | | | | — | | |
| Cash flows from operating activities | [removed: 232.6] [added: 406.1] | | | | [removed: 291.0] [added: 232.6] | | | | [removed: 366.9] [added: 291.0] | | | | [removed: 549.6] [added: 366.9] | | | | [removed: 373.2] [added: 549.6] | | |
| Total assets | [removed: 5,806.0] [added: 6,461.8] | | | | [removed: 5,457.0] [added: 5,806.0] | | | | [removed: 5,093.5] [added: 5,457.0] | | | | [removed: 4,937.6] [added: 5,093.5] | | | | [removed: 4,892.2] [added: 4,937.6] | | |
| Long-term obligations, net | [removed: 1,559.2] [added: 1,769.3] | | | | [removed: 1,361.7] [added: 1,559.2] | | | | [removed: 1,311.0] [added: 1,361.7] | | | | [removed: 1,310.6] [added: 1,311.0] | | | | [removed: 1,160.9] [added: 1,310.6] | | |
| (a) | Refer to “[IPL’s Results of [removed: Operations](#s5FF8C440E4B4753BC29CF8B9C9B0B466)”] [added: Operations](#s718964D057811BAEF8E46ABA4EFF2CDB)”] in MDA for a discussion of the [removed: 2013, 2012] [added: 2014, 2013] and [removed: 2011] [added: 2012] results of operations. |
| WPL | [removed: 2013] [added: 2014] (a) | | | | [removed: 2012] [added: 2013] (a) | | | | [removed: 2011] [added: 2012] (a) | | | | [removed: 2010] [added: 2011] | | | | [removed: 2009] [added: 2010] | | |
| Operating revenues | | [removed: $1,406.3] [added: $1,449.1] | | | | [removed: $1,392.0] [added: $1,406.3] | | | | [removed: $1,434.4] [added: $1,392.0] | | | | [removed: $1,423.6] [added: $1,434.4] | | | | [removed: $1,386.1] [added: $1,423.6] | |
| Net income | [removed: 177.5] [added: 180.8] | | | | [removed: 165.7] [added: 177.5] | | | | [removed: 163.5] [added: 165.7] | | | | [removed: 152.3] [added: 163.5] | | | | [removed: 89.5] [added: 152.3] | | |
| Earnings available for common stock | [removed: 175.9] [added: 180.1] | | | | [removed: 162.4] [added: 175.9] | | | | [removed: 160.2] [added: 162.4] | | | | [removed: 149.0] [added: 160.2] | | | | [removed: 86.2] [added: 149.0] | | |
| Cash dividends declared on common stock | [removed: 116.3] [added: 118.7] | | | | [removed: 112.0] [added: 116.3] | | | | [removed: 112.1] [added: 112.0] | | | | [removed: 109.5] [added: 112.1] | | | | [removed: 91.0] [added: 109.5] | | |
| (b) | In 2009, Alliant Energy incurred $203 million of pre-tax losses related to the repurchase of its 2.5% Exchangeable Senior Notes due 2030. |
An excerpt. Shown here: 40 of 44 rewritten, all 0 added and all 1 removed. The counts are complete. For every sentence, read Item 6. SELECTED FINANCIAL DATA in the FY2014 filing and the FY2013 filing.
Item 8. FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA
1,383 rewritten, 469 added, 570 removed, 940 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Alliant Energy’s management assessed the effectiveness of Alliant Energy’s internal control over financial reporting as of December 31, [removed: 2013] [added: 2014] using the criteria set forth in Internal Control - Integrated Framework [removed: (1992)] [added: (2013)] issued by the Committee of Sponsoring Organizations of the Treadway Commission.
Based on this assessment, Alliant Energy’s management concluded that, as of December 31, [removed: 2013,] [added: 2014,] Alliant Energy’s internal control over financial reporting was effective.
[removed: February 25, 2014][added: | 2014: | | | | | | | | | | | | | | | | | | | | | | | |]
We have audited the internal control over financial reporting of Alliant Energy Corporation and subsidiaries (the “Company”) as of December 31, [removed: 2013,] [added: 2014,] based on the criteria established in Internal Control - Integrated Framework [removed: (1992)] [added: (2013)] issued by the Committee of Sponsoring Organizations of the Treadway Commission.
In our opinion, the Company maintained, in all material respects, effective internal control over financial reporting as of December 31, [removed: 2013,] [added: 2014,] based on the criteria established in Internal Control - Integrated Framework [removed: (1992)] [added: (2013)] issued by the Committee of Sponsoring Organizations of the Treadway Commission.
We have also audited, in accordance with the standards of the Public Company Accounting Oversight Board (United States), the consolidated financial statements and financial statement schedules as of and for the year ended December 31, [removed: 2013] [added: 2014] of the Company and our report dated February [removed: 25, 2014] [added: 24, 2015] expressed an unqualified opinion on those financial statements and financial statement schedules.
[removed: February 25, 2014][added: | 2014: | | | | | | | | | | | | | | | |]
We have audited the accompanying consolidated balance sheets of Alliant Energy Corporation and subsidiaries (the “Company”) as of December 31, [removed: 2013] [added: 2014] and [removed: 2012,] [added: 2013,] and the related consolidated statements of income, common equity, and cash flows for each of the three years in the period ended December 31, [removed: 2013.][added: 2014.]
Our audits also included the [added: Company’s] financial statement schedules listed in the Index at Item 15.
In our opinion, such consolidated financial statements present fairly, in all material respects, the financial position of the Company as of December 31, [removed: 2013] [added: 2014] and [removed: 2012,] [added: 2013,] and the results of its operations and its cash flows for each of the three years in the period ended December 31, [removed: 2013,] [added: 2014,] in conformity with accounting principles generally accepted in the United States of America.
We have also audited, in accordance with the standards of the Public Company Accounting Oversight Board (United States), the Company’s internal control over financial reporting as of December 31, [removed: 2013,] [added: 2014,] based on the criteria established in Internal Control-Integrated Framework [removed: (1992)] [added: (2013)] issued by the Committee of Sponsoring Organizations of the Treadway Commission and our report dated February [removed: 25, 2014] [added: 24, 2015] expressed an unqualified opinion on the Company’s internal control over financial reporting.
[removed: February 25, 2014][added: | 2014: | | | | | | | | | | | | | | | | | | | |]
| | [removed: 2013] [added: 2014] | | | | [removed: 2012] [added: 2013] | | | | [removed: 2011] [added: 2012] | | |
| Electric | | [removed: $2,689.0] [added: $2,713.6] | | | | [removed: $2,589.3] [added: $2,689.0] | | | | [removed: $2,635.8] [added: $2,589.3] | |
| Gas | [removed: 464.8] [added: 517.5] | | | | [removed: 396.3] [added: 464.8] | | | | [removed: 476.7] [added: 396.3] | | |
| Other | [removed: 71.3] [added: 66.1] | | | | [removed: 56.7] [added: 71.3] | | | | [removed: 62.0] [added: 56.7] | | |
| Non-regulated | [removed: 51.7] [added: 53.1] | | | | [removed: 52.2] [added: 51.7] | | | | [removed: 46.9] [added: 52.2] | | |
| Total operating revenues | [removed: 3,276.8] [added: 3,350.3] | | | | [removed: 3,094.5] [added: 3,276.8] | | | | [removed: 3,221.4] [added: 3,094.5] | | |
| Electric production fuel and energy purchases | [removed: 725.0] [added: 852.1] | | | | [removed: 712.3] [added: 725.0] | | | | [removed: 764.5] [added: 712.3] | | |
| Purchased electric capacity | [removed: 216.8] [added: 25.1] | | | | [removed: 271.5] [added: 216.8] | | | | [removed: 257.2] [added: 271.5] | | |
| Electric transmission service | [removed: 418.3] [added: 447.5] | | | | [removed: 341.3] [added: 418.3] | | | | [removed: 323.8] [added: 341.3] | | |
| Cost of gas sold | [removed: 276.7] [added: 327.8] | | | | [removed: 217.2] [added: 276.7] | | | | [removed: 295.2] [added: 217.2] | | |
| Other operation and maintenance | [removed: 620.7] [added: 658.3] | | | | [removed: 590.0] [added: 620.7] | | | | [removed: 630.2] [added: 590.0] | | |
| Non-regulated operation and maintenance | [removed: 14.9] [added: 6.7] | | | | [removed: 11.9] [added: 14.9] | | | | [removed: 18.0] [added: 11.9] | | |
| Depreciation and amortization | [removed: 370.9] [added: 388.1] | | | | [removed: 332.4] [added: 370.9] | | | | [removed: 321.0] [added: 332.4] | | |
| Taxes other than income taxes | [removed: 99.6] [added: 101.1] | | | | [removed: 98.2] [added: 99.6] | | | | 98.2 | | |
| Total operating expenses | [removed: 2,742.9] [added: 2,806.7] | | | | [removed: 2,574.8] [added: 2,742.9] | | | | [removed: 2,708.1] [added: 2,574.8] | | |
| Operating income | [removed: 533.9] [added: 543.6] | | | | [removed: 519.7] [added: 533.9] | | | | [removed: 513.3] [added: 519.7] | | |
| Interest expense | [removed: 172.8] [added: 180.6] | | | | [removed: 156.7] [added: 172.8] | | | | [removed: 158.3] [added: 156.7] | | |
| Equity income from unconsolidated investments, net | [removed: (43.7] [added: (40.4] | | ) | | [removed: (41.3] [added: (43.7] | | ) | | [removed: (39.3] [added: (41.3] | | ) |
| Allowance for funds used during construction | [removed: (30.8] [added: (34.8] | | ) | | [removed: (21.9] [added: (30.8] | | ) | | [removed: (12.0] [added: (21.9] | | ) |
| Interest income and other | [removed: (0.4] [added: (1.8] | | ) | | [removed: (4.0] [added: (0.4] | | ) | | [removed: (4.3] [added: (4.0] | | ) |
| Total interest expense and other | [removed: 97.9] [added: 103.6] | | | | [removed: 89.5] [added: 97.9] | | | | [removed: 102.7] [added: 89.5] | | |
| Income from continuing operations before income taxes | [removed: 436.0] [added: 440.0] | | | | [removed: 430.2] [added: 436.0] | | | | [removed: 410.6] [added: 430.2] | | |
| Income taxes | [removed: 53.9] [added: 44.3] | | | | [removed: 89.4] [added: 53.9] | | | | [removed: 69.2] [added: 89.4] | | |
| Income from continuing operations, net of tax | [removed: 382.1] [added: 395.7] | | | | [removed: 340.8] [added: 382.1] | | | | [removed: 341.4] [added: 340.8] | | |
| Loss from discontinued operations, net of tax | [removed: (5.9] [added: (2.4] | | ) | | [removed: (5.1] [added: (5.9] | | ) | | [removed: (19.5] [added: (5.1] | | ) |
| Net income | [removed: 376.2] [added: 393.3] | | | | [removed: 335.7] [added: 376.2] | | | | [removed: 321.9] [added: 335.7] | | |
| Preferred dividend requirements of subsidiaries | [removed: 17.9] [added: 10.2] | | | | [removed: 15.9] [added: 17.9] | | | | [removed: 18.3] [added: 15.9] | | |
| Net income attributable to Alliant Energy common shareowners | | [removed: $358.3] [added: $383.1] | | | | [removed: $319.8] [added: $358.3] | | | | [removed: $303.6] [added: $319.8] | |
February 24, 2015
February 24, 2015
February 24, 2015
| | 2014 | | | | 2013 | | |
| Other | 116.9 | | | | 125.7 | | |
| | 2014 | | | | 2013 | | |
| Other | 262.4 | | | | 233.8 | | |
| Total other liabilities | 3,624.0 | | | | 3,218.1 | | |
| Equity: | | | | | | | |
| Other | 2.0 | | | | (3.7 | | ) | | 0.7 | | |
| Other | (14.9 | | ) | | (18.8 | | ) | | 2.6 | | |
| Payments to retire long-term debt | (358.5 | | ) | | (1.5 | | ) | | (1.4 | | ) |
| Other | (7.1 | | ) | | (17.4 | | ) | | (8.9 | | ) |
| Beginning balance | $1.1 | | | | | $1,510.8 | | | | $1,510.2 | | | | ($0.8 | ) | | | ($8.3 | ) | | | $3,013.0 | |
| Ending balance | | $1.1 | | | | $1,509.1 | | | | $1,938.0 | | | | ($0.6 | ) | | | ($8.9 | ) | | | $3,438.7 | |
February 24, 2015
February 24, 2015
| | 2014 | | | | 2013 | | |
| | 2014 | | | | 2013 | | |
| Total other liabilities | 2,123.1 | | | | 1,882.0 | | |
| Equity: | | | | | | | |
| Other | 11.3 | | | | (0.7 | | ) | | 10.6 | | |
| Payments to retire long-term debt | (38.4 | | ) | | — | | | | — | | |
| Beginning balance | | $33.4 | | | | $927.7 | | | | $433.3 | | | | $1,394.4 | |
| Ending balance | | $33.4 | | | | $1,242.8 | | | | $537.9 | | | | $1,814.1 | |
February 24, 2015
February 24, 2015
| Net income attributable to noncontrolling interest | 0.7 | | | | — | | | | — | | |
| | 2014 | | | | 2013 | | |
| Cash and cash equivalents | | $46.7 | | | | $0.5 | |
| | 2014 | | | | 2013 | | |
| Other | 46.6 | | | | 38.3 | | |
| Other liabilities: | | | | | | | |
| Total other liabilities | 1,562.3 | | | | 1,386.9 | | |
| Equity: | | | | | | | |
| Noncontrolling interest | 8.5 | | | | — | | |
| Total equity | 1,712.3 | | | | 1,642.4 | | |
| Other | (1.2 | | ) | | (0.2 | | ) | | (2.9 | | ) |
| Other | (6.9 | | ) | | 10.2 | | | | (22.1 | | ) |
| Other | (7.2 | | ) | | (4.5 | | ) | | 7.8 | | |
| Gas plant | 909.9 | | | | 878.4 | | |
| Other plant | 547.9 | | | | 506.2 | | |
| Accumulated depreciation (accum. depr.) | (3,726.2 | | ) | | (3,513.0 | | ) |
| Net plant | 7,147.3 | | | | 6,942.3 | | |
| Construction work in progress: | | | | | | | |
| Columbia Energy Center Units 1 and 2 emission controls (WPL) | 265.0 | | | | 130.4 | | |
| Ottumwa Generating Station Unit 1 emission controls (IPL) | 135.1 | | | | 73.7 | | |
| George Neal Generating Station Unit 3 emission controls (IPL) | 54.6 | | | | 26.5 | | |
| Other | 223.2 | | | | 188.2 | | |
| Other, less accum. depr. of $5.6 for both periods | 22.3 | | | | 21.2 | | |
| Total utility | 7,847.5 | | | | 7,382.3 | | |
| Non-regulated Generation, less accum. depr. of $40.0 and $31.0 | 249.4 | | | | 258.6 | | |
| Alliant Energy Corporate Services, Inc. and other, less accum. depr. of $214.2 and $200.2 | 229.6 | | | | 197.1 | | |
| Customer | 81.8 | | | | 94.9 | | |
| Other | 299.2 | | | | 209.4 | | |
| Other | 84.9 | | | | 89.4 | | |
| Capitalization: | | | | | | | |
| Cumulative preferred stock of Wisconsin Power and Light Company | — | | | | 60.0 | | |
| Total capitalization | 6,461.0 | | | | 6,478.4 | | |
| Accrued taxes | 50.0 | | | | 48.0 | | |
| Accrued interest | 50.7 | | | | 48.0 | | |
| Other | 133.1 | | | | 176.0 | | |
| Other long-term liabilities and deferred credits: | | | | | | | |
| Total long-term liabilities and deferred credits | 3,218.1 | | | | 3,287.1 | | |
| Non-cash valuation charges and other | (3.7 | | ) | | 0.7 | | | | 20.3 | | |
| Collections of advances for customer energy efficiency projects | 16.6 | | | | 22.9 | | | | 31.0 | | |
| Other | (35.4 | | ) | | (20.3 | | ) | | (9.7 | | ) |
| Other | (18.9 | | ) | | (10.3 | | ) | | (9.4 | | ) |
| 2011: | | | | | | | | | | | | | | | | | | | | | | | |
| Beginning balance | $1.1 | | | | | $1,506.8 | | | | $1,394.7 | | | | ($1.4 | ) | | | ($7.6 | ) | | | $2,893.6 | |
| Other | | | | | 4.0 | | | | | | | | | | | | (0.7 | | ) | | 3.3 | | |
| Ending balance | 1.1 | | | | 1,510.8 | | | | 1,510.2 | | | | (0.8 | | ) | | (8.3 | | ) | | 3,013.0 | | |
February 25, 2014
February 25, 2014
| Electric plant | | $5,034.9 | | | | $4,815.2 | |
| Gas plant | 456.8 | | | | 441.4 | | |
| Steam and other plant | 302.8 | | | | 289.1 | | |
| Accumulated depreciation | (2,025.3 | | ) | | (1,930.7 | | ) |
| Net plant | 3,769.2 | | | | 3,615.0 | | |
| Construction work in progress: | | | | | | | |
An excerpt. Shown here: 40 of 1,383 rewritten, 40 of 469 added and 40 of 570 removed. The counts are complete. For every sentence, read Item 8. FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA in the FY2014 filing and the FY2013 filing.
Item 9A. CONTROLS AND PROCEDURES
4 rewritten, 0 added, 0 removed, 0 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Alliant Energy’s, IPL’s and WPL’s management evaluated, with the participation of each of Alliant Energy’s, IPL’s and WPL’s CEO, CFO and Disclosure Committee, the effectiveness of the design and operation of Alliant Energy’s, IPL’s and WPL’s disclosure controls and procedures as of the end of the quarter ended December 31, [removed: 2013] [added: 2014] pursuant to the requirements of the Securities Exchange Act of 1934, as amended.
Based on their evaluation, the CEO and the CFO concluded that Alliant Energy’s, IPL’s and WPL’s disclosure controls and procedures were effective as of the end of the quarter ended December 31, [removed: 2013.][added: 2014.]
The information required by Item 9A relating to “Management’s Annual Report on Internal Control over Financial Reporting” and, with respect to Alliant Energy, “Report of Independent Registered Public Accounting Firm,” is incorporated herein by reference to the relevant information in [Item [removed: 8](#s9817C8F3C608E919A2AEF8B9E1BB8ABF)] [added: 8](#sB47AC4C8A418965286766ABA7CE32D72)] Financial Statements and Supplementary Data.
There was no change in Alliant Energy’s, IPL’s and WPL’s internal control over financial reporting that occurred during the quarter ended December 31, [removed: 2013] [added: 2014] that has materially affected, or is reasonably likely to materially affect, Alliant Energy’s, IPL’s or WPL’s internal control over financial reporting.
Item 10. DIRECTORS, EXECUTIVE OFFICERS AND CORPORATE GOVERNANCE
4 rewritten, 0 added, 0 removed, 2 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
The information required by Item 10 relating to directors and nominees for election of directors at the [removed: 2014] [added: 2015] Annual Meeting of Shareowners is incorporated herein by reference to the relevant information under the caption “Election of Directors” in the [removed: 2014] [added: 2015] Alliant Energy Proxy Statement, which will be filed with the SEC within 120 days after the end of Alliant Energy’s, IPL’s and WPL’s fiscal years.
The information required by Item 10 relating to the timely filing of reports under Section 16 of the Securities Exchange Act of 1934 is incorporated herein by reference to the relevant information under the caption “Section 16(a) Beneficial Ownership Reporting Compliance” in the [removed: 2014] [added: 2015] Alliant Energy Proxy Statement.
Information regarding executive officers of Alliant Energy, IPL and WPL may be found in Part I of this report under the caption “[Executive Officers of the [removed: Registrants](#s245FC04BD0E9D5704487F8B9DE037E68).”] [added: Registrants](#s4B2D5A37A900B1025FB96ABA792EDD79).”] The information required by Item 10 relating to audit committees and audit committee financial experts is incorporated herein by reference to the relevant information under the caption “Meetings and Committees of the Board” in the [removed: 2014] [added: 2015] Alliant Energy Proxy Statement.
The information required by Item 10 relating to Alliant Energy’s, IPL’s and WPL’s Code of Conduct is incorporated herein by reference to the relevant information under the caption “Corporate Governance” in the [removed: 2014] [added: 2015] Alliant Energy Proxy Statement.
Item 11. EXECUTIVE COMPENSATION
1 rewritten, 0 added, 0 removed, 1 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Therefore, the information required by Item 11 for each of Alliant Energy, IPL and WPL is incorporated herein by reference to the relevant information under the captions “Compensation Discussion and Analysis,” “Compensation and Personnel Committee Report,” “Summary Compensation Table,” “Grants of Plan-Based Awards,” “Outstanding Equity Awards at Fiscal Year-End,” “Option Exercises and Stock Vested,” “Pension Benefits,” “Nonqualified Deferred Compensation,” “Potential Payments Upon Termination or Change in Control” and “Director Compensation” in the [removed: 2014] [added: 2015] Alliant Energy Proxy Statement, which will be filed with the SEC within 120 days after the end of Alliant Energy’s, IPL’s and WPL’s fiscal years.
Item 12. SECURITY OWNERSHIP OF CERTAIN BENEFICIAL OWNERS AND MANAGEMENT AND RELATED STOCKHOLDER MATTERS
6 rewritten, 2 added, 2 removed, 10 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
Information regarding Alliant Energy’s equity compensation plans as of December 31, [removed: 2013] [added: 2014] was as follows:
| (a) | Represents performance shares granted under the OIP. The performance shares may be paid out in shares of Alliant Energy’s common stock, cash, or a combination of cash and stock and are adjusted by a performance multiplier, which ranges from zero to 200%, based on the performance criteria. The performance shares included in column (A) of the table reflect an assumed payout in the form of Alliant Energy’s common stock at the maximum performance multiplier of 200% for the [removed: 2013] [added: 2014] and [removed: 2012] [added: 2013] grants and at the actual performance multiplier of [removed: 148%] [added: 168%] for the [removed: 2011] [added: 2012] grants. |
| (b) | All of the available shares under the OIP may be issued as awards in the form of restricted stock, restricted stock units, performance shares, performance units and other stock-based awards. As of December 31, [removed: 2013,] [added: 2014,] there were performance shares and restricted stock awards outstanding under the OIP. Excludes [removed: 160,589] [added: 98,812] shares of non-vested restricted common stock previously issued and outstanding under the OIP at December 31, [removed: 2013.] [added: 2014.] |
| (c) | As of December 31, [removed: 2013,] [added: 2014,] there were [removed: 227,469] [added: 238,935] shares of Alliant Energy’s common stock outstanding under the DCP, which is described in [Note [removed: 12(c)](#s896DCE7ED55AD01F4592F8B9B3E8D31B) of the “Combined Notes to Consolidated Financial Statements.”] [added: 12(c)](#sC68ED85142298F24DC9A6ABA3801C146).] |
The remainder of the information required by Item 12 is incorporated herein by reference to the relevant information under the caption “Ownership of Voting Securities” in the [removed: 2014] [added: 2015] Alliant Energy Proxy Statement, which will be filed with the SEC within 120 days after the end of Alliant Energy’s fiscal year.
The remainder of the information required by Item 12 is incorporated herein by reference to the relevant information under the caption “Ownership of Voting Securities” in the [removed: 2014] [added: 2015] Alliant Energy Proxy Statement, which will be filed with the SEC within 120 days after the end of IPL’s and WPL’s fiscal years.
| Equity compensation plans approved by shareowners | | 274,024 (a) | | | $48.56 | | 3,949,771 (b) |
| | | 274,024 | | | $48.56 | | 3,949,771 |
| Equity compensation plans approved by shareowners | | 256,132 (a) | | | $43.67 | | 4,056,198 (b) |
| | | 256,132 | | | $43.67 | | 4,056,198 |
Item 13. CERTAIN RELATIONSHIPS AND RELATED TRANSACTIONS, AND DIRECTOR INDEPENDENCE
1 rewritten, 0 added, 0 removed, 0 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
The information required by Item 13 for each of Alliant Energy, IPL and WPL is incorporated herein by reference to the relevant information under the caption “Corporate Governance” in the [removed: 2014] [added: 2015] Alliant Energy Proxy Statement, which will be filed with the SEC within 120 days after the end of Alliant Energy’s, IPL’s and WPL’s fiscal years.
Item 14. PRINCIPAL ACCOUNTING FEES AND SERVICES
10 rewritten, 1 added, 1 removed, 12 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
The information required by Item 14 is incorporated herein by reference to the relevant information under the caption [removed: “Report of the Audit Committee”] [added: “Fees Paid to Independent Registered Public Accounting Firm”] in the [removed: 2014] [added: 2015] Alliant Energy Proxy Statement, which will be filed with the SEC within 120 days after the end of Alliant Energy’s fiscal year.
| Audit fees | | [removed: $1,011] [added: $1,037] | | | 91 | % | | | [removed: $824] [added: $1,011] | | | 91 | % | | | [removed: $888] [added: $1,042] | | | [removed: 92] [added: 96] | % | | | [removed: $898] [added: $888] | | | [removed: 87] [added: 92] | % |
| Audit-related fees | [removed: 81] [added: 88] | | | | [removed: 7] [added: 8] | % | | [removed: 75] [added: 81] | | | | [removed: 8] [added: 7] | % | | [removed: 57] [added: 38] | | | | [removed: 6] [added: 3] | % | | [removed: 135] [added: 57] | | | | [removed: 13] [added: 6] | % |
| Tax fees | [removed: 14] [added: —] | | | | [removed: 1] [added: —] | % | | [removed: —] [added: 14] | | | | [removed: —] [added: 1] | % | | [removed: 11] [added: —] | | | | [removed: 1] [added: —] | % | | [removed: —] [added: 11] | | | | [removed: —] [added: 1] | % |
| All other fees | [removed: 5] [added: 9] | | | | 1 | % | | 5 | | | | 1 | % | | [removed: 5] [added: 9] | | | | 1 | % | | [removed: 4] [added: 5] | | | | [removed: —] [added: 1] | % |
| | | [removed: $1,111] [added: $1,134] | | | 100 | % | | | [removed: $904] [added: $1,111] | | | 100 | % | | | [removed: $961] [added: $1,089] | | | 100 | % | | | [removed: $1,037] [added: $961] | | | 100 | % |
IPL’s and WPL’s audit fees for [removed: 2013] [added: 2014] and [removed: 2012] [added: 2013] consisted of the respective fees billed for the audits of the [removed: consolidated] financial statements of IPL and its subsidiary and WPL and its subsidiary, for reviews of financial statements included in Form 10-Q filings, and for services normally provided in connection with statutory and regulatory filings, such as financing transactions.
IPL’s and WPL’s audit fees also included their respective portion of fees for the [removed: 2013] [added: 2014] and [removed: 2012] [added: 2013] audits of Alliant Energy’s [removed: consolidated] financial statements and effectiveness of internal controls over financial reporting.
IPL’s and WPL’s audit-related fees for [removed: 2013] [added: 2014] and [removed: 2012] [added: 2013] consisted of the fees billed for services rendered related to employee benefits plan audits and attest services not required by statute or regulations.
All other fees for [removed: 2013] [added: 2014] and [removed: 2012] [added: 2013] for IPL and WPL consisted of license fees for accounting research software products and seminars.
| | 2014 | | | | | | | 2013 | | | | | | | 2014 | | | | | | | 2013 | | | | | |
| | 2013 | | | | | | | 2012 | | | | | | | 2013 | | | | | | | 2012 | | | | | |
Item 15. EXHIBITS, FINANCIAL STATEMENT SCHEDULES
115 rewritten, 26 added, 35 removed, 181 unchanged
Read the full itemFY2014 item · filed February 25, 2015FY2013 item · filed February 25, 2014
| (1) | Consolidated Financial Statements - Refer to [Item [removed: 8](#s9817C8F3C608E919A2AEF8B9E1BB8ABF)] [added: 8](#sB47AC4C8A418965286766ABA7CE32D72)] Financial Statements and Supplementary Data. |
NOTE: All other schedules are omitted because they are not applicable or not required, or because that required information is shown either in the [removed: consolidated] financial statements or in the notes thereto.
| (3) | Exhibits Required by SEC Regulation S-K - Exhibits for Alliant Energy, IPL and WPL are listed in the [Exhibit [removed: Index](#s6432FD549985D20A51CEF8B9F677833F),] [added: Index](#s7C4B3506FC93935B96AA6ABA915A6786),] which is incorporated herein by reference. |
| | [removed: 2013] [added: 2014] | | | | [removed: 2012] [added: 2013] | | | | [removed: 2011] [added: 2012] | | |
| Operating revenues | | $2 | | | | $2 | | | | [removed: $4] [added: $2] | |
| Operating expenses | [removed: 1] [added: 3] | | | | 1 | | | | 1 | | |
| Operating income [added: (loss)] | [removed: 1] [added: (1] | | [added: )] | | 1 | | | | [removed: 3] [added: 1] | | |
| Equity earnings from consolidated subsidiaries | [removed: (362] [added: (387] | | ) | | [removed: (322] [added: (362] | | ) | | [removed: (304] [added: (322] | | ) |
| Interest expense | [removed: 11] [added: 9] | | | | 11 | | | | 11 | | |
| Interest income | (2 | | ) | | [removed: (4] [added: (2] | | ) | | [removed: (2] [added: (4] | | ) |
| Total interest expense and other | [removed: (353] [added: (380] | | ) | | [removed: (315] [added: (353] | | ) | | [removed: (295] [added: (315] | | ) |
| Income before income taxes | [removed: 354] [added: 379] | | | | [removed: 316] [added: 354] | | | | [removed: 298] [added: 316] | | |
| Income tax benefit | (4 | | ) | | (4 | | ) | | [removed: (5] [added: (4] | | ) |
| Net income | | [removed: $358] [added: $383] | | | | [removed: $320] [added: $358] | | | | [removed: $303] [added: $320] | |
| | [added: 2014 | | | |] 2013 | | | | 2012 | | |
| Notes receivable from affiliated companies | | [removed: $72] [added: $95] | | | | [removed: $77] [added: $72] | |
| Other | [removed: 3] [added: 4] | | | | [removed: 2] [added: 3] | | |
| Investments in consolidated subsidiaries | [removed: 3,585] [added: 3,753] | | | | [removed: 3,447] [added: 3,585] | | |
| Other | [removed: 14] [added: 15] | | | | [removed: 20] [added: 14] | | |
| Other assets | [removed: 6] [added: 10] | | | | [removed: 5] [added: 6] | | |
| Total assets | | [removed: $3,680] [added: $3,877] | | | | [removed: $3,551] [added: $3,680] | |
| [removed: CAPITALIZATION AND] LIABILITIES [added: AND EQUITY] | | | | | | | |
| Common stock and additional paid-in capital | [added: 1,510] | [removed: $1,509] | | | [added: 1,509] | [removed: $1,512] | |
| Retained earnings | [removed: 1,777] [added: 1,934] | | | | [removed: 1,627] [added: 1,777] | | |
| Shares in deferred compensation trust | [removed: (8] [added: (9] | | ) | | [removed: (7] [added: (8] | | ) |
| [removed: Total common equity] [added: Common equity:] | [removed: 3,278] | | | | [removed: 3,131] | | |
| Long-term debt, net | [removed: —] [added: 250] | | | | [removed: 250] [added: —] | | |
| Current maturities of long-term debt | [removed: 250] | [added: $—] | | | [removed: —] | [added: $250] | |
| Commercial paper | [removed: 96] [added: 141] | | | | [removed: 105] [added: 96] | | |
| Other | [removed: 10] [added: 29] | | | | [removed: 21] [added: 10] | | |
| Deferred income taxes | [removed: 39] [added: 11] | | | | [removed: 38] [added: 39] | | |
| Other | [removed: 7] [added: 11] | | | | [removed: 6] [added: 7] | | |
| Total [removed: capitalization and] liabilities [added: and equity] | | [removed: $3,680] [added: $3,877] | | | | [removed: $3,551] [added: $3,680] | |
| Net cash flows from operating activities | | [removed: $238] [added: $246] | | | | [removed: $260] [added: $238] | | | | [removed: $193] [added: $260] | |
| Capital contributions to consolidated subsidiaries | [removed: (120] [added: (90] | | ) | | [removed: (230] [added: (120] | | ) | | [removed: (144] [added: (230] | | ) |
| Capital repayments from consolidated subsidiaries | [removed: 95] [added: 50] | | | | [removed: —] [added: 95] | | | | [removed: 101] [added: —] | | |
| Net change in notes receivable from affiliates | [removed: 5] [added: (23] | | [added: )] | | [removed: 134] [added: 5] | | | | [removed: —] [added: 134] | | |
| Other | [removed: (2] [added: —] | | [removed: )] | | [removed: 1] [added: (2] | | [added: )] | | [removed: —] [added: 1] | | |
| Net cash flows used for investing activities | [removed: (22] [added: (63] | | ) | | [removed: (95] [added: (22] | | ) | | [removed: (43] [added: (95] | | ) |
| Common stock dividends | [removed: (208] [added: (226] | | ) | | [removed: (199] [added: (208] | | ) | | [removed: (188] [added: (199] | | ) |
[Schedule I](#sA52E9ED77160B346A1CD6ABA36724993).
[Schedule II](#sA666921C964E40C2F39F6ABA35533DE1).
| | 2014 | | | | 2013 | | |
| | 99 | | | | 75 | | |
| | 3,768 | | | | 3,599 | | |
| | 2014 | | | | 2013 | | |
| | 170 | | | | 356 | | |
| Other liabilities: | | | | | | | |
| | 22 | | | | 46 | | |
| | 3,435 | | | | 3,278 | | |
| Proceeds from issuance of long-term debt | 250 | | | | — | | | | — | | |
| Payments to retire long-term debt | (250 | | ) | | — | | | | — | | |
| | | | Year ended December 31, 2014 | | $4.8 | | | $11.7 | | | $4.1 | | | $15.5 | | | $5.1 | |
| | | | Year ended December 31, 2013 | 4.0 | | | 13.6 | | | 0.6 | | | 13.4 | | | 4.8 | | |
| | | | Year ended December 31, 2014 | | $0.7 | | | $11.5 | | | $— | | | $11.8 | | | $0.4 | |
| | | | Year ended December 31, 2014 | | $1.7 | | | $— | | | $4.1 | | | $1.6 | | | $4.2 | |
| | | | Year ended December 31, 2014 | | $38.2 | | | $12.5 | | | $— | | | $18.1 | | | $32.6 | |
| | | | Year ended December 31, 2013 | 33.4 | | | 23.2 | | | — | | | 18.4 | | | 38.2 | | |
| | | | Year ended December 31, 2014 | | $18.1 | | | $3.9 | | | $— | | | $11.4 | | | $10.6 | |
| | | | Year ended December 31, 2013 | 11.6 | | | 9.3 | | | — | | | 2.8 | | | 18.1 | | |
| | | | Year ended December 31, 2014 | | $16.2 | | | $2.5 | | | $— | | | $2.4 | | | $16.3 | |
| | | | Year ended December 31, 2013 | 13.5 | | | 8.8 | | | — | | | 6.1 | | | 16.2 | | |
| 10.2 | | Term Loan Credit Agreement, dated as of October 7, 2014, between Alliant Energy, Wells Fargo Bank, N.A. and the lender parties set forth therein (incorporated by reference to Exhibit 10.1 to Alliant Energy’s Form 8-K, filed October 14, 2014 (File No. 1-9894)) |
| 10.3c# | | Form of Performance Share Agreement amended in 2015, pursuant to the OIP, amended in 2012 |
| 10.3e# | | Form of Performance Contingent Restricted Stock Agreement amended in 2015, pursuant to the OIP, amended in 2012 |
| 10.16# | | Terms of Alliant Energy Management Performance Pay Plan |
[Schedule I](#s9CC45B947DA64136BD23F8B9BA5FB4D4).
[Schedule II](#s6D8ECE2F67F9B6A76CF0F8B9BAD87BBD).
| | 75 | | | | 79 | | |
| | 3,599 | | | | 3,467 | | |
| | 2013 | | | | 2012 | | |
| Capitalization: | | | | | | | |
| Accumulated other comprehensive loss | — | | | | (1 | | ) |
| | 3,278 | | | | 3,381 | | |
| | 356 | | | | 126 | | |
| Other long-term liabilities and deferred credits: | | | | | | | |
| | 46 | | | | 44 | | |
| | 2013 | | | | 2012 | | | | 2011 | | |
| Net change in borrowings with affiliates | — | | | | — | | | | (155 | | ) |
| | | | Year ended December 31, 2013 | | $4.0 | | | $13.6 | | | $0.6 | | | $13.4 | | | $4.8 | |
| | | | Year ended December 31, 2011 | 3.2 | | | 7.8 | | | 1.9 | | | 8.7 | | | 4.2 | | |
| | | | Year ended December 31, 2011 | 0.4 | | | 7.4 | | | — | | | 6.9 | | | 0.9 | | |
| | | | Year ended December 31, 2013 | | $1.8 | | | $— | | | $0.6 | | | $0.7 | | | $1.7 | |
| | | | Year ended December 31, 2013 | | $33.4 | | | $23.2 | | | $— | | | $18.4 | | | $38.2 | |
| | | | Year ended December 31, 2011 | 24.0 | | | 8.8 | | | — | | | 6.9 | | | 25.9 | | |
| | | | Year ended December 31, 2013 | | $11.6 | | | $9.3 | | | $— | | | $2.8 | | | $18.1 | |
| | | | Year ended December 31, 2011 | 8.8 | | | 3.6 | | | — | | | 2.2 | | | 10.2 | | |
| | | | Year ended December 31, 2013 | | $13.5 | | | $8.8 | | | $— | | | $6.1 | | | $16.2 | |
| | | | Year ended December 31, 2011 | 12.8 | | | 3.7 | | | — | | | 4.8 | | | 11.7 | | |
| /s/ | David A. Perdue | | Director |
| | David A. Perdue | | |
| /s/ | David A. Perdue | | Director |
| | David A. Perdue | | |
| /s/ | David A. Perdue | | Director |
| | David A. Perdue | | |
For the fiscal year ended December 31, 2013
| 10.3d# | | Form of Restricted Cash Agreement pursuant to the DLIP, amended in 2012 (incorporated by reference to Exhibit 10.5d to Alliant Energy’s Form 10-K for the year 2011 (File No. 1-9894)) |
| 10.3e# | | Form of Performance Restricted Award Agreement pursuant to the DLIP, amended in 2012 (incorporated by reference to Exhibit 10.5e to Alliant Energy’s Form 10-K for the year 2011 (File No. 1-9894)) |
| 10.5# | | Alliant Energy Rabbi Trust Agreement for DCPs (incorporated by reference to Exhibit 10.19 to Alliant Energy’s Form 10-K for the year 2005 (File No. 1-9894)) |
| 10.12# | | Executive Severance Benefit under the Alliant Energy Severance Plan Summary Plan Description, effective March 19, 2008 (incorporated by reference to Exhibit 10.1 to Alliant Energy’s Form 8-K, dated March 19, 2008 (File No. 1-9894)) |
| 10.12a# | | Amendment to the Executive Severance Benefit under the Alliant Energy Severance Plan Summary Plan Description (incorporated by reference to Exhibit 10.5 to Alliant Energy’s Form 8-K, dated December 1, 2011 (File No. 1-9894)) |
An excerpt. Shown here: 40 of 115 rewritten, all 26 added and all 35 removed. The counts are complete. For every sentence, read Item 15. EXHIBITS, FINANCIAL STATEMENT SCHEDULES in the FY2014 filing and the FY2013 filing.